Metro Vancouver New Waste-to-Energy Capacity Project Update

Metro Vancouver New Waste-to-Energy Capacity Project Update. Presented to SWANA Northern Lights June 20, 2013 Sarah Wellman, P.Eng. Presentation Overview. Regional solid waste management system overview Integrated Solid Waste & Resource Management Plan (ISWRMP) WTE technologies

elia
Download Presentation

Metro Vancouver New Waste-to-Energy Capacity Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Metro Vancouver New Waste-to-Energy CapacityProject Update Presented to SWANA Northern Lights June 20, 2013 Sarah Wellman, P.Eng

  2. Presentation Overview • Regional solid waste management system overview • Integrated Solid Waste & Resource Management Plan (ISWRMP) • WTE technologies • Existing waste-to-energy (WTE) facility • New WTE procurement

  3. Regional Solid Waste Mgmt System

  4. ISWRMP • Overriding principle of the ISWRMP is the avoidance of waste through an aggressive waste reduction campaign. • Submitted 2010 • Approved with conditions 2011 • Implementation underway

  5. Reduce Reuse Recycle Recover Residuals ISWRMP - Goals Minimize waste generation GOAL 1 GOAL 2 Maximize reuse, recycling, and material recovery GOAL 3 Recover energy from waste stream after recycling GOAL 4 Dispose of all remaining waste in landfill after material and energy recovery

  6. ISWRMP - Targets • 10% per capita waste reduction by 2020 • Increase regional diversion rate from 55% to a minimum of: • 70% by 2015 • 80% by 2020 6

  7. ISWRMP Goal 3: Recover Energy • Continue use of the existing WTE facility in Burnaby • Increase WTE capacity in the region up to a limit of 500,000 t/year additional capacity* (replace Cache Creek Landfill) • Maximize energy recovery through district heat and electricity • Scale WTE capacity so that total capacity does not exceed minimum waste flow projection • Recover metals and ash for beneficial use • Recover landfill gas at the Coquitlam and Vancouver Landfills for beneficial use • * As per ISWRMP

  8. WTE Technologies

  9. Metro Vancouver’s Waste-to-Energy Facility • Located in Burnaby • Operating since 1988 • Metro Vancouver owned • Privately operated & maintained • Lowest cost disposal facility

  10. New WTE Procurement • Additional Capacity Required: 370,000 t/yr • Goals: • Maximize competition • Determine technology and location (in or out of region) through competitive process • Ensure transparency, meaningful consultation and engagement • Maximize environmental, financial and social benefits

  11. New WTE Procurement • Stage 1: Request for Qualifications 1 (RFQ1) • Stage 2: Potential Site Identification Process • Stage 3: Request for Qualifications 2 (RFQ2) • Stage 4: Request for Proposals • Stage 5: Regulatory and Environmental • Stage 6: Detailed Design and Construction

  12. New WTE Procurement: Consultation & Engagement • Purpose: • Consult meaningfully with stakeholders • Key Elements: • Consultation and engagement program underway • Program to be linked to key project milestones and activities • Consultation activities to occur throughout the process • Continue to report regularly to the Metro Vancouver Zero Waste Committee and Board with additional information as project proceeds

  13. New WTE Procurement: RFQ1 – Technology Only - Complete • Purpose: • Short-list to proponents with demonstrated ability to deliver new WTE capacity • Key Elements: • Duration: 5 months, Oct 2012 – Jun 2013 • Technology focus • Demonstrated ability based on reference facilities • Reference facility must meet five minimum requirements • 22 submissions were received, 10 were short-listed, including 7 mass-burn, 2 gasification, and 1 RDF

  14. New WTE Procurement: Potential Site Identification - Ongoing • Purpose: • Identify all potential sites (in or out-of-region) • Key Elements: • Duration: 8 months, Jan 2013 – Nov 2013 • Public invitation to allow site owners to self identify •  communal sites • Proponents specify any site that they are considering for project  exclusive sites • Short-list potential sites based on logistics, proximity to energy users, compatible land uses, and environmental criteria • Communicate all communal and exclusive sites to the public

  15. New WTE Procurement: Potential Site Identification - Ongoing • Site evaluation criteria are currently being finalized to assess communal sites. These include: • Air quality impacts and health risk • Permitted land use • GHG emissions • Proximity to energy customers • Technical and financial criteria • The public has been asked to provide comments on the evaluation criteria. • Public meetings will be held in proximity to all short-listed sites.

  16. New WTE Procurement: One vs Multiple Projects • Purpose: • Metro Vancouver will decide if one or more project(s) will be built, whose aggregate capacity will equal 370,000 tonnes/year • Key elements: • Based on short-listed technologies and sites • Includes evaluation of transportation optimization, costs, risk to project delivery, opportunities for energy use, and public acceptance

  17. New WTE Procurement: RFQ2: Technology + Site • Purpose: • Short-list to a small number of proponents/projects based on site, technology and teams • Key Elements: • Duration: 9 months, Nov 2013 – Jul 2014 • Proponents work with potential host communities to develop integrated project proposals, including technology and site • Ensures fair competition between technology vendors with and without previously secured sites

  18. New WTE Procurement: Request for Proposals • Purpose: • Select final proponent(s) including site(s) • Key Elements: • Duration: 10 months, Aug 2014 – Mar 2015 • Extensive design and environmental investigation • Proposals require demonstrated community support • Fixed proposal price including environmental and community obligations

  19. New WTE Procurement: Regulatory and Environmental • Purpose: • Obtain regulatory approvals • Key Elements: • Duration: 2 years, Aug 2014 – Mar 2017 • Metro Vancouver engaging health, environment and municipal agencies to define uniform regulatory process • Proponents to initiate preliminary approval process as part of proposal development • Selected proponent to secure municipal and environmental approvals

  20. New WTE Procurement: Detailed Design & Construction • Purpose: • Deliver completed and commissioned WTE facility • Key Elements: • Duration: 3 years, 2015 – 2018 • Design process initiated during RFP stage • Monitoring committee likely established for duration of construction • Operation to begin once commissioning period ends in 2018 • Likely 25 year operation contract