ChocoPlane Project. Software Engineering II Exercise I. Problem Statement. Goal: Construct an Airplane that carries a choco-kiss as far as possible without harming it. Chocoplane Requirements. Functional Requirements: The airplane has to fly The airplane carries a Cocoa-Kiss

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' ChocoPlane Project' - duane


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
chocoplane project

ChocoPlane Project

Software Engineering II

Exercise I

problem statement
Problem Statement
  • Goal: Construct an Airplane that carries a choco-kiss as far as possible without harming it.
chocoplane requirements
Chocoplane Requirements
  • Functional Requirements:
    • The airplane has to fly
    • The airplane carries a Cocoa-Kiss
  • Nonfunctional Requirements
    • Takeoff is the porch area outside the seminar room.
    • The Cocoa-Kiss is not damaged at take-off
chocoplane project organization
Chocoplane Project Organization
  • 5 teams with 6 participants each
    • Each team builds its own solution
  • Resources:
    • Everything you can find at TUM or the Lidl-Supermarkt (shortly before Garching) can be used to build the plane
schedule
Schedule
  • Project Duration: 15:00 - 16:40
  • Development time: 15:00-15:45
  • Integration testing: 15:45- 16:00
  • Mile Stone: Client Acceptance Test: 16:15-16:30
    • The teams perform their flights simultaneously
  • Determination of the winner: 16:30
acceptance criteria
Acceptance Criteria
  • The plane must prominently display the name of the subsystem team
  • The plane must actually demonstrating flying behavior (throwing is not allowed)
  • The Cocoa-Kiss must be undamaged after landing
  • The client inspects the Cocoa-Kiss after the plane has come to complete standstill and determines its healthiness.
prize
Prize
  • The team whose plane actually flies, and covers the longest distance wins a prize
    • The distance is measured from the wall of the building to the first contact on the ground.
  • Metrics used by the client:
    • State of Cocoa-Kiss: damaged (0 points), undamaged (30 points)
    • Length of flight: 0 m: 0 points, 1-5 m: 30 points, 5-15 m: 40 points, 16-20 m: 50 points, 21 or more m: 60 points
    • Beauty of flight: Throwing: 0 points, Flying: 30 points
development laboratories
Development Laboratories
  • Team 1: Seminar room
  • Team 2: Glas room
  • Team 3: Aquarium
  • Team 4: Terrarium
  • Team 5: Aurarium