GEORANGE Är Järn Guld för Pajala ? 2 april 2009 PowerPoint PPT Presentation


  • 61 Views
  • Uploaded on
  • Presentation posted in: General

GEORANGE Är Järn Guld för Pajala ? 2 april 2009. Planned Iron Ore Mining in the Pajala/Kolari Region. Karl-Axel Waplan MD of European Operations. Key events. Infrastructure. MOU signed with operator as well as port authorities to develop Kemi port for the initial tonnage

Download Presentation

GEORANGE Är Järn Guld för Pajala ? 2 april 2009

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Georange r j rn guld f r pajala 2 april 2009

GEORANGE

Är Järn Guld för Pajala ?

2 april 2009

Planned Iron Ore Mining in

the Pajala/Kolari Region

Karl-Axel Waplan

MD of European Operations


Key events

Key events

Infrastructure

  • MOU signed with operator as well as port authorities to develop Kemi port for the initial tonnage

  • MOU signed with GIIC on long term shipment of concentrate from the Pajala/Kolari area

  • Consortium organized to support the development of the Rail transportation to port; NRI, Bombardier and VR

  • EPA Filed April 1, 2009

  • Application to the Border River Commission to be filed May/April

2


Mou with giic

MoU with GIIC

Contractual YearAnnual Basic Quantity (in WMT)

2011 250,000

20121,500,000

20132,000,000

2014 onwards3,000,000


Georange r j rn guld f r pajala 2 april 2009

Investment Highlights

Investment Highlights

  • Focus on Tapuli, Hannukainen, Stora Sahavaara and Pellivuoma

  • Management priority is developing early cash flow

    • start up of Tapuli mine with Kaunisvaara mill

  • Existing infrastructure support early production of up to 2-3 Mt pa

  • Resource base growing

  • Staged growth of production up to 8-10 Mt pa of iron ore products

4


Georange r j rn guld f r pajala 2 april 2009

●Kaunisvaara


Tapuli fast track to cash flow

Tapuli: Fast Track to Cash Flow

Fast Track Tapuli

Open-pittable resource

Existing infrastructure can take Tapuli’s full production with minor upgrades

Preliminary studies suggest lowest CapEx, highest IRR and quickest payback

Synergies with nearby Stora Sahavaara and Pellivuoma projects


Tapuli mine

Tapuli mine

Open cast mine

Minimum operation time 10 years

Verified resource 65 Mton (NI 43-101)

Additional reserves ca 40 Mton

Blasting daytime, ca 1-4 times/week


Georange r j rn guld f r pajala 2 april 2009

  • Planned industry layout:

  • Mine

  • Mill

  • Service facilities

  • Office

  • Waste rock deposit

  • Tailings storage facility

  • Access & transportation roads


Georange r j rn guld f r pajala 2 april 2009

Artists impression of the mine during operation


Georange r j rn guld f r pajala 2 april 2009

Waste rock

  • A total of 250 Mton will be mined

  • May be used for construction purposes

  • Area ca 330 ha

  • Height ca 75 m


Anrikningsprocess

Anrikningsprocess

Planerad genomsnittlig produktion

År 1: 3 Mton malm, motsvarande ca 1 Mton Slig

År 2-10: 10 Mton malm, motsvarande ca 3 Mton Slig

Ansökan avser 20 Mton per år

Process

Krossning, malning, magnetseparering, avvattning och möjligen torkning

Inget flotationssteg


Mill tailings storage

Mill tailings storage

  • Total tonnage c. 70 Mton

  • Total area c. 340 ha

  • Final height c. 60 m

ca 2-3 m


Efterbehandling

Efterbehandling

Byggnader tas bort och vägar återställs. Ledningar kvar i marken.

Gråberg täcks med morän och vegeteras. Sandmagasin vegeteras. Gödningsmedel kan behöva tillföras.

Dagbrottet bildar en sjö


Transport

Transport

  • Initially truck (60 ton net) to Kolari – rail to Kemi

  • Extension of railroad to Kaunisvaara being investigated

  • 290 return transports per day (c. 12 per hour)


Transloading station alternatives

Transloading station alternatives


Georange r j rn guld f r pajala 2 april 2009

Rail & Port Options

Narvik

Pajala

Kolari

Existing rail link

Kemi

Kalix

Luleå

17


Logistics key issues

Logistics – Key issues

Infrastructure

  • Initial transportation Kaunisvaara – Kolari on road

  • Long term solution Kaunisvaara – Kolari to be railroad

  • Increase capacity on rail from Kolari region to Tornio up to 10 Mt

  • Develop Kemi port initially for 3 Mt and up to 10 Mt in case Kemi is the only port going forward

  • Kemi port dredging to enable access by feasible vessels

18


Transportation from kaunisvaara tapuli to finnish rail

Transportation from Kaunisvaara/Tapulito Finnish Rail

Infrastructure

  • 2011 – 2013 trucking

  • Rail alternative is studied

  • Alternative studies on pipeline and conveyor belt in progress

  • Future solution operational from 2012/13

  • Loading station south of Kolari, land available

  • Rail – Necassary

19


Production timeline estimate

Production Timeline Estimate

Northland’s Future Growth

2013 / 2014

  • Tapuli at full production 1.5 Mt Concentrate

  • Pellivuoma – ramps up production to 1.5 Mt of Concentrate

  • Stora Sahavaara – begin production of 2 Mt of Concentrate

  • Hannukainen begins production and ramps up to 2-3 Mt of DR pellet feed

2012

  • Tapuli – ramp up production to 1.5Mt Concentrate

  • Pellivuoma – begin production of Concentrate

2011

  • Tapuli – Begin production of Concentrate

2010

  • Tapuli – Begin construction

Production:

1-2 Mt/y 3 Mt/y 8-10 Mt/y

20


Summary nri projects

Summary NRI projects

  • Staged development to build the assets in Sweden and Finland

  • Initial cash flow will be the base to increase production and employment

  • Joint effort necessary - NO “Finnkamp”

  • The projects will create employment within NRI as well as support structures, services etc

  • Employment will be created in the whole region – in both countries


Summary logistics

Summary Logistics

  • Rail Kaunisvaara – Tornio with capacity + 8 Mt necessary for development of the projects

  • Rail from Kaunisvaara to be operational from 2013

  • Port development Kemi ready 2011

  • Dredging Kemi ready 2011/12

  • Ice breaker capacity must be expanded