From Hardware Commissioning to Machine Check-out

From Hardware Commissioning to Machine Check-out. S Baird LHC HC review 11-13 May 2005. Questions…. How does HC leave a sector? Which cycles, to what energy…? Ready for beam? Late/repaired systems? What happens to a sector after HC and before beam

jael
Download Presentation

From Hardware Commissioning to Machine Check-out

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. From Hardware Commissioning to Machine Check-out S Baird LHC HC review 11-13 May 2005

  2. Questions…. • How does HC leave a sector? • Which cycles, to what energy…? • Ready for beam? • Late/repaired systems? • What happens to a sector after HC and before beam • Which systems will be maintained? By whom? • Who is responsible for coordinating interventions/repairs? • Re-testing/re-commissioning • What does OP expect? • Safety issues • Conclusions…

  3. How does HC leave a sector? • Sectors will be commissioned to nominal and no higher. I.e. 7 TeV • Maybe lower… If there is a weak magnet • After HC a sector is “ready for beam” • Sector run has been through all standard LHC operations • First 4 sectors will NOT be kept cold. They will “float” • Lack of resources (Cryo) • 400 kCHf/month to keep a sector at operating temperature • RF does not want to warm up point 4 after HC… • Do RF commissioning as late as possible??

  4. What happens after HC? • HC will not wait for late but non-essential equipment • E.g Collimators, BLM,s • Late installation done by specialists – coordinated by HC team • This may need support from vacuum, cryo… & others • Repairs • Done by specialists – coordinated by HC team • Again possible need support from vacuum, cryo… & others • Strong need for coordination with on-going installation & HC

  5. Vacuum & Cryo support • Cryo will have a small team to cover work in the already commissioned sectors • With at least one responsible person/point • Vacuum will also have people responsible for installed/commissioned sectors • Vacuum operation/maintenance will start before first beam • Two Vacuum teams (CERN staff), who will not be “fully loaded”, will be available for interventions on commissioned sectors • These teams will make all non-standard interventions • However, late installation and equipment changes should not be programmed in parallel with sector “re-commissioning”

  6. What happens after HC? • Need a solid co-ordination of all post-HC installation and repairs • Using same resources as HC • Restarting/re-testing all systems will also need solid co-ordination • But “HC circus can only perform at one pit at a time” • Restarting/re-testing looks like the end of a shutdown • Early role for a shutdown co-ordinator

  7. Sector re-commissioning • (Re)cool-down - main roles for Vacuum & Cryo • Vacuum need 2 weeks per octant before (re)cool-down can start • Vacuum only has resources for 1 octant at a time • Cryo need 6 weeks per octant for first (re)cool-down • Nominally 3 weeks but this is the “first time” • Cryo can work on octants in parallel • Therefore (re)cooling of 4 octants needs a minimum of 14 weeks • During last 4 months absolutely no vacuum work elsewhere (including injectors)

  8. Sector re-commissioning • Some systems may need a full re-commissioning if there have been changes or repairs • Safety systems, machine/magnet protection etc. • PIC, WIC, QPS etc. will need some sort retesting in any case • This re-commissioning will be part of the HC but it looks like a restart (hardware tests leading into cold check out) after a shutdown

  9. Sector re-commissioning • For existing machines • Hardware tests coordinated (with a daily meeting for planning and decisions etc) by Shutdown Coordinator working very closely with by OP • Hardware tests stop and lead into the machine cold check out under OP responsibility • HC responsible for cool-down and retesting PIC, WIC, QPS etc… • As soon as a sector is cold and ready hand over to OP • Switch on done by system specialists (RF, BT, BDI, CO, PO etc…

  10. What does OP expect? • All systems fully tested to nominal (plus X%?) • All systems put through all “standard” LHC cycles • All safety and machine protection systems operational • Sector ready for cool-down or already cold? • Get hands-on experience as soon as possible

  11. Safety issues • LHC tunnel is a single worksite • TS & SC established procedures for HC. • SC recommend maintaining this responsibility for late installation/repairs • E.g exchange a magnet • Use same procedures safety procedures as installation • Need cryogenics, vacuum as well as system experts • When should HC team officially hand over to OP? • Safety-wise prefer not to sub-divide the tunnel into separated work-sites as this requires a physical separation – leads to a single hand-over • Not ideal….

  12. Conclusions… • LHC will be tested to nominal performance and not beyond • LHC may be tested to less than nominal performance if there are “weaker” elements • HC team should be responsible for sectors until they are cold and ready to start hardware switch on for machine check-out • OP should coordinate this switch on ready for the full machine check out and getting the LHC ready for beam

  13. Conclusions… • Sector re-commissioning, late installation and system repairs look rather like shutdown work • Appoint a shutdown coordinator (part of the HC team?) as early as possible to coordinate these activities with a strong OP involvement • OP should take responsibility for retested sectors as they become available to start machine check out • Coordinate these handovers with the testing/certification of the access safety systems