Hellenic contribution to the lhc hardware commissioning
This presentation is the property of its rightful owner.
Sponsored Links
1 / 21

Hellenic Contribution to the LHC Hardware Commissioning PowerPoint PPT Presentation


  • 77 Views
  • Uploaded on
  • Presentation posted in: General

Hellenic Contribution to the LHC Hardware Commissioning. Rachel-Maria Avramidou On behalf of the Hellenic Team. The team. 1 physicist (PhD), 1 computer scientist, 3 computer engineers, 7 electronics engineers. Introduction to LHC. Basic layout

Download Presentation

Hellenic Contribution to the LHC Hardware Commissioning

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Hellenic contribution to the lhc hardware commissioning

Hellenic Contribution to the LHC Hardware Commissioning

Rachel-Maria Avramidou

On behalf of the Hellenic Team


The team

The team

1 physicist (PhD), 1 computer scientist, 3 computer engineers, 7 electronics engineers


Introduction to lhc

Introduction to LHC

Basic layout

8 sectors (~3.3 km): arcs and straight sections (~528 m)

P1: ATLAS detector

P2: ALICE detector

P3: Collimation system to capture off-momentum particles

P4: Radio Frequency superconducting acceleration cavities (400 MHz)

P5: CMS detector

P6: Beam abort systems for the beams to be extracted safely and deposited onto external dump (absorb the stored energy)

P7: Collimation systemto control the beam halo

P8: LHCb detector

Two-ring superconducting pp collider of 27 km circumference

The dipoles must operate at 8.3 T and be cooled in superfluid helium at 1.9K


Lhc status

LHC Status

  • Installation of LHC almost completed

  • Emphasis moves from installation to commissioning

  • The cool down of the sector 7-8 to helium liquid temperature recently completed

  • First beam injection (450 GeV/c) is foreseen before the end of the year to debug the machine and detectors

  • First physics run at 7 TeV per beam in 2008


Team contributions

Team contributions

  • Development of the Test Bench that assures the quality of Cryogenics Electronics

  • Debugging of Cryogenic Instrumentation in the tunnel

  • PVSS (software development and graphics)

  • Communication and coherence tests (CIET, PLC+SCADA, troubleshooting)

  • Installation, configuration, initialization and troubleshooting of the electronics units for the positioners

  • Testing and troubleshooting for the cryogenic sensors, cards and cables with the Mobile Test Bench (MTB)

  • Cryogenics electronics for the radio frequency system (design, installation, etc)

  • Sensor cabling (deployment, connection, extensions)

  • Sector inspection

  • Preparation, labeling and installation (connections) for the crates.

  • Labeling (crate positions, IFS cables, QV valves, sensor cables etc)

  • Measurements with gauge level (helium level) and data analysis

  • ATLAS (A. Koumparos, G. Theodoropoulos, C. Vottis)

  • CMS (K. Anastasopoulos, F. Karagiannis, I. Polychroniadis)


Cryogenics instrumentation installation in the tunnel

Cryogenics instrumentation installation in the tunnel

Instrumentation crates (~800) are being installed and connected to the LHC. They contain electronic cards that measure temperature, pressure and cryogenic liquid level.


Test bench

Test Bench

  • Development of the Test Bench that assures the quality of all electronics for Cryogenics (Temperature, Pressure, He Level Transducers) in their manufacturing factory.

    This Test Bench consisted of a means of debugging the pre-series designs of the electronics in order to conclude to their final models that went to mass production.

  • Debugging of Cryogenic Instrumentation (electronics, cables, sensors) after their installation in the LHC tunnel.


Mobile test bench

Mobile test bench

  • Useful tool for the electronics troubleshooting

    • Consistency test

    • Card test (simulation)

    • Instrument test

      Examples of problems: not connected and wrongly connected cables (machine side), blown fuses, bad cables, broken connectors, missing connections


Digital valve positioners for qrl

Digital Valve Positioners for QRL

Installation, configuration, initialization and troubleshooting of the electronics units

  • Intelligent positioners (communicating by Profibus PA) used to adjust and control the pneumatic actuators of the cryogenic control valves of the QRL (cryogenic distribution line)

  • The electronic unit in radiation protected areas

  • The pressure radiation block close to the valve (potentiometer reads the stem position, 2 piezo-valves pressurise and depressurise the pneumatic actuator)

rack front

rack back

Profibus DP/PA couplers

Drawers with intelligent valve positionners


Cryogenics control system

Cryogenics Control System

  • Cryo Control System

    Provides the measurements from the cryogenics instrumentation (Temperature, Pressure, Level and QV, PV valves). Gives orders to the heater actuators coming from the control system PLC and commands to protect the Level measurements electronics

  • CIET: Cryo Instrumentation Expert Tool

    Provide all the info coming from the signal conditioners/electronic boards to the cryogenics experts by means of an expert tool based on PVSS


Hellenic contribution to the lhc hardware commissioning

PVSS

  • The SCADA system used in UNICOS

  • Provides the supervision layer for the cryogenics instrumentation

  • The supervision layer is designed in PVSS


Contribution to pvss

Contribution to PVSS

  • Design and maintain the supervision panels


Contribution to pvss1

Contribution to PVSS

  • Develop the necessary software tools for fast and efficient maintenance.


Team s web page

Team’s web page

The webpage was developed during summer 2006 by A.Koumparos as a mean to offer some information to the public about our contribution to the LHC and the other experiments.

http://cern.ch/hellenicomm/


Conclusions

Conclusions

  • Working at CERN is a unique experience for young scientists and engineers

  • The team has been adjusted quickly to the CERN environment, has gained experience, has increased speed and efficiency and is highly appreciated by CERN group.

  • Many thanks to all people who made this project a reality

  • Some more support by the greek administration concerning relevant issues would have been very helpful


Hellenic contribution to the lhc hardware commissioning

Extra slides


Hellenic contribution to the lhc hardware commissioning

Controls architecture for LHC full sector

Full Sector

All valves in alcoves accessed through Profibus

All tunnel instruments accessed through WorldFip


Cooldown

Cooldown

  • 2 weeks of flushing

  • Electrical quality assurance test

  • 2 weeks from ambient to 80 K

  • Second electrical quality assurance test

  • 1 week from 80 K to 4.2 K and then to 1.9 K


  • Login