1 / 23

Development of the Capital Improvement Program FY14/15 – FY18/19

Development of the Capital Improvement Program FY14/15 – FY18/19. GOAL: Develop 5 Year CIP Request for FY14/15 – FY18/19: Identify Projects Decide Timing of Projects Prioritize & Rank Projects. Current Adopted CIP FY12/13 – FY16/17. Current Adopted CIP FY12/13 – FY16/17.

Download Presentation

Development of the Capital Improvement Program FY14/15 – FY18/19

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Development of the Capital Improvement Program FY14/15 – FY18/19

  2. GOAL: • Develop 5 Year CIP Request for • FY14/15 – FY18/19: • Identify Projects • Decide Timing of Projects • Prioritize & Rank Projects

  3. Current Adopted CIP FY12/13 – FY16/17

  4. Current Adopted CIP FY12/13 – FY16/17

  5. Current Adopted CIP FY12/13 – FY16/17

  6. LRPAC RECOMMENDATION: 5 YEAR SUMMARY

  7. MULTI-YEAR, MULTI-SCHOOL PROJECTS Any questions??

  8. SCHOOL-SPECIFIC PROJECTS

  9. SCHOOL-SPECIFIC PROJECTS D: Design C: Construction

  10. AGNOR-HURT ADDITION • Design is currently underway • 13,824 SF Addition • 7 Classrooms • 1 SPED Classroom • Support Spaces • Adds 134 Seats • NEW: Funding request increased to improve bus & parent drop-off areas. YEAR 1: $4,418,000 Open: 2015/16

  11. HENLEY AUXILIARY GYM + MEDIA CENTER • Multi-Purpose Room Addition: 60' x 105' Auxiliary Gym with maple floor • Media Center Expansion: • Enlarge existing media center to align with a 900 student middle school • NEW: LRPAC recommends a fast-tracked design & construction schedule (1.5 years rather than the typical 2) Year 1: $2,989,000 Open: 2015/16 (during)

  12. RED HILL MODERNIZATION • 5,500 SF addition: • Art classroom • Music classroom • Toilets for the existing K-1 rooms • Expanded Media Center • Expanded Gym • New administration area & vestibule • Renovation: • Existing classrooms • Existing toilets • New furniture throughout the building Years 1 & 2: $5,304,000 Open: 2016/17

  13. YANCEY MODERNIZATION • This project will modernize and renovate classrooms, hallways, bathrooms, cafeteria, media center, and other support spaces. • New windows will be added to the classrooms. • It will include improvements to both the bus and parent drop-off areas. • Scope has been revaluated and refined since last year. Years 2 & 3: $1,733,000 Open: 2017/18

  14. CROZET ADDITION • Phase 1: 130 Seats • 15,535 SF Addition • 6 K-5 Classrooms • 1 Pre-K Classroom • 3 Resources Classrooms • Renovation • Media Center • Kitchen, Stage, Cafeteria Ramp • Front Office • Site Improvements • Sized based on the assumption that redistricting will occur from Brownsville and/or Meriwether Lewis YEARS 2 & 3: $5,665,000 Open: 2017/18

  15. W. ALBEMARLE KITCHEN UPGRADES • New walk-in refrigeration and freezer • New serving lines • Installation of heating and air conditioning • New kitchen hood and fire suppression system, grease trap, electric coiling & overhead grills • New ceiling and light fixtures • New kitchen equipment and hand sink as required by health department regulations. YEARS 1 & 2: $858,000 Open: 2016/17

  16. W. ALBEMARLE MODERNIZATION • New entrance canopy and re-facing of the front of the main entrance • Renovation and expansion for additional administrative space and secure entries • Interior renovations (4,000 sf) YEARS 3 & 4: $1,002,000 Open: 2018/19

  17. YANCEY ADDITION • 6,800 sf addition: • 2 new classrooms & small resource space • 6 staff specialist offices • Expand & modernize existing Media Center • Add toilets to three existing classrooms • Modernize existing spaces in the building • Additional parking & playfields • ** Exact scope dependent on recommendations of separate, recently formed advisory committee Years 4 & 5: $3,013,000 Open: 2019/20

  18. STONY POINT ADDITION • 6,000SF Addition • 4 K-1 Classrooms • Support Spaces YEARS 4 & 5: $2,099,000 Open: 2019/20

  19. SCHOOL-SPECIFIC PROJECTS D: Design C: Construction

  20. ADDITIONAL PROJECTS • LRPAC Recommended Projects in Out Years: • High School Addition • Henley Large Group Meeting Space + Security Improvements • Scottsville Addition • Additional Administration Space • Projects NOT Recommended by LRPAC • Land for Future School

  21. High Schools: Enrollment Projections vs. Capacity

  22. High School of the Future In accordance with the Division’s new Horizon 2020 Strategic Plan, one option would be to design a high school of the future. • Objective 1 - We will engage every student • Board Priority 1.3 - Integrate the use of contemporary learning spaces and supportive technologies into the instructional program delivery Three Options to Meet Future High School Needs: • Building growth (ex. Renovations)* • Purchasing land and build • Leasing space *LRPAC recommendation

  23. LRPAC RECOMMENDATION: 5 YEAR SUMMARY