An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS LS1Planning meeting (N08)27/02/13 David Mcfarlane SPS.Technical-Coordination@Cern.ch

  2. Topics • Key dates at the start of LS1. • Magnet testing • Impacts • Planning (Now to the end of April) • False floors lifted in Surface BAs • E.C.Rs • A.O.B SPS.Technical-Coordination@Cern.ch

  3. Key dates at the start of LS1 SPS.Technical-Coordination@Cern.ch

  4. RP Survey dates • Vendredi 15 février à partir de 08h30 :Surveys Zone Nord (TT81, TT82,...). • Lundi 18 février à partir de 13h00 :Surveys Pts. 1, 2, et 8. • Mardi 19 février à partir de 08h30 : Suite et fin des surveys Zone Nord. • Mercredi 20 février de 07h30 à 11h00:Surveys Pts. 5 (droit), et 6 du LHC. • Jeudi 21 février de 07h30 à 11h00 :Surveys Pts. 3, 4 et 5 (gauche). • Vendredi 22 février à partir de 08h30 :SurveysBAs 4, 5, + TI8 (partie haute), TJ8 et TT40. • Lundi 25 février à partir de 08h30 :SurveysBAs 3, 6, 7, + TI2 (partie haute), et TT60. • Mardi 26 février à partir de 08h30 :SurveysBAs 1, 2 + TT10 et TT20. • Jeudi 28 février de 08h30 à 11h30 : Survey du Pt.7. SPS.Technical-Coordination@Cern.ch

  5. Magnet testing27th February to the 26th March This work is being overseen by Jeremie Bauche (TE/MSC) SPS.Technical-Coordination@Cern.ch

  6. Lift MaintenanceFebruary and March SPS.Technical-Coordination@Cern.ch

  7. Lift works SPS.Technical-Coordination@Cern.ch

  8. Dates for replacement of Star-points(On these dates access will not be possible) This work is being overseen by Maryse Da Costa (IT/CS) SPS.Technical-Coordination@Cern.ch

  9. Key dates at the start of LS1 SPS.Technical-Coordination@Cern.ch

  10. Please remember the following!! • All services must remain on until the 27th March 2013!!!!!!! • Only works that do not require access and do not affect the operational mode of the SPS will be allowed to be scheduled before the 27thMarch 2013! • If you are not sure then check with myself and Operations first!!!! SPS.Technical-Coordination@Cern.ch

  11. “Standard” IMPACTs SPS.Technical-Coordination@Cern.ch

  12. “Standard” IMPACTs SPS.Technical-Coordination@Cern.ch

  13. “Standard” IMPACTs SPS.Technical-Coordination@Cern.ch

  14. Planning SPS.Technical-Coordination@Cern.ch

  15. Test AUG/ Bank holidays(Access will be blocked) SPS.Technical-Coordination@Cern.ch

  16. False floors lifted in Surface BAs • Below is a table showing the dates that EL will be pulling cables at each point of the SPS. • During these periods large sections of the false floor in these surface buildings will be lifted • If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first. SPS.Technical-Coordination@Cern.ch

  17. Engineering Change Requests • ECR link • http://sps.web.cern.ch/SPS/quality.htm • ECR Procedure • http://sps.web.cern.ch/SPS/files/quality/ECR_note_gestion_rev02.pdf • ECR Template • http://sps.web.cern.ch/SPS/files/quality/ECR_SPS_formulaire_FR.pdf • All ECRs must be submitted to Jerome Axensalva (BE/OP) AND myself. SPS.Technical-Coordination@Cern.ch

  18. Current ECR’s for LS1 https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3 • Removal of AEWB Pick-up from position 31932 to 31502 • (EDMS No. 1245361) RELEASED • Removal of a BPWA Pick-up from position 31931 to 31101 • (EDMS No. 1245393)RELEASED • Installation of a new Wideband Kickers system in position 32173 • (EDMS No. 1245400)RELEASED • Installation of a new HBW Damper Pick-up in place of BPWA 31931 & AEWB 31932 • (EDMS No. 1245401)RELEASED • Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2 • (EDMS No. 1246559)RELEASED • Reinstallation of pump and gauges (Pirani + Penning) in 11993 (vacuum sector 150) • (EDMS No. 1249305)RELEASED • Modification of the SPS sectorization in long vacuum sectors (110, 210, 310, 410, 510, 610, 160, 260, 360, 460, 560, 660) • (EDMS No. 1249306)NOT IMPLIMENTED • Modification LSS1 sectorization (new VVSF + displacement VVSB 11772) • (EDMS No. 1249307)RELEASED SPS.Technical-Coordination@Cern.ch

  19. Current ECR’s for LS1 https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3 • Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS. • (EDMS No. 1075945) UNDER IMPLEMENTATION • Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5. • (EDMS No. 1221341) RELEASED • SPS Beam Position Monitoring Prototyping Setup in LSS4. • (EDMS No. 1099630)RELEASED • Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper. • (EDMS No. 1251693)RELEASED • Installation d'un nouveau moniteur de position de type BPCR en LSS2 au 22105. • (EDMS No. 1251695) UNDER APPROVAL • Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel. • (EDMS No. 1253832) UNDER APPROVAL • Interlocking of Injection Tunnel upstream areas with LHC powering. • (EDMS No. 1257949) UNDER APPROVAL SPS.Technical-Coordination@Cern.ch

  20. Important information • Access requests • Ensure everyone entering the SPS has the correct access authorisation (via EDH) and has completed the correct courses. • The following safety equipment is Obligatory in the SPS for EVERYONE! • Safety shoes • Biocell • Electronic dosimetre (Make sure you have your new one from Building 55!) • Passive dosimetre • Helmet plus Light • Useful Contact Numbers • SPS Coordination Team • David MCFARLANE- 164247 • Franck BAIS - 165467 • Control Room • SPS CCC – 77500 • TI CCC – 72201 • RP • Christophe Tromel – 163199 • Angelito Herve - 163168 • Coordination Safety • Emmanuel Paulat – 163870 • John Etheridge - 164647 SPS.Technical-Coordination@Cern.ch

  21. Access blocked to BA80 Bonjour, Nous  vous informons que la prochaine intervention sur un star-point réseau  (BA80) ,  dans le cadre du projet HP2910 ,  nécessitera l’arrêt complet du service  informatique suivant https://network.cern.ch/sc/fcgi/sc.fcgi?Action=Describe&Service=S887-R-IP12 https://network.cern.ch/sc/fcgi/sc.fcgi?Action=Describe&Service=S887-R-PB10 https://network.cern.ch/sc/fcgi/sc.fcgi?Action=Describe&Service=S887-R-IP32 Cet coupure s’effectuera  le Lundi 4 Mars   de  8h30 à 17h30 Vous êtes  déclarés administrateur  et/ou principal utilisateur de devices connectes sur ce service,  nous vous demandons en conséquence de prendre toutes les mesures nécessaires lors de cette intervention . Un clic sur le  lien vous permet de lister les devices concernés. Bonne journée Netcom SPS.Technical-Coordination@Cern.ch

  22. A.O.B. • I will be absent from CERN from Monday the 4th March until Monday the 11th March. Franck Bais will replace me. SPS.Technical-Coordination@Cern.ch

  23. SPS coordination website http://sps.web.cern.ch/SPS/ http://cern.ch/LS1planning \\cernhomeJ.cern.ch\J\jocksoft\Public\LS1 Next meeting 13/03/2013 892–1-D20 SPS.Technical-Coordination@Cern.ch