Status of the ITER Project Norbert Holtkamp PDDG Nominee September 11, 2006. Short Bio. Norbert Holtkamp Born Nov. 23, 1961 Studied Physics in Berlin, Darmstadt and SLAC ('82-'88,'89-'91,'91); PhD at TU Darmstadt 1990. DESY '92-'98 FERMI National Accelerator Lab, '98-'00

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Status of the ITER Project Norbert Holtkamp PDDG Nominee September 11, 2006' - devin


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Status of the iter project norbert holtkamp pddg nominee september 11 2006 l.jpg

Status of theITER ProjectNorbert HoltkampPDDG NomineeSeptember 11, 2006

Norbert Holtkamp, SOFT Symposium, Warsaw 2006


Short bio l.jpg
Short Bio

  • Norbert Holtkamp

  • Born Nov. 23, 1961

  • Studied Physics in Berlin, Darmstadt and SLAC ('82-'88,'89-'91,'91); PhD at TU Darmstadt 1990.

  • DESY '92-'98

  • FERMI National Accelerator Lab, '98-'00

  • Oak Ridge National Lab, Jan '01- Aug ‘06

  • Married, two children (15, 18)

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The spallation neutron source l.jpg
The Spallation Neutron Source

  • SNS is funded through DOE-BES and has a Baseline Cost of 1.4 B$

  • SC linac

  • Single ring ready for 1.3 GeV

  • One target station

  • The peak neutron flux will be ~20–100x ILL

  • SNS had first beam on April 28 and began user operation right after.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Content l.jpg
Content

  • ITER International Organisation (IO)

  • Procurement Sharing

  • Staffing

  • Project Schedule

  • Relationship between IO and Domestic agencies (DAs)

  • Design Review

  • Licensing

  • Summary

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Slide5 l.jpg

The Mission

  • Demonstrate up to steady state fusion power production.

  • Plasma makes 10x more power than needed to run it.

  • Study and optimise plasma behaviour.

  • Have dimensions comparable to a power station.

  • Produce about 500 MW of fusion power.

  • Demonstrate or develop all the new technologies required for fusion power stations, except materials endurance.

  • Require go through licensing and construction.

  • Operate for about 20 years.

  • Cost about €5bn to construct (over 9 years) and €5bn to operate (about 20 years) and decommission.

Cadarache Site

The ITER building

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The genealogy of iter l.jpg
The Genealogy of ITER

Courtesy: S. Chiocchio

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Iter collaboration l.jpg
ITER Collaboration

  • For its size and cost and the involvement of virtually all the most developed countries, representing over half of today world’s population ITER will become a new reference term for big science projects.

  • The ITER project is one of the world’s biggest scientific collaboration.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Slide8 l.jpg

CENTRAL SOLENOID MODEL COIL

VACUUM VESSEL SECTOR

Radius 3.5 m

Height 2.8m

Bmax=13 T

0.6 T/sec

Double-Wall,

± 5 mm

REMOTE MAINTENANCE OF DIVERTOR CASSETTE

Attachment Tolerance ± 2 mm

BLANKET MODULE

HIP Joining Tech

REMOTE MAINTENANCE OF BLANKET

TOROIDAL FIELD MODEL COIL

4 t blanket sector ±0.25 mm

DIVERTOR CASSETTE AND PFCs

Height 4 m

Width 3 m

Bmax=7.8 T

20 MW/m2

Key Technology Projects Completed

In The Design Phase Largely Ending 2001

Cost ~ 600 M$

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Procurement sharing l.jpg
Procurement Sharing

Example for the Procurement Sharing Agreements

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The iter site l.jpg
The ITER site

Magnet power

convertors buildings

Cryoplant buildings

Hot

cell

Tokamak building

Tritium building

  • Will cover an area of about 60 ha

  • Large buildings up to 170 m long

  • Large number of systems

Cooling towers

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Status of the iter organisation l.jpg
Status of the ITER Organisation

  • Presently there are still three JWS: IPP-Munich, JAEA-Naka and CEA Cadarache

    • Worksites will be closed by the end of the year.

