Procurement of works. "The project is co-funded by EU trough the Bulgaria – Serbia IPA Cross-border Programme”. Single tender (< or equal to 10 ,000 Euro) Competitive Negotiated procedure (> 10,000 Euro < 300,000 Euro) Local open tender (> or equal to 300,000 Euro and < 5,000,000 Euro)

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' "The project is co-funded by EU trough the Bulgaria – Serbia IPA Cross-border Programme”.' - duaa


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Procurement of works

"The project is co-funded by EU trough the Bulgaria – Serbia IPA Cross-border Programme”.

budget v s procedure
Single tender (< or equal to 10,000 Euro)

Competitive Negotiated procedure (>10,000Euro < 300,000 Euro)

Local open tender (> or equal to 300,000 Euro and < 5,000,000 Euro)

International open tender (> 5,000,000 Euro)

Budget v/s Procedure
single tender
Single Tender

Minimum of one company required

 Letter of invitation and tender dossier sent

 Evaluation to follow the procedure for openworks tenders

competitive negotiated procedure
Competitive Negotiated Procedure

No procurement notice needs to be published

Minimum of three contractors to be consulted

Letter of invitation and tender dossier sent

A minimum of three technically compliant offers must be received

Evaluation to follow the procedure for open works tenders

local open procedure
Local Open Procedure

Procurement forecast & notice published only in beneficiary country.

ECpublishes reference on the Internet with address from which interested companies can obtainfurther information

Tender dossiers either picked up at CA or sent to interestedtenderers

A fee can be charged to cover the cost of the preparation of the tender dossier

Often the tender dossier, particularly the Technical Specifications, will be prepared by an external expert

Clarification or site meetings may be foreseen

Variant solutions may be taken into account if permitted by the Contracting Authority, and are:

Submitted by tenderer with the least expensive compliant offer, and

They meet the required technical specifications

Bids formally evaluated (minimum of 3 voting members required)

international open procedure
International Open procedure
  • Procurement forecast & notice to be published on the Internet, in the Official Journal of theEuropean Communities and in the media
  • Tender dossiers either picked up at CAor sent to interestedtenderers
  • A fee can be charged to cover the cost of the preparation of the tender dossier
  • Often the tender dossier, particularly the Technical Specifications, will beprepared by an external expert
  • Clarification or site meetings may be foreseen
  • Variant solutions may be taken into account if permitted by the Contracting Authority, andare:

o    Submitted by tenderer with the least expensive compliant offer, and

o    They meet the required technical specifications

  • Bids formally evaluated (minimum of 5 voting members required)
  • In exceptional and justified cases, and with the approval of the EC, a restricted tenderprocedure may be used.
negotiated procedure
Negotiated Procedure
  • In certain circumstances, and with EC approval, a negotiated procedure may be used, notably:

 Where there is an urgency incompatible with the appropriate tendering/contractingtimetable

 For unforeseen additional works becoming necessary to be carried out byexistingcontractor

 Where such works cannot be separated from main contract

 Where such works can be separated but are absolutely necessary

 Aggregate cost of contracts awarded for additional works cannot exceed 50% oforiginal contract

 Where a tender has been unsuccessful

works tender dossier
Works Tender Dossier

Volume 1

Section 1 : instructions to tenderers

Section 2 : Tender Form and Appendix to the tender

Section 3 : tender guarantee form

Section 4 : questionnaire

Section 5 : Administrative Compliance Grid and Evaluation grid

Volume 2

Section 1 : contract form

Section 2 : general conditions for works contracts FIDIC

Section 3 : particular conditions

Section 4 : specimen performance guarantee

Section 5 : specimen prefinancing payment guarantee

Section 6 : specimen retention guarantee

Section 7: tax and customs arrangements

Volume 3

Technical specifications

Volume 4

Financial Interpretative Note

Financial offer lump sum contracts / financial offer unit price contracts

Volume 5

Design documents, including drawings

fidic
FIDIC

Federation Internationale des Ingenieurs-Conseils

what is fidic
What is FIDIC?
  • Federation of Consulting Engineers Council
  • Founded in 1913 (Based in Switzerland)
  • Mission is to promote Engineering Expertise and fair procurement
  • Extensive bookshop (cash on delivery)
  • Represents member organisations in 68 countries
  • Web site is http://www.fidic.org
fidic books
FIDIC Books

Short Form Construction EPC Turnkey Plant and Design Build

which book
Which Book ?

Is there any risk on design or process?

no

Is it a straightforward and simple project?

no

yes

Are the market and the unprecedented risks high?

