EURO4M Financial aspects of the project

EURO4M Financial aspects of the project. Contents presentation:. Euro4M General Financial and Legal aspects so far Reporting Difference FP7 vs. FP6 Eligible costs Non-eligible costs Audit report Pre-financing. Euro4M General. Euro4M financed by European Union

Download Presentation

EURO4M Financial aspects of the project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EURO4MFinancialaspects of the project

  2. Contents presentation: • Euro4M General • Financial and Legal aspects so far • Reporting • Difference FP7 vs. FP6 • Eligible costs • Non-eligible costs • Audit report • Pre-financing

  3. Euro4M General • Euro4M financed by European Union • Project within the FP7 program • Specific regulation by the European Commission • From financial/legal aspect attendance to the “Financial Guidance” • Start date April 1st • Duration 48 months • Available budget for the project 3.989.200 euro • Divided among 9 partners • Coordination by KNMI

  4. Financial and Legal aspects so far • Proposal • Evaluation by the EC (13 points out of 15) • Negotiation phase • Grant Preparation Forms (already signed) • Grant Agreement (to be signed within 45 days) • Consortium Agreement (to be signed) • Start of the project (1st April 2010)

  5. Reporting Reporting periods for Euro4M are as follows: • P1: from month 1 to month 12 • P2: from month 13 to month 24 • P3: from month 25 to month 36 • P4: from month 37 to the last month of the project (expected 48) First reporting from April 1st 2010 till March 31th 2011 Reporting: • within 45 days to the EC • use of Form-C for financial part • and reporting on the performed research (project results)

  6. Difference FP7 vs. FP6 Not to much: • General changes like possibilities for: duration, calls, themes and new activities • Some terminology Financial changes in relation to EURO4M: • Terms for eligible costs didn’t change • Audit certificate!

  7. Eligible costs Financial Guide: Article II.14 Criteria: • Actual (real) • Incurred by the beneficiary • Incurred during the duration of the project • Determined according to the usual accounting principles • Used for the sole purpose of achieving the objectives of the project and it’s expected results, in a manner consistent with the principles of economy, efficiency and effectiveness. • Recorded in the accounts of the beneficiary • Have been indicated in the estimated overall budget

  8. Non-eligible costs Financial Guide: Article II.14.3 For instance: • Taxes (including VAT) • Duties • Interest • Provisions for possible future losses • Exchange losses • Cost declared or incurred, or reimbursed in respect of another community project • debt and debt service charges, excessive or reckless expenditure

  9. Audit report Financial Guide: Article II.4.4 • Certificates on the Financial Statements (CFS) should be provided only once the threshold of EUR 375.000 has been reached. • This means only one audit certificate during the project for partners 1, 2 and 5 till 9 (KNMI, MO, MS, DWD, SMHI, UEA and MF). • Partners 3 and 4 (URV and NMA-RO) don’t need a audit certificate. • Once a audit certificate is given; there is no need for another certificate only when the threshold of 375.000 euro is reached again (this means also for the project end).

  10. Pre-financing • First pre-financing 35% of the total budget = EUR 1.396.220 • To each participant will be transferred 35% of the partners budget • Payment arrangement are made

  11. Contact If there are questions on financial or legal matters please contact: Project leader: Albert Klein Tank Project assistant: Karin van der Schaft Project (financial) controller: Jeroen Sassen E-mail: sassen@knmi.nl Mail: PO-box 201, 3730 AE, De Bilt, Netherlands Phone: +31 30 2206 464