    • People already transitioning per many to Cadarache on a interim basis with the intend to become employees as soon as possible.

  • Final ITER agreement underway:

    • Agreement accepted by negotiators April 1st.

    • Documents were initialed May 21st.

    • Documents are to be signed on Nov 21st.

    • After that ITER should become an (interim) legal entity and should execute all function of a legal body.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Iter organisation l.jpg
ITER Organisation

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The scope the schedule and the cost of iter l.jpg
The Scope, the Schedule and the Cost of ITER

  • The Scope: Is clear.

  • The Schedule: Begin construction in 2007 and have first plasma In 2016.

  • The Cost: 3.578 kIUA (~5.000 M€)

    • + 80 kIUA R&D

    • + 188 kIUA Operation/year

    • + 281 kIUA for deactivation

    • + 530 kIUA for decommissioning

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The international organisation as a legal entity l.jpg
The International Organisation as a Legal Entity

  • What do we (IO) need to do:

    • Staff regulations

      • Draft document finalisation proposals to be made to Interim Council (IC).

      • Employment conditions to be clarified.

      • Salary calculation to be finalised (pensions, etc)

    • Project Resource Management Rules

      • Draft document finalisation proposals to be made to IC.

      • Financial regulations and procedures to be written.

      • Budget for 2007 to be presented within these rules.

    • Site support agreement

      • Details to be developed and agreed upon between IO and Host

    • Headquarters agreement

      • Details to be developed and agreed upon between IO and French government

  • What do the parties have to do:

    • Proposals to be agreed directly after signature on November 21, 2006.  very important step for the organisation.

    • Put a provisional agreement in place before final ratification next summer.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Near term technical targets l.jpg
Near Term Technical Targets

  • Technical:

    • Clearing of the construction site and preparation for road and utility connections.

    • Call for tenders of superconducting strands through Domestic Agencies (by end 2006).

    • Technical specifications for call for tenders for fabrication of vacuum vessel, superconducting coils, building & excavation design.

    • Completion of Preliminary Safety Report (submission end 2007).

    • Development of a consistent IPS and Procurement schedule

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Licensing l.jpg
Licensing

  • Is on the critical path of the project to start construction.

  • An English version of the draft preliminary safety report (RPrS) has been provided by the European Participant Team and is under review. Extensive work with a strong support of the EUPT/Host is needed to submit RPrS by the end of 2007.

  • New European regulations for pressurized equipment could significantly affect the design and procurement. Support by experts with the knowledge of technical and administrative practice in construction is urgently needed for clarification of the implementation requirements. These issues is being addressed by an International Codes & Standard Working Group during autumn.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Integrated project schedule l.jpg
Integrated Project Schedule

LICENSE TO CONSTRUCT

TOKAMAK ASSEMBLY STARTS

FIRSTPLASMA

ITER IO

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

EXCAVATE

Bid

TOKAMAK BUILDING

Contract

OTHER BUILDINGS

Complete

blanket/divertor

Construction License Process

Complete VV

First sector

TOKAMAK ASSEMBLY

Install CS

Install

cryostat

PFC

COMMISSIONING

Vendor’s Design

Bid

MAGNET

Contract

PFC

TFC

CS

Last TFC

Last CS

fabrication start

Bid

VESSEL

Contract

First sector

Last sector

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Staffing plan l.jpg
Staffing Plan

Boundary condition

  • Respect the budget envelope agreed in JIA coming still from the FDR: 477 k IUA (=~1800 PPY and ~2760 SPY) during the construction period (9 years).

  • Review the staffing requirement in a few years and after the design review when the resource-loaded schedule is developed.

  • Impact since 2001:

    • 7 Parties not 3

    • Many split procurements

    • Some of the R&D from the FDR is not finished

    • Worldwide: ~ 3000-4000 people working on ITER

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Team build up l.jpg
Team Build-up

  • Truly International Organization with the need of a balanced employment between parties across the organisation.

  • Short term: Smooth transition to new Organization

    • Fill the organisational structure from the top and the bottom.

