An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Engineering and InspectionI-75, from Charlotte County Line to I-275Freeway Management SystemFPID 414730-1-62-01, 414732-1-62-01, 414736-1-62-01 September 23, 2011

  2. Awareness/Approach to Project Understanding of Scope of the Project Identification of Unique Project Issues Innovative Concepts

  3. Understanding Project Scope Project Overview • Design Build Contract • $30 Million • 760 days • Three Financial Project ID’s • 56 miles, from Charlotte County Line to I-275 • Final Phase of the District One I-75 FMS • Design, furnish, install, integrate and test ITS field devices • Provide for a redundant system between SWIFT and Satellite Traffic Management Center (STMC)

  4. Understanding Project Scope Primary Responsibility of the CEI • Act as extension to FDOT staff • Proactively manage the work • Anticipate and address project issues • Coordinate all aspects of design and construction • Review/ analyze CPM schedules • Provide interpretation of contract documents • Enforce contract requirements and implement CPPR • Operate in accordance with FDOT procedures (CPAM)

  5. Understanding Project Scope (Design) • Detailed Reviews for 60%, 90% & Final (100%) • Conformance with Design Build Technical Proposal - “Book of Promises” • Conformance with RFP & MTRs • Hardware/ Software Compatibility • Review/ Resolution of Potential Integration Issues • Compatibility/Coordination with Future Projects • Confirm existing fiber (I-75/SR 70 to STMC) • Provide Clarifications - RFP vs. MTRs • Permit Acquisition

  6. Understanding Project Scope (Design) • ERC utilization • Plan submittals • Device Cut Sheets • Shop Drawings • Other • Field Assessments • ITS field device locations • Potential underground utility conflicts • Review of Right of Way limits • Review of existing slope conditions • Site survey

  7. Understanding Project Scope (Construction) Primary Components of the Work • Fiber Optic Communications Infrastructure • Conduit, locate system and enclosures/ boxes • Two conduits (1 for FOC and 1 spare) • Separate conduit for electric • Install eight (8) feet inside northbound right-of-way fence • Seven (7) bridges potentially requiring new bridge mounted conduit Braden River Crossing Charlotte Harbor Crossing

  8. Understanding Project Scope (Construction) • Fiber Optic Communications Infrastructure • Locate existing utilities (Sunshine One Call) • Bore logs to verify horizontal locations & depths • Recommend field adjustments to avoid unforeseen conflicts • Update plans to ensure accuracy of as-builts • Conduits “proofed” to ensure continuity and absence of obstructions • OTDR testing

  9. Understanding Project Scope (Construction) • Dynamic Message Signs (DMS) • 25 shown on Concept Layout • 24 cantilever structures, 1 half-span truss structure • Ensure proper height (19.5’) • Allied’s structural inspector will oversee operations of upright and sign

  10. Understanding Project Scope (Construction) • Drilled Shaft Installations • 26 drilled shafts @ 25 DMS structures • DBF to perform sub-surface investigations, analysis & design • DBF to develop foundation plan • Drilled shaft logs to be submitted within 24 hours • Cross-hole sonic logging (CSL) must be performed on at least 30% of the shafts • Utilization of Allied’s Drilled Shaft QAP

  11. Understanding Project Scope (Construction) • Highway Advisory Radio System (HAR) • 10 transmitter stations and 20 flashing beacon signs • Capable of broadcasting unique message/ synchronized global message • 800-foot spacing between signs • 1640 AM frequency/ FCC licensing process • Microwave Vehicle Detectors (MVDS) • Installed at approximate one-mile intervals (mainline) • Half-mile within 2 miles of each interchange and at each off-ramp • Must report for eight (8) lanes of travel for volume, occupancy & speed

  12. Understanding Project Scope (Construction) • Road Weather Information System (RWIS) • Two (2) to be installed along the project • Placed outside clear zone limits • Fenced enclosure for device and cabinet • Power/ Emergency Generators • DBF to provide all power services to devices • Diesel-electric generator units required at all power service point locations providing power; • DMS locations • Communications backhaul locations

  13. Understanding Project Scope (Construction) • CCTV (Closed Circuit TV) • Installed at approximate one-mile intervals (70 +/-) • Complete coverage of both directions of I-75 traffic, on/off-ramps, interchanges (video site survey) • Shall provide for view of all DMS messages and HAR beacons • Cannot be installed in the medians or top side of overpass slopes • Pole height cannot exceed 65 feet • Locate more than 50 feet away from any high mast light pole • Pre-stressed concrete pole with grounding, lightning protection, and lowering devices

  14. Understanding Project Scope (Construction) • ITS Inspection • CEI check lists based on • Final Plans/ RFP/ MTR requirements • Standards/ Specifications/ NEC • FDOT 780 Supplemental Specifications • Inspection Guidelists • Components to be QPL/APL approved • Splice and pull box conformance • APL/ITS certified products • Proper sizing of products • Use of expanded RTVM for field inspections

  15. Understanding Project Scope (Construction) • MOT/ Safety • MOT Certified Personnel/ Interstate (I-75) experience • Minimize traffic disruptions & maximize safety • Ensure advance coordination for lane closures & nighttime operations (PIO, Law Enforcement & Emergency Services) • Full span truss installation – Charlotte FMS • Conformance with MUTCD & FDOT standards • MOT & Safety as agenda item @ project meetings • Critical during DMS installation & bridge work (limited ROW) • MOT verification inspection each day prior to leaving site

  16. Understanding Project Scope (Construction) • Environmental Concerns • Scattered wetland presence along northbound ROW • Potential for endangered species • Gopher tortoises • Low-lying areas with standing water which could impact equipment access • NPDES inspections (weekly, ½”) • Permit conformance • Erosion Control Plan • Performance Turf Specifications • Mowing requirements

  17. Understanding Project Scope (Documentation) • CEI Reporting • Daily Reporting of Construction Activities/ Site Manager • Verification Testing Reports & LIMS Entry • MOT Reviews & Verification of Contractor’s Reports • CPM Reviews • Digital Progress Photos & Log • Monthly FDOT Project Status Reports (CSRS) • Meetings Minutes & Follow-Up Action Items

  18. Understanding Project Scope (Documentation) • DBF Submittal Tracking • Design Submittals • Cut Sheets/ Shop Drawings • CPM Schedule/ Updates • Schedule of Values • Field Equipment Operational Manuals • Software Manuals/ Device Protocols • Test Procedures and Results • Training Manuals • 270+ Design Submittals - Charlotte FMS • We will prepare a submittal tracking log in advance of project start & track all submittals via ERC

  19. Understanding Project Scope (Documentation) • Project Close Out/ Warranties • Timely submittal of all close out documents • As-Built plans • Bore Logs/ GPS locations • Spare Parts (as required) • Timely/ Accurate Final Estimate • Early FE submittal