Fixed price – turn key

Restricted client contribution

High market risks

yes

yes

no

no

yes

DETAILED EXAMINATION

Correct according to Client`s requisitions and then create a modified contract

fidic red book
FIDIC Red Book
  • The Client carries out all the engineering services and copes with the risks.
  • The Consultant is responsible for the management and supervision.
  • Checking and supervision of the design and Works, approval of those or rejection are Consultant\'s responsibilities
  • The Contractor is paid per production and based on unit prices, risk of cost overrun is the risk of the Client.
  • During the implementation of the Works detailed tests are performed. Usually tests are simpler during the Handover Period and Start-up.
  • Disputes are caused are due to unexpected extra Works and increase of Cost.
  • There is usually a cost overrun
  • Consultant works as a daily Arbitrator.
fidic yellow book
FIDIC Yellow Book
  • The Contractor carries out all the detail engineering services.
  • The Contract deals not with "HOW TO DO" but with "WHAT TO DO"
  • The main document is the "Employers Requirements" and explains what performance and quality is expected.
  • The Contractor takes most of the risks including the overrun in quantity and cost.
  • The Client may hold the authority to approve the design.
  • Management and supervision of the contract is carried out by the Consultant.
  • Checking and supervision of the design and Works, approval of those or rejection are Consultant\'s responsibilities
  • The Contractor is paid on a calendar basis at on some milestones.
  • During the implementation of the Works simpler tests are performed. Usually tests are more complicated during the Handover Period and Start-up.
  • Disputes are caused are due to different interpretation of the "Employer\'s Requirements"
  • Consultant works as a daily Arbitrator.
fundamentals of works tender dossiers
Fundamentals of Works Tender Dossiers

Conditions of Contract (CC) – part of the Tender Dossier, respectively of the future contract that are addressing specific issues, required for the contract implementation.

General C – are establishing a set of rules, generally valid in all EU financed contracts

Special C – are modifying, amending, supplementing the General C, for including in the contract the specificities of a certain country, or of a certain project.

order of precedence of contract
Order of precedence of Contract
  • Contract (Agreement)
  • Tender Form with its appendix
  • Particular Conditions of Contract
  • General Conditions of Contract
  • Technical Specifications
  • The design (drawings etc.)
  • BoQs after arithmethical corrections
  • Any other document forming part of the contract

Addenda shall have the order of precedence of teh document

they are modifying

particular conditions of contract
Particular Conditions of Contract
  • The Particular Conditions take priority over the General Conditions
  • Are the instrument for the Contracting Authority/ Beneficiary, for introducing the particular aspects of the local legislation, or of the project.
  • The General Conditions can be applied for any project, anywhere in the world, but will never be able to deal with the specific issues related to a specific project, nor to the legislation of a certain country
particular conditions of contract1
Particular Conditions of Contract
  • The PC should provide all relevant conditions that relate to the projects and the laws of the contract, which add, complement, or amend the General C
  • In drafting the PC, one must pay particular attention to cross-reference with all other interconnected Clauses that may be affected.
  • Make sure you don’t create ambiguities with other Clauses, or provisions of other documents
  • Major exercise in cross referencing PC with:
      • GC
      • Technical Specifications
      • Schedule/ Annexes (e.g. delivery schedule)
particular conditions of contract2
Particular Conditions of Contract
  • Examples should be only used after verifying they are suitable for your specific case and adapted accordingly
  • The guidance is to assist writers of the special conditions, by giving options for various sub-clauses where appropriate
  • It is recommendable that suitably-qualified engineers (technical staff) to prepare documents and a review by a suitably-qualified legal advisers
  • There is no specific Clause in the General C requiring additional data to be included in the PC, this is done only when and as much as necessary
  • Any modification of existing Clauses, or insertion of a new Clause, must be made for a clear reason and only in conjunction with the other Clauses
  • PC will only contain modified Clauses, without repeating the ones from GC that are not modified
main aspects to be addressed in pc
Main aspects to be addressed in PC

Applicable law and language

Contractor’s obligations

Performances/ Insurances

Timetable/ Schedules

Documents/ Drawings/ Specifications/ Manuals

Patents and licences

Variations of contracted quantities

main aspects to be addressed in pc1
Main aspects to be addressed in PC

Quality levels

Inspection/ Testing at the delivery, Testing after installation

Acceptance

Payments methods/ schedules

Delivery – place, risks, related documents and procedures

Warranty/ After-sales services

Disputes resolution

bill of quantities boqs
Bill of Quantities-BoQs

The objectives of BoQs are;

  • to provide sufficient information on the quantities of Works to be performed toenable Bids to be prepared efficiently and accurately
  • when a Contract has been entered into, to provide a priced (BOQ)

for use inthe periodic evaluation of Works executed.

In order to attain these objectives, Works should be itemized in the (BOQ) in sufficientdetail to distinguish between the different classes of Works, or between Works of thesame nature carried out in different locations or in other circumstances which may giverise to different considerations of cost.