      • Major influx of staff to Cadarache JWS from Garching and Naka JWSs in September, and remainder in December.

      • Around 25 new members for the “urgent” positions to join Cadarache JWS by September-December.

    • Recruitment by IO also of supporting staff to start December 1st.

    • 150 professional staff by end 2007.

  • Long term: Ensure a smooth transition of staff across different phases of the project: DESIGN-CONSTRUCTION-INSTALLATION-COMMISSIONING-OPERATION

  • ITER within the collaboration has access to 70% of the world population. We need to find the best and the brightest within this pool.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Staff ramp up projection l.jpg
Staff Ramp Up Projection

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Budget profile l.jpg
Budget Profile

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


General roles responsibilities for construction l.jpg
General Roles & Responsibilities for Construction

  • ITER IO

    • Planning/Design

    • Integration / QA / Safety / Licensing / Schedule

    • Installation

    • Testing + Commissioning

    • Operation

  • Parties – DA

    • Detailing / Designing

    • Procuring

    • Delivering

    • Support installation

  • IO and all parties plus Fusion community work together on Exploitation of ITER. ITER IO coordinates and participates in the program (e.g.: TBM).

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The relationship of the international team and the domestic agency l.jpg
The Relationship of the International Team and the Domestic Agency

  • The IO

    • Spends time in the DA and surveys progress with suppliers.

    • Can agree field changes within cost and schedule contingency without consulting IO.

    • Controls the design.

    • Integrates the subsystems.

    • Provides the tools and the manpower to manage the project.

    • Installs and tests the subsystems.

    • Operates ITER.

  • The Domestic Agency

    • Delivers cost, schedule and performance information to the FTL.

    • Provides FTL and staff with an office.

    • Executes the design, procurement and tests.

  • The FTL

    • The FTL submits cost, schedule and performance info each month to the project office (PO).

    • Reports all other necessary and useful information to the PO or the leadership team.

    • Communicates any schedule variance, scope changes, scope variances or potential issues.

    • Guided by the PO the FTL develops a risk matrix in which potential threats are tracked. Estimates on potential cost or schedule variances are given to the PO as well as mitigation plans and strategies that the FTL develops in close collaboration with the DA.

    • Ensures all relevant documents are transmitted to the DA from the ITER Organisation.

    • Ensures consistency of procurement packages, designs prepared by the DA, and ITER specifications.

    • Uses staff from the existing technical divisions in the ITER Organization, preferably those ultimately responsible for the installation, testing and operation of the component.

PDDG

PO

Tech.

Eng.

FTLQAPM

DA

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The design review status l.jpg
The Design Review: Status Agency

  • Today different procurement packages are defined to a different extent.

  • The scope of the ITER design is sufficiently defined so that

    • Their value is / can be estimated

    • Presently a review process is in place limited largely to the International team.

  • The foreseen design review in this context is a continuous process over the next one to two years involving all parties.

  • Goal is to have a 2007 baseline late spring

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The general charge for the design review l.jpg
The General Charge for the Design Review Agency

  • Identify all systems that are not designed yet or are still in the conceptual stage.

  • Starting from the 2001 design report, identify all systems that have integration or technical issues which need to or should be resolved before a procurement specification can be assembled. Identify the issues and a path forward for resolution.

  • Identify areas, concepts and technical designs where recent R&D results indicate a possible performance problem or an unacceptably high manufacturing cost. Identify issues and path for resolution.

  • Identify areas, concepts and technical designs in which recent R&D results would benefit the design technically, schedule or cost-wise.

  • Prioritize open issues with respect to scope, schedule and cost impact and identify and implement solutions in the order of priority. The integration group will provide a risk assessment document that will guide the risk assessment in terms of scope, schedule and cost, and assign a priority number.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Design change integration l.jpg
Design Change Integration Agency

  • Overall budget is fixed -> changes which lead to cost increases, work or designs identified as not finished or any other task that requires budget and was not foreseen before, need to be offset:

    • Quantify the monetary, scope or schedule impact of the change, as well as the man-hours needed for integration and who is supposed to provide them.

