An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Board of Education: Special Meeting on October 4th , 2019 • Presenter: Tammy MacKay (Chair of FFT) • FFT Committee: Joe Faranetta (Vice President), Jeanne Stifelman and Alison Manfred • Other Board Members in Attendance: Ron Conti (President), Anne Standridge, and Rob Soni • Administration in Attendance: Jenn Fano, Gerry Eckert, Stephen Frost and Matt Pfouts • Architect: Greg Somjen

  2. Original Concept • New Construction • 17,000 square feet • New Bathrooms/locker rooms/concession stand • Space for multi-purpose use • Projected spend of $8 million with an expected construction cost of $7,245,000 • October 2018: Voters Approved $24,495,000 Referendum • Collaboration with Stakeholders : Project Functionality and Scope Enhanced • Added 3,000 sq. ft to field house • Original design featured new fitness / multi-purpose room. Enhanced design (floor space and height) accommodated additional flexibility (i.e. basketball, volleyball, color guard, and other uses) during gym class and recreation use. • 500 to 800 sq. ft of additional general storage space was incorporated into the design • Moved position of Field House further into hillside to create plaza, improve access and egress, and maintain use of the track and field during construction

  3. Bid Project • Based on project scope, we expected to receive construction bids in the range of $7 million - $8 million ($350 – $400 sq. ft. x 20,000) • 9/12/19 – 9 bids received • Bids ranged from $10.4 million - $11.9 million ($520 - $595 per sq. ft. x 20,000) • Cost per sq. ft. under low bid was 30% higher than expected upper range of cost per sq. ft. Board rejected all bids • Board/Admin/Architect began process of examining why bids were so high • Preliminary findings: • Steel costs were higher than expected due to detailing: rough estimate - couple of hundred thousand dollars • Blasting – higher than expected and includes cushion protecting them from “unknowns” • Project Detailing – roof overhangs, stonework, etc. – higher than expected • Timeline – completion date of Fall 2020 caused contractors to increase bid price

  4. Options for Consideration • Rebid current package and hope for lower bids – award OR reject a second time, we could then begin negotiations – no savings • Maintain current project design but streamline detailing and convert construction from single bid to a series of specific construction projects to reduce cumulative project risk for bidders. Requires 4 weeks to prepare package for possible bidding. • Reduce scope and functionality of building (reduce height, space, and storage capacity). Design would need to be revised (new cost) and a new bid process opened. • Option 2 - Rescoping Ideas (Greg to discuss) • Blasting – pull out of bid separately • Localize disposal • Field House Demo – pull out and bid separately • Water Trenching – pull out of bid and engage Township • Streamline detailing

  5. Financial Snapshot • Savings can be reallocated, used to purchase items for projects, or returned to taxpayers (estimate $100 per HH per $1MM saved – impact would be felt in 2023-2024)

  6. Moving Forward - Direction to Architect • Board needs to provide direction to Architect • Specific Option or Approach • Reallocation of Referendum Project Savings • Update: Board of Education Agreed on the Following at the October 4th Meeting: • Bid the field house demo and blasting projects this fall and complete over the colder months • Bid the science rooms in Jan. 2020 • Bid the field house after bids from science rooms are awarded (later Jan. or Feb. 2020) • Board agreed to concept of reallocation of some/part of the referendum savings