Consistent with these requirements, the layout andcontent of the (BOQ) should be as simple and brief as possible.

bill of quantities boqs1
Bill of Quantities-BoQs

The Bill of Quantities should be divided generally into

the following sections:

a. Preamble;

b. Work Items (grouped into parts);

c. Daywork Schedule; and

d. Summary.

boqs preamble
BoQs Preamble

The Preamble should indicate the inclusiveness of the unit prices, and should state the methods of measurementthat have been adopted in the preparation of the Bill of Quantities and that are to be used for themeasurement of any part of the Works.

slide25

BoQs Work Items

The items in the Bill of Quantities should be grouped into sections to distinguish between those parts ofthe Works that by nature, location, access, timing, or any other special characteristics may give rise todifferent methods of construction, phasing of the Works, or considerations of cost.

General items commonto all parts of the Works may be grouped as a separate section in the Bill of Quantities. When a family ofPrice Adjustment Formulae are used, they should relate to appropriate sections in the Bill of Quantities.

boqs work items
BoQs Work Items

The Bill of Quantities usually contains the following part Bills, which have been grouped accordingto the nature or timing of the work:

  • Bill No. 1-General Items;
  • Bill No. 2-Earthworks;
  • Bill No. 3-Culverts and Bridges;
  • Bill No. 4-etc., as required;
  • Daywork Schedule; and
  • Summary Bill of Quantities.
boqs daywork schedule
BoQs Daywork schedule

Daywork Schedule should be included if the probability of unforeseen work, outside the items includedin the Bill of Quantities, is relatively high. To facilitate checking by the Employer of the realism of ratesquoted by the bidders, the Daywork Schedule should normally comprise:

  • list of the various classes of labor, materials, and Contractor’s Equipment for which basic Dayworkrates or prices are to be inserted by the bidder, together with a statement of the conditions under whichthe Contractor will be paid for work executed on a Daywork basis;
  • a percentage to be entered by the bidder against each basic Daywork Subtotal amount for labor, materials,and Plant representing the Contractor’s profit, overheads, supervision, and other charges.
boqs summary
BoQs Summary

The Summary should contain a tabulation of the separate parts of the Bill of Quantities carried forward,with provisional sums for Daywork, for physical (quantity) contingencies, and for price contingencies(upward price adjustment) where applicable.

boqs provisional sums
BoQs Provisional Sums

A general provision for physical contingencies (quantity overruns) may be made byincluding a provisional sum in the Summary Bill of Quantities. The inclusion of suchprovisional sums often facilitates budgetary approval by avoiding the need to requestperiodic supplementary approvals as the future need arise.

Where such provisional sumsor contingency allowances are used, the Particular Conditions of Contract should state themanner in which they will be used, and under whose authority (usually the Engineer’s but here is the CA)

evaluation of works
Evaluation of Works

Evaluations are held in phases:

  • Receipt and registration of tenders
  • Prepatory meeting
  • Tender Opening Session (Public Open)
  • Administrative Compliance
  • Technical Evaluation
  • Financial Evaluation
  • Conclusion
evaluation committee
Evaluation Committee
  • 5 members for contract < 5,000,000 Euro
      • 2 non-voting + 3 voting
  • 7 members for contract > 5,000,000 Euro
      • 2 non-voting + 5 voting
  • Reasonable command of English + technical & administrative capacity
  • Impartiality and confidentiality (conflict of interest)
admin check
Admin Check
    • To check tenders are complete and tender guarantee is submitted
    • EU representatives should be informed (ex-ante)
    • Opening checklist should be filled
    • Chairperson has to check the conflict of interest of the Evaluation Committee
    • Tender opening checklist & report has to be completed

Administrative Compliance Grid:

    • Documentation complete as required
    • Nationality of the Tenderer
    • Language Correct
  • Committee may request clarifications within reasonable time
  • Only compliant tenders go on to next phase
technical evaluation
Technical Evaluation
  • Done Lot by Lot (if applicable)

Be careful about criteria for tenderers tendering for multiple Lots

  • Use the Evaluation Grid in the tender dossier
  • Rules of origin
  • Eligibility of sub-contractors
  • Required Capacity (economic, financial, professional and technical)
  • Only technically compliant offers go on to the next phase
financial evaluation
Financial Evaluation
  • Check arithmetical errors
  • Calculate discounts for multiple Lots
  • Contract is awarded to the lowest compliant offer; within the available budget
  • Evaluation of variant solution – only those submitted

by the lowest compliant offer

  • Problem of abnormally low offers
conclution
Conclution
  • Evaluation Committee recommends to:
  • Award the contract to the tenderer which
    • complies with administrative and technical requirements
    • is the lowest offer within the maximum budget available
  • Cancel the procedure