Marine Corps Firing Range and Historic 4S Outfall Project Update Mare Island Restoration Advisory Board Meeting October 27, 2005 PowerPoint PPT Presentation


  • 84 Views
  • Uploaded on
  • Presentation posted in: General

Marine Corps Firing Range and Historic 4S Outfall Project Update Mare Island Restoration Advisory Board Meeting October 27, 2005. Firing Range Excavated Grids. Firing Range Soil Excavation. Historic 4S Outfall Boundary. 4S Outfall Excavation. 4S Outfall Soil Screen Plant.

Download Presentation

Marine Corps Firing Range and Historic 4S Outfall Project Update Mare Island Restoration Advisory Board Meeting October 27, 2005

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Slide1 l.jpg

Marine Corps Firing Range andHistoric 4S OutfallProject UpdateMare IslandRestoration Advisory Board MeetingOctober 27, 2005


Firing range excavated grids l.jpg

Firing Range Excavated Grids


Firing range soil excavation l.jpg

Firing Range Soil Excavation


Historic 4s outfall boundary l.jpg

Historic 4S Outfall Boundary


4s outfall excavation l.jpg

4S Outfall Excavation


4s outfall soil screen plant l.jpg

4S Outfall Soil Screen Plant


Excavated soil post screening survey l.jpg

Excavated Soil Post-Screening Survey


Firing range 4s outfall soil sampling l.jpg

Firing Range/4S Outfall Soil Sampling

  • Excavated soil analyzed for leachable lead levels

    • Deionized Water Waste Extraction Test (DI WET)

    • Analysis results:

      • Firing Range - ND (< 0.003 mg/L) to 0.077 mg/L

      • 4S Outfall - ND (< 0.003 mg/L) to 0.020 mg/L

    • Acceptance criteria is 5.0 mg/L


Soil placement in ia h1 l.jpg

Soil Placement in IA H1

Haul Route along 4M/4N Pond Levee

30-40 trips per day

Total volume placed = 64,246 cy

  • Firing Range: 32,644 cy

  • 4S Outfall: 31,602 cy


4s outfall soil excavation summary l.jpg

4S Outfall Soil Excavation Summary


Recovered metal scrap l.jpg

Recovered Metal Scrap

184,450 lbs of (non-MEC) metal scrap recycled


Summary of recovered munitions l.jpg

Summary of Recovered Munitions


Examples of recovered mec l.jpg

Examples of Recovered MEC

MK18 Time Fuze

MK2 Hand Grenade

40mm, 20mm, 7.2” Rocket Fuze

1.1 inch Projectile


Rad screening and recovered items l.jpg

RAD Screening and Recovered Items

Recovered RAD Items

Radiological Survey


Recovered outfall masses lennar eastern early transfer parcel l.jpg

Recovered Outfall Masses – Lennar Eastern Early Transfer Parcel


Slide16 l.jpg

Additional Outfall Mass Location


Project status l.jpg

Project Status

  • Complete soil excavation/screening - 10/28/05

  • Complete soil transport to IA H1 – 11/04/05

  • Perform geophysical confirmation survey – 11/7/05

  • Lennar outfall mass disassembly – 11/11/05

  • MEC Treatment Range Operation –> Nov-Dec 05