1 / 12

Section 12

Section 12. Under Construction. Your role as the owner. What to expect at the preconstruction meeting Do’s and Don’t during construction How to handle change orders. The Preconstruction Meeting. Why do we have to do this?

isaw
Download Presentation

Section 12

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Section 12 Under Construction

  2. Your role as the owner • What to expect at the preconstruction meeting • Do’s and Don’t during construction • How to handle change orders

  3. The Preconstruction Meeting • Why do we have to do this? • The preconstruction meeting gives everyone involved a chance to sit down, discuss the specifics of the project and voice their concerns, so that all have a clear understanding of what is going to happen.

  4. The Preconstruction Meeting • Who will be there? • Your engineer - to run the meeting. • authority members • the contractor • the contractors sub’s • the testing lab • airport tenants that will be effected • Aeronautics and/or FAA

  5. The Preconstruction Meeting • What will we talk about? • Roles and responsibilities of the main parties (Sponsor, Engineer, Contractor, Aeronautics, FAA) • Scope • Schedule and coordination • Observation and testing • SAFETY!

  6. Do’s and Don’t during construction • Do’s • Stay in the loop • Keep lines of communication open • Attend the meetings • Talk to your engineer • Keep an eye on your costs • Pay your bills promptly

  7. Do’s and Don’t during construction • Do’s • Authorize someone to sign for the authority • Send in project costs • Set up a system and keep track of your paperwork.

  8. Do’s and Don’t during construction • Don’t • Tell the contractor what to do • Sit on progress estimates or statements of cost • Ask the contractor to do “little projects” • Give up

  9. Change Orders • Why do we need a change order? • A change order revises the contract to establish quantities and unit costs for work that was not in the original contract

  10. Change Orders • What does a change order look like? • It describes the additional work. Many times this requires a drawing be part of the change order • It explains the reason for doing the additional work • It establishes the cost of doing the additional work • It revises the contract time

  11. Change Orders • What do we need to do to make sure we are reimbursed for this additional work? • Provide an unsigned copy for review • Provide an independent estimate of cost • Needs to be within 10% • Get verbal approval • Under $10,000 Aeronautics can approve • Over $10,000 requires FAA approval

  12. Under Construction Questions?

More Related