1 / 21

The Construction Process

The Construction Process. Construction Process Integration. Example Construction Site. Construction Process. Zoning Issues Governmental requirements for permits, etc. Planning & Design Project Bidding / Tender / Take-off Material, Labor, and Equipment Estimates Pricing and Submittal

jirair
Download Presentation

The Construction Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Construction Process

  2. Construction Process Integration

  3. Example Construction Site

  4. Construction Process • Zoning Issues • Governmental requirements for permits, etc. • Planning & Design • Project Bidding / Tender / Take-off • Material, Labor, and Equipment Estimates • Pricing and Submittal • Project Award • Project Start • Develop digital model of project for control, layout and 3D

  5. Construction Process • Establish Local Control (Cadastral) • Tie site to “legal” control. Preliminary building envelope, setbacks, Right of Ways, establish control points for the site. • Clearing & Grubbing Limits • Establish Area of Disturbance. Segregate environmentally sensitive areas. Identify what vegetation is to be removed. • Verify Existing Topo • Measure existing surface. Compare to original bid plan. Does it match? Are there grounds for additional claims? Volume Difference.

  6. Construction Process • Strip Topsoil • How much is there? How much do we need to put back? What is the actual amount? Monetary, efficiency and space issues. Volumes. • Bulk Earthwork • Cut/Fill Grid. Mass Haul Diagrams. Progress Reporting. Ongoing Volume Differences, Slope Staking, Cut/Fill Staking. • Sub Strata • Unsuitable Soils, Water, Rock. Model and quantities for payment. Volumes and Modeling.

  7. Construction Process • Underground Infrastructure • Storm Drains, Water, Sewers, Natural Gas, Power, Communications, Irrigation. Position, Depth, and Slope Sub Strata and Select Material Volumes. Position & Elevation. • Subgrade and Structural Materials • Subgrade elevations. Structural & Select Material elevations. Grade checking and Material Yields. • Critical Layout Control • Building Corners, Roadway tie-ins, Easements, Right of Ways. All control with “significant legal bearing.” High Accuracy Elevation & Position

  8. Construction Process • Foundation and Structural Surface Control • Footings, Foundations, Concrete Floors, Supporting Structures, Car Parks, Access Roads, Curb & Gutter, Hard Surface Canals, etc. Elevation, Position, Slopes, Offsets, and Material Yields • Superstructure (Building Proper) • Structural Layout - Columns, Anchor bolts, Elevator shafts • Interior Layout - All functional layout. (Walls, utility chases, etc.) • Hard Surface Placement • Roadway & Car Park paving. Hard surface placement. Elevation, Position, and As-built

  9. Construction Process • Topsoil Respread and Landscaping • Finish all unpaved areas for aesthetics and proper drainage. Elevation and Position. • As-Built and Close-out • Measure all finished surfaces and create model. Compare against design for payment and future GIS issues. Surface measurement and modeling.

  10. The Construction Process Using Trimble Grade Control Systems Presenters Name

  11. How do you use TrimbleMachine Control Systems in the Construction Process? A simple scenario to illustrate

  12. 1. Strip the topsoil • Guides the operator to the edge of strip • No stakes required Cost reduction • Reduces over strip Cost reduction • Not restricted to scrapers, use any machine • e.g. Dozer/Grader/Excavator/Scraper

  13. 2. Excavate unsuitable material • Guides the operator to the extents of excavation • No stakes required Cost reduction • Reduces over excavation Cost reduction • Not restricted to scrapers, use any machine • e.g. Dozer/Excavator/Scraper

  14. 3. Compact, validate in-situ material • Measure density using intelligent compaction • Look for soft spots Better to sort it out now than fix later • Record the surface • For volume calculations • Ensure that you get paid

  15. 4. Place a layer of imported material • System controls grade – guides the operator • Correct layer thickness Meets spec for compaction • As a result you get a smooth surface • Trucks travel faster Increase productivity • Water runs off if it rains Less downtime

  16. 5. Compact layer of imported material • Record the number of passes & measure density using intelligent compaction • Documentation Verify that you meet specifications • Look for soft spots Better to sort out now, than fix later • Record the surface • Calculate the volume Progress payments

  17. 6. Place the next layer of imported material • System controls grade – guides the operator • Reduces number of passes to grade, increases productivity • Ensures the correct layer thickness • Meets spec for compaction • Higher quality final product! • To grade with less time & effort

  18. 7. Compact the layer of imported material • Record the number of passes & measure density using intelligent compaction • Documentation Verify that you meet specifications • Record the final surface • Documentation that you have meet grade requirements • Calculate the volume Progress payment for imported material

  19. Summary • Integrated solutions for all machines • Reduces costs • Increases productivity • Reduces re-work • Provides QA/QC • Process Improvement • Provides value in all phases of the project • Stripping topsoil • Excavating unsuitable • Grading imported material • Compacting imported material

  20. Thank you

More Related