CVA Presentation to Energy Balancing Committee 25 May 2007 by John Fitzpatrick & Peter Collins. Agenda. Objectives of the claims validation process Organisations Claiming gas Rules for balancing claims Claims validation timetable Disaster recovery. Objectives of CVA.

evania
Download Presentation

CVA Presentation to Energy Balancing Committee 25 May 2007 by John Fitzpatrick & Peter Collins

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CVA Presentation to Energy Balancing Committee 25 May 2007 by John Fitzpatrick & Peter Collins

  2. Agenda • Objectives of the claims validation process • Organisations • Claiming gas • Rules for balancing claims • Claims validation timetable • Disaster recovery

  3. Objectives of CVA • Objectives of CVA • Provide the information necessary for National Grid to allocate NTS (National Transmission System) charges to shippers/traders based on actual gas flows into the NTS

  4. Organisations involved

  5. How is gas claimed? • Claim made by shipper/trader • Claim is checked by agent • matched to National Grid information • matched to producer information • matched to other shipper information • Balancing rules applied • Claim is validated • Validated claim notified to National Grid

  6. Daily Entitlement Statements • Producers: (D+3) • Gas flow day • Sub-terminal • Amounts in kWh • (A) Allocated Entitlement • (B) Upstream Acquisitions and Disposals • (C) Disposals to CVSA Principals • (D) Amount retained as CVSA Principal

  7. Daily Activity Logs • Shippers/Traders: (D+5) • Gas flow day • Sub-terminal • Transactions • Transaction type (Base,Purchase,Sale) • Counter party • Amount (kWh) • Total daily claim quantity (B+P-S)

  8. Trade Validation - Rule 1 When the parties to a trade disagree on the amount of gas sold, the sale amount should be used (“seller wins” rule)

  9. Trade Validation - Rule 2 • When a Shipper/Trader has insufficient gas to meet its sales obligations, its sale will be scaled down accordingly

  10. Trade Validation - Rule 3 • Where a Shipper/Trader has its sales scaled down, the ‘seller wins’ rule (Rule 1) shall be applied to the affected parties

  11. Base Quantity Validation - Rule 1 • Gas claimed cannot exceed the delivery quantity at any sub terminal

  12. Base Quantity Validation - Rule 2 • Rights to base quantity gas can be protected if a producer can substantiate your claim

  13. Validation timetable • Delivered quantity (D+1) • Daily Entitlement Statements (D+3) • Daily Activity Logs (D+5) • Validation by Agent (D+5 to D+7) • Validated claims submitted to National Grid via Gemini (D+7) • Interim upload by Agent (1st & 2nd working day of the month)

  14. Revision timetable (daily after D+7) • Revisions to Daily Entitlement Statements • Revisions to Daily Activity Logs • Validation by Agent

  15. Close out timetable • Deadline for revisions to Daily Entitlement Statements (M+10) • Deadline for revisions to Daily Activity Logs (M+12 12:00 pm) • Final revisions (M+13 to M+15) • Final validated claims submitted to National Grid via Gemini (M+15)

  16. Agenda • Objectives of the claims validation process • Organisations • Claiming gas • Rules for balancing claims • Claims validation timetable • Disaster recovery

  17. Disaster Recovery Systems • Remote DR Site with full capability • Back Up Routine • Log shipping to DR site every 5 mins via VPN • Database backed up to tape on a daily basis • Tapes rotated on a 7 day cycle • Back up internet connection at Cambridge for VPN • Servers on UPS • CLAIM2 website hosting at main and DR locations • Phones & Faxes can be diverted to any location • GMSL has 24 hour IT Network support

  18. Disaster Recovery Event • Short term system outage • CVA team access DR servers from main site • CVA team relocate to DR site Recent Outage - Inconsistency between a table in the web admin system and the processing table which subsequently affected the system’s data transfer functionality. • Outage < 24 hours • CLAIM2 software run live for 6 years • CVA process 11 years with no missed deadlines