An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS LS1Planning meeting (N017)17/07/13 David Mcfarlane SPS.Technical-Coordination@Cern.ch

  2. Topics • Lifts and Monte-charges. • TT10 update. • Removal of equipment in LSS1+ • Works around the CCC (Surface) • PositionnementgruesBA3. • Planning. • False floors open in the BAs • E.C.Rs. • Access rights and safety equipment • Important Information. • A.O.B SPS.Technical-Coordination@Cern.ch

  3. Lift Maintenance July/August SPS.Technical-Coordination@Cern.ch

  4. TT10 • The first test support was installed last week. SPS.Technical-Coordination@Cern.ch

  5. New storage location for Vacuum chambers SPS.Technical-Coordination@Cern.ch

  6. Removal of equipment in LSS1+ • Work has started to remove the equipment in LSS1+ in preparation for the irradiated cable campaign that will start in October. • The most radioactive equipment will be removed first (Dumps etc) • When they are moved round the tunnel to ECX5 all of the zones that transport will pass through MUST be clear of equipment AND personnel. (BA1-, BA6 and BA5+) • When the exact times of transport are known, everyone will be informed and someone from coordination will pass in front of transport to ensure the areas are clear. • All equipment owners that are transporting equipment must make and EDH request for transport. SPS.Technical-Coordination@Cern.ch

  7. Works around the CCC • Installation of new Transformers • Creation of the new cable trench from the CCC to BA3 • Works inside Building 874 (this includes works on the outside of the building. • Access required around CCC for HVAC replacement works • Installation of PIPES trench between CCC and 774 • Installation of CABLE trench between CCC and 774 • Installation of WASTE WATER trench between CCC and 774 (near Jura) • Waste water pump and pipe work (Seleve side of CCC) • Changing of SPS ring-main valves • Fibre Optics Works (Jura side of CCC) SPS.Technical-Coordination@Cern.ch

  8. SPS.Technical-Coordination@Cern.ch

  9. Planning for the next few months SPS.Technical-Coordination@Cern.ch

  10. Positionnementgrues BA3 Salut David, Nous commencerons donc les transfos au BA3 la semaine prochaine. Nous essayerons de perturber le moins possible les alentours de la CCC mais il faudra quand même bloquer temporairement la route Adams Au niveau des accès vers les transfos (équipement de la grue) plus les Allés et venues des remorques (8 transfos -> 16 passages..).. Je te tiendrai informé en fonction de l’avancement Bonne journée. Serge SPS.Technical-Coordination@Cern.ch

  11. POSITIONNEMENT GRUES BA3POUR TRANSFORMATEURS TE Fred Delsaux/Serge Pelletier

  12. Dépose de tous les anciens transformateurs Possible avec laGrue 55 t… ~10 m

  13. Dépose de tous les anciens transformateurs Possible avec laGrue 55 t…(voir test a blanc)

  14. Mise en place transformateurs Dipôles Grue 55 t

  15. Mise en place transformateurs Quadripôles Grue 220 t

  16. SPS LS1 schedule Open Access : 27/03/13 Close Access : 27/06/14 Beam off : 16/02/13 Beam on: 13/10/14 Beam on Cool down/RP survey and Magnet tests Cool down NO ACCESS Kicker Survey General Maintenance Survey General Maintenance Survey Survey Cables EPC works RF upgrade works RF upgrade works EPC works Survey Cables Survey Kicker Survey 18 KV Civil Engineering in TT10 Fibres Magnets Magnets Magnets Magnets Magnets Magnets Kicker Cables Magnets Magnets 18 KV General maintenance General Maintenance Survey General maintenance CrabCavities General Maintenance Cooling tower 863 Vacuum Septa works Septa works Vacuum Vacuum Ring-main Ring-main Ring-main Ring-main Ring-main Fibres Ring-main Ring-main General Maintenance 18 KV General Maintenance Vacuum Prep work in LSS1 Vacuum Survey Horizontal Vertical smoothing RF Upgrade works Cables Cool down Limited ACCESS UA9 works TT20 pipework 18 KV Fibres CV maintenance CV maintenance Civil Engineering CV maintenance 18 KV Fibres Irradiated Cables Cables Cables Cables Fibres Cables 18 KV EL Studies Civil Engineering TT10 Consolidation CV studies Cables Septa replacement Civil Engineering Civil Engineering Civil Engineering CrabCavities RF Upgrade works Civil Engineering RF Upgrade works Re-install equipment removed for cable works RAL CV works Magnets Fibres Cables Magnets Magnets Magnets Magnets Magnets Magnets Magnets EPC Commissioning tests Vacuum DSO tests/HV tests Cold check out & Start-up Protons to the North Area Protons to LHC Ions to NA61 CV Controls upgrade Re-route Cabling

  17. False floors lifted in Surface BAs • Below is a table showing the dates that EL will be pulling cables at each point of the SPS. • During these periods large sections of the false floor in these surface buildings will be lifted. • Any works in the BA’s that involve lifting of the false floors MUST be reported to the Coordination team • If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first. SPS.Technical-Coordination@Cern.ch

  18. Engineering Change Requests • Templates and Guidelines for Engineering Change Requests: • EDMS: 1271880 • SPS ECR template (in DFS): • https://dfsweb.web.cern.ch/dfsweb/Services/DFS/DFSBrowser.aspx/Applications/CERN/Workgroup%20Templates/SPS/ECR-Template-SPS.dotx SPS.Technical-Coordination@Cern.ch

  19. Current ECR’s for LS1 https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3 • Removal of AEWB Pick-up from position 31932 to 31502 • (EDMS No. 1245361) RELEASED • Removal of a BPWA Pick-up from position 31931 to 31101 • (EDMS No. 1245393)RELEASED • Installation of a new Wideband Kickers system in position 32173 • (EDMS No. 1245400)RELEASED • Installation of a new HBW Damper Pick-up in place of BPWA 31931 & AEWB 31932 • (EDMS No. 1245401)RELEASED • Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2 • (EDMS No. 1246559)RELEASED • Reinstallation of pump and gauges (Pirani + Penning) in 11993 (vacuum sector 150) • (EDMS No. 1249305)RELEASED • Modification LSS1 sectorization (new VVSF + displacement VVSB 11772) • (EDMS No. 1249307 v.2) RELEASED • Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS. • (EDMS No. 1075945) UNDER IMPLEMENTATION SPS.Technical-Coordination@Cern.ch

  20. Current ECR’s for LS1 https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3 • Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5. • (EDMS No. 1221341) RELEASED • SPS Beam Position Monitoring Prototyping Setup in LSS4. • (EDMS No. 1099630)RELEASED • Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper. • (EDMS No. 1251693)RELEASED • Installation d'un nouveau moniteur de position de type BPCR en LSS2 au 22105. • (EDMS No. 1251695) RELEASED • Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel. • (EDMS No. 1253832)RELEASED • Interlocking of Injection Tunnel upstream areas with LHC powering. • (EDMS No. 1257949)RELEASED • Move of BPH.31998 to BPH.42173. • (EDMS No. 1272718) RELEASED • Optical Fibre Racks. • (EDMS No. 1273766) RELEASED SPS.Technical-Coordination@Cern.ch

  21. Current ECR’s for LS1 https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3 • Removal of old fixed TMP vacuum groups in 11655-11691. • (EDMS No.1273232)RELEASED • BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS). • (EDMS No. 1282651) UNDER IMPLEMENTATION • Installation de Coffrets d'Alimentation en LSS1 et TT10. • (EDMS No. 1282860) RELEASED • Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement. • (EDMS No. 1288607) RELEASED • Installation de nouveaux chemins de câbles en LSS1+ et LSS2- du SPS. • (EDMS No. 1291889 v.2)IN WORK SPS.Technical-Coordination@Cern.ch

  22. Access rights and safety equipment • Everyone who enters the SPS MUST have the following: • Completed the correct courses. • Safety course levels 1,2 and 3. • HabilitationElectrique. • Radiological Protection. • Self Rescue Mask Training. • The correct access authorisation (via EDH). • A valid approved IMPACT. (with their name included on this IMPACT) • They must know the number of this IMPACT. • Safety shoes. • Biocell. • Electronic dosimetre. • Passive dosimetre. • Helmet plus Light. • Please note that the medical service no longer contact you when your medical is about to expire!!!!!!! • You will receive an e-mail 2 months before informing you that some of your access rights will soon expire. • It is up to you to contact the medical service to arrange a medical. SPS.Technical-Coordination@Cern.ch

  23. Important information • Useful Contact Numbers • SPS Coordination Team • David MCFARLANE- 164247 • Franck BAIS – 165467 • James RIDEWOOD - 160590 • Control Room • SPS CCC – 77500 • TI CCC – 72201 • CSA - 62511 • RP • Christophe Tromel – 163199 • Angelito Herve – 163168 • Nadine Conan (BA1) – 160641 • Kurt Weiss (BA1) -160759 • Coordination Safety • Emmanuel Paulat – 163870 • John Etheridge - 164647 SPS.Technical-Coordination@Cern.ch

  24. A.O.B. • There are currently 47 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT. • I will be absent from CERN on Friday the 19th July and Monday the 22nd July. You can contact Franck or James on matter concerning the SPS. SPS.Technical-Coordination@Cern.ch

  25. SPS coordination website http://sps.web.cern.ch/SPS/ http://cern.ch/LS1planning \\cernhomeJ.cern.ch\J\jocksoft\Public\LS1 Next meeting 31/07/2013 892-1-D20 SPS.Technical-Coordination@Cern.ch