Blue print for throughput enhancement on HDN

Blue print for throughput enhancement on HDN . B.V.L.Narayana SPTM/ RSC/ BRC. Critical issues and redressal. Constraints CAPACITY CONSTRAINTS ON HDN ROUTES Terminal constraints Overcome by Investments in Strategic capacity expansions. High density network. Consists of Seven routes

daphne
Download Presentation

Blue print for throughput enhancement on HDN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Blue print for throughput enhancement on HDN B.V.L.Narayana SPTM/ RSC/ BRC

  2. Critical issues and redressal • Constraints • CAPACITY CONSTRAINTS ON HDN ROUTES • Terminal constraints • Overcome by • Investments in Strategic capacity expansions

  3. High density network • Consists of • Seven routes • Six feeder routes • Carries • 76% of freight GMT • 71% of passenger and freight GMT • Accounts for 28% of route KMs

  4. HDN –routes and feeders

  5. ISSUES CONSIDERED • GROWTH PATTERNS OF MAJOR COMMODITIES FOR ALL ROUTES EXCEPT NDLS-HWH and NDLS-BB • STEEL • COAL • CONTAINERS • IRON ORE • PORT CONNECTIVITY • LRDSS PROJECTIONS FROM 2005-06

  6. Eleventh plan targets

  7. Methodology • Collate all line capacity statements for all HDN routes • Project capacity utilization till 2011-12 • Identify critical sections • Validated by projections from LRDSS • Review with zonal railways • Estimate level of investments

  8. Recommendations • 124 works • 14185 crores investments • Over and above DFC projects • Investment needs for 25t Axle load separately done

  9. LRDSS • an objective tool for planning and prioritizing capacity enhancement projects based on traffic projections over the next two decades. • Started in 1994 • Strategic tool for long term investment planning

  10. LRDSS • The system consists of a comprehensive set of modules which cover different aspects of the investment analysis viz:-  • 1)Facility Performance Module • 2)Market Analysis Module • 3)Traffic Forecasting Module • 4)Traffic Assignment Module • 5)Benefit Cost Analysis Module • 6)Terminal Analysis Module • 7)Multi-modal Corridor Analysis Module

  11. LRDSS • Inputs required • Production and consumption forecasts • From planning commission • Ministries • Traffic surveys • Market surveys for customer sensitivity • Cost data • Field Level Data To Simulate Train Running On a Section

  12. THANK YOU