An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISQA 479 Customer Value Smart Pricing Expediting

  2. Customer Value • Timing and Lead Time • Location • Conformance to Specifications • Information/Visibility • Value Added Services • Product Selection • Price • Long Term Relationship

  3. Power Shift in Manufacturing • Contract Manufacturing • Electronics • Clothing • Auto Sub-assemblies • Jewelry • Food • Furniture • Pharmaceuticals

  4. Locations • Hi Tech/ Hi Quality or Cheap • Asia • China • India • Malaysia • Indonesia • Taiwan • Korea • Japan

  5. Locations • Central and South America • Brazil • Mexico • Maquiladoras • Central America and Caribbean • Africa • Kenya • South Africa

  6. Smart Pricing • Customer Differentiation • Timing • Price According to Demand • Airlines • Hotels • Rebates • Surcharges

  7. Smart Pricing • Differential Pricing • Group Pricing • Regional Pricing • Product Versions • Transportation Preferences • Seasonality • Freight and Handling

  8. Pricing and the Internet • Information Availability • Expanded Customer Base • Expanded Supply Base • Price • Service • Customer Ratings • Look Up • Alibaba.com • Thomasnet.com • Solusource.com

  9. Sourcing and Expediting

  10. Sourcing Objectives • Fundamental Objectives • Continuity of Supply • Quality • Minimize Administrative Costs

  11. Avoiding Problems • Complete Specifications • Minimize Change Orders • Order Timing • Order Outside Supplier Normal Lead Time • Minimize Rush Orders • Continuous Supplier Information Flow • In Both Directions • Supplier Visits

  12. Expediting Objectives • Avoid surprises • Receive Materials ON TIME • Manage supply base • Persuade supplier to do what was agreed • Solve problems • Supplier Problems • Industry Problems • Build supplier relationships • Understand supply chains

  13. Why Suppliers Fail • Inaccurate lead times • Impossible sales promises • Lead time changes • Supplier’s sources • Overmatched supplier • Errors • Undercapitalized • Logistics • Force Majeure

  14. Before you place an order • Salesperson’s home phone • Manager’s home phone • Other emergency numbers • List of carriers in immediate vicinity • Other useful information • Organization chart • Credit manager • Engineering manager • Production manager • Purchasing manager

  15. Before Placing an Order • Early Delivery Bonus? • Sliding Pay Scale • On Time = Full Pay • Late = Deductions • Agree on Transportation • Mode • Carrier • Agree on Force Majeure • Agree on Liquidated Damages

  16. After Placing an Order • Read contract documents carefully • Think before you act • BE NICE but firm • Authorize overtime • Partial shipment • Next closest dealer • Next closest major customer • Available in another form? • Hold all new orders to supplier pending resolution • Threats are ALWAYS a last resort

  17. Structural Steel:An Example • Engineering Specs • General Contract • Sub-Contract With Installer • Sub Orders Materials • Local Steel Supply Firm • Order From Supplier – Bao Steel Shanghai • Bao Steel • Hot Roll • Fabricate • Deliver to Dock

  18. Structural Steel, Cont. • Load on Ship (Schedule) • Transit Time • Discharge at Port • Customs • Arrange Local Trucking • Deliver to Jobsite • Erect

  19. Structural Steel • Finalize Engineering Specs & Drawings 6 • Award Contract to LCL 4 • Contract With Installer 4 • Installer Orders Materials 2 • Local Steel Supply Firm 2 • Order From Supplier – Bao Steel Shanghai • Bao Steel • Hot Roll 2-4 • Fabricate 1-2 • Deliver to Ship 1

  20. Structural Steel, Cont. • Load on Ship (Schedule) 1-2 • Transit Time 2-3 • Discharge at Port 1 • Customs 1-2 • Arrange Local Trucking 1 • Deliver to Jobsite 1 • Erect • Total Lead Time Could Be 6 Months

  21. Structural Steel, Cont. • Assume Contract w/ Erector • Assume Steel Supplier Has Raw Material • Still Need Fabrication Time, Transportation Time

  22. Expediting • Ask Subs – “Does your supplier have the materials IN STOCK?” • If YES, is the material set aside and earmarked for us? • If not in stock, what is the lead time and what process does sub have in place to be sure it gets ordered in time? • Don’t forget that transportation lead time needs to be included (Permits?)

  23. Expediting and Project Management • This ties back to the need for prompt submittals and A&E approvals. • Do A&E folks know what lead times are for materials? • A Materials Critical Path?

  24. Expediting • Backward Scheduling • Date needed on jobsite • Slack • Transportation time • Fabrication time • Materials lead time • A&E approvals • A&E submittals

  25. Expediting • Make a materials checklist that includes proactive checking on subs to be sure they and their suppliers have ordered material in time. • Ask Subs – “What is your Forecast (not guess) for availability of materials?” Why? • Lead times change depending on economic conditions. Verify periodically

  26. Questions, Comments, Observations, Conclusions, Arguments?