1 / 46

STONES DRILLED & PINNED TO BEDROCK WITH METAL RODS (Two case studies) by Dave Derrick

STONES DRILLED & PINNED TO BEDROCK WITH METAL RODS (Two case studies) by Dave Derrick. THE EIGHTEENMILE CREEK PROJECT PHASE I CONSTRUCTED AUG-SEPT 2003 by Dave Derrick. At higher flows energy is vectoring straight into 14 ft tall eroding bank. Pix by Mark Seider.

dbrenda
Download Presentation

STONES DRILLED & PINNED TO BEDROCK WITH METAL RODS (Two case studies) by Dave Derrick

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STONES DRILLED & PINNED TO BEDROCK WITH METAL RODS(Two case studies)by Dave Derrick

  2. THE EIGHTEENMILE CREEK PROJECT PHASE I CONSTRUCTED AUG-SEPT 2003by Dave Derrick

  3. At higher flows energy is vectoring straight into 14 ft tall eroding bank Pix by Mark Seider

  4. My sneaker Close-up of large stones, these were hand selected & are 3 ft by 3 ft with two sides flat.

  5. Tough to specify stone. Call some quarries to see what is available. Stone might be called “ledge rock, shelf rock, flats, or big flats”. Thickness will be determined by how it is fractured & breaks out during blasting. Must be fairly flat on two sides. Inspect stone, then spec. minimum measurements, say 2 ft x 3 ft by 4 ft (can be exceeded, but cannot be smaller). When ready for construction go to the quarry & hand pick the stone.

  6. Schematic detail of Great Wall with backfill & plantings (does not include LUNKERS or keys) Toe stones are placed, drilled through stone & 1 ft deep into underlying bedrock, metal rod is driven into the hole, excess cut

  7. Stepped back design allows fishing folk to use different levels Pix by Derrick Looking DS at the Great Wall, it is approx. 300 ft long, notice upper bank is not smoothed, seeded, or planted yet

  8. Looking DS, placing the first row of stones on bedrock

  9. Detail of Great Wall of Newfane & Turbidity Curtain from project Plans & Specifications Only the bottom row of stone is drilled & pegged to bedrock Shot rock used for foundation

  10. Hand drilling completely through the stone & one ft deep into bedrock. Stones now pinned with a 4 ft long, one inch diameter rebar (not cut off yet)

  11. Drilling completely through the stone & one ft deep into bedrock. Stones now pinned with a 4 ft long, one inch diameter rebar (not cut off yet)

  12. Bottom row of stones drilled and pinned with 1 inch diameter rebar

  13. Drilling completely through the stone & one ft deep into bedrock. Stones will be pinned with a 4 ft long, one inch diameter rebar. Shot rock foundation in foreground. Flow from dam aimed right at wall!! 8” Surge stone base for large walk-able bank protection

  14. Erosion Control Blankets supplied by Indian Valley Industries, Inc. Coir 700 mat (700 grams per square meter). 100% spun coir, with an open area of 50%. 100% biodegradable.

  15. Pix by Derrick Looking US. 5 growing seasons later. Riparian plantings are robust, June 7, 2009. Scale, daughter Dana is 5 ft 2”

  16. Since construction this project has been used extensively for public outreach (adult and children) & as a teaching platform for fellow professionals.

  17. I got to fly in the DEC/State Police helicopter. Looking downstream, red line is the Great Wall of Newfane - Feb 2, 2005

  18. Peaceful co-existence “combat” fishing

  19. BIG THAW PLUS RAIN = HIGH STAGES Feb 6, 2008

  20. Looking US @ the Great Wall. Power generating dam in background. Post-Project-18 Mile Creek, Phase II-Feb 6, 2008, Pix-Vic