    • Clarify the impact on other WBS elements as precisely as possible.

    • Clarify whether the cost increase is a result of changes/conditions imposed by a Party.

  • Design Change Proposals are to be accompanied by:

    • proposed offsets in kind to keep the Total Project Cost (TPC) constant.

    • proposed offsets in terms of scope (scope increase in one WBS versus scope decrease in another).

    • proposed offset using contingency.

    • flagging of imposed changes and information management in order to contact the Party.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006



The technical advisory group l.jpg
The Technical Advisory Group Agency

  • Reports to the DG and PDDG.

  • Members appointed by the DG for 3 year term + 3 year extension.

  • Members supposed to accompany the design review process and the build up of the IO.

  • Advice will cover technical, managerial and organizational aspects to help the DG and PDDG to successfully manage the project.

  • Membership is12-15 and will be recruited from the International science community.

  • The reports will be public.

  • Recommendations will be tracked and reported on in subsequent reviews.

  • At least 2 meetings per year.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Charge for the design progress review dec l.jpg
Charge for the Design Progress Review Dec. Agency

  • Is the physics baseline established and documented well enough? Is the technical baseline consistent with the physics requirements?

  • Is the manpower sufficient for this stage of the project? Is the distribution of manpower appropriate?

  • Is the overall schedule consistent and sufficiently well established for this stage of the project? Is there sufficient schedule contingency?

  • Is the organization of ITER maturing and developing fast enough to be able to launch into construction in the very near future. Which parts of the organization should be improved and how in order to support the construction project?

  • Is the civil construction on track for construction start in 2009?

  • Are the business systems in place to handle scope, schedule and cost of the ITER construction project?

  • Are the safety and civil construction aspects properly addressed for this stage of the project? Where are the highest vulnerabilities?

  • Is the design review process appropriate to address all technical, scope, schedule and cost aspects of the project? How can it be improved?

  • All other general recommendations

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


The design progress review dec 12 15 l.jpg
The Design Progress Review, Dec 12-15 Agency

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Participation in iter l.jpg
Participation in ITER Agency

  • Attract the best qualified people to the IO - send us your CV (see ITER web site).

  • Share responsibility for success with the Domestic Agencies by ensuring joint aim is mutual success on time and within budget.

  • Involve all Parties’ fusion researchers actively in preparing for ITER operation, as well as in developing diagnostics, heating and current drive systems, and test blanket modules.

  • Encourage researcher’s ownership of the ITER design by participation in the design finalisation process through the design review.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Role of iter io outside of construction l.jpg
Role of ITER IO Outside of Construction Agency

  • Test Blanket Modules

    • IPC-8 in Goa asked for establishment of Ad hoc group on TBM programme.

      • Terms of reference were prepared by DGN/ITER.

      • Members are nominated.

      • First meetings have occurred.

    • All parties confirmed interest to participate in TBM testing program, which is outside of ITER construction.

      • Agreed to prepare qualification programs

      • Cooperate to finalization of optimized test program for 6 TBM’s / 3 ports.

    • Each party prepares proposal with:

      • clarification of Party-ITER mutual obligations.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Conclusions l.jpg
Conclusions Agency

  • The ITER Organisation is imminent and final preparations are underway to make it effective at the earliest opportunity.

  • The Parties are aware of their budget and staffing obligations and are making progress in satisfying them.

  • The project team is coming together in Cadarache.

  • The design review has begun in September which will strengthen involvement of all stakeholders, DAs and project team members.

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006


Summary l.jpg
Summary Agency

  • ITER organisation is still in a transitional phase.

  • Very important to establish Legal entity as soon as possible to effectively execute all task of a construction project.

  • Recruiting and strengthening the team is a prime concern.

  • Holding cost and schedule is important to gain trust with the parties and thrust for the project.

  • Executing the Design Review effectively to establish new baseline and involve world community is necessary

  • A whole bunch of luck will be required too…

Norbert Hotlkamp, SOFT Symposium, Warsaw 2006