An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Today’s Agenda • Opportunity/Problem Investigated • Overview of Recommendations • Overview of Analysis • Detailed Recommendations • Limitations

  2. Opportunity/Problem Investigated • Demand levels for audio equipment currently exceed capacity • Final test and inspection station is bottleneck operation

  3. Overview of Recommendations • Dedicate test and inspection employees • Do not cross-train them • Concentrates experience among smaller group of employees • 12% increase in capacity • Impact on workforce flexibility

  4. Overview of Analysis • Inspection time data collected for 176,000 units • Data from 148 workers • Curves fit to each worker’s performance data • Simulation models developed to investigate a number of factors • Rate of worker learning, task-tenure times, amount of cross-training, and degree to which workers forget

  5. Summary of Results • Average prior experience was 1,150 radios • Range was 0 to 13,000 radios • Needed to inspect 921 radios on average to reach half potential • Range was 2 to 15,000 radios • Significant relationships between variables

  6. Results Related to Worker Cross-Training • Cross-training increases size of worker pool • This increases time between successive assignments to test and inspection station • Longer times between assignments result in more forgetting

  7. Short-Term Recommendations • Assign workers with most previous experience to the inspection stations. • Identify ways to mange task assignments to the inspection station more effectively • Incentives, policies on bumping, working with union

  8. Long-Term Recommendations • Pilot test video-based computer system • Create worker profiles based on the methodology used in this study • Assess the forgetting rate of new hires during the probationary period

  9. Limitations/Assumptions • Employees work independently • Data used all came from same task • All workers were assumed to have an equal chance of being assigned to the test and inspection station