  21. PROJECT CONSTRUCTED June 2006 CHAUTAUQUA CREEK ICE DAMAGE REDUCTION PROJECT –Near its mouth @ Lake Erie

  22. CHAUTAUQUA CREEK ICE DAMAGE REDUCTION PROJECT –Near its mouth @ Lake Erie • Severe scour from ice and high flow velocities on the right descending bank had resulted in an overwidened section of stream. • Mid-channel sediment bars, mouth of creek @ Lake Erie clogged • No holding areas or habitat for steelhead • A heavily used public fishing section of the stream

  23. Single Stone Bendway Weirs (pegged to bedrock), spaced 50 ft apart NEED PLANS & SPECS Trench Stone (drilled & pegged) Stacked Stone Wall (bottom row drilled & pegged) Key Sloped Stone using “Big Flats”, most 5 ft by 5 ft by 2 ft thick Key Key Flow Key Key Key Key

  24. DRILLING & PEGGING TOE STONES & SINGLE STONE BENDWAY WEIRS WITH METAL RODS INTO BEDROCK

  25. Construction June 2006. Looking DS @ 2 hoes jack hammering a footer trench through a layer of weathered stone. Would not need to do this if stone was not weathered. Pix by derrick

  26. 7 ft long, 1 5/8 inch diameter solid rods for pegging stone to bedrock. Pix by Joe Galati

  27. Dave Spann of Chautauqua County Soil & Water Conservation District with a 7 ft long, 1 5/8 inch diameter solid bar. Dave did everything from writing the grant to providing extraordinary project management. On time & under budget!!!! Pix by Joe Galati

  28. This type of drill needs a flat solid foundation. Construction June 2006. Looking DS. Drilling 2 inch holes to peg stone to bedrock. The 2 inch bit was the only one they had on hand… Pix by Joe Galati

  29. Construction June 2006. A good hole in a footer stone in the jackhammered trench. Pix by Joe Galati

  30. Construction June 2006. Looking US. Metal pinning rods not cut off yet. Pix by derrick

  31. Construction July 2006. Cut off solid metal rod in drilled hole pinning stone to underlying bedrock Pix by Joe Galati

  32. Construction June 2006. Looking US during placement of “big flat” stones on the backfill/filter stone. Pix by derrick

  33. EVERYBODY WANTS COSTS, FOR ONCE WE HAVE COSTS!! Big thanks to Dave Spann, Chautauqua County Soil & Water Conservation District for these figures.

  34. CONSTRUCTION COSTSDoes not include admin, design, permitting, program management, construction oversight, or plant installation Total: $200,584.

  35. CONSTRUCTIONCOMPLETE

  36. May 17, 2007. Looking DS @ top bank willow poles & other plantings Pix by Joe Galati

  37. Looking upstream at the SINGLE-STONE BENDWAY WEIRS

  38. Aug 31, 2006, looking US at two pegged to bedrock Single-Stone Bendway Weirs in the stacked stone wall section. Only bottom stones in wall are pinned Pix by derrick

  39. Aug 29, 2006 -high water- Looking US, note dead water near toe & thalweg location near arrow, all due to the Single Stone Bendway Weirs Photo by Dave Spann

  40. Looking downstream at the SINGLE-STONE BENDWAY WEIRSHIGH WATERAUG 29, 2006

  41. Aug 29, 2006-high water-looking DS Photo by Dave Spann Note rooster tail defining right edge of high velocity water, slow smooth water surface near bank.

  42. Mar 14, 2006. Looking DS. Close-up of two submerged Single-Stone Bendway Weirs. Note dead water between weirs Pix by Joe Galati

  43. 16 MONTHS AFTER CONSTRUCTIONNOV 2007

  44. Nov 8, 2007. Looking DS. Good thalweg alignment off the ends of the Single-Stone Bendway Weirs Pix by Joe Galati

  45. This PowerPoint presentation was developed & built by Dave Derrick. Any questions or comments, call my personal cell @ 601-218-7717, or email @ d_derrick@r2d-eng.comEnjoy the information!!

  46. Cleophus napping in the sun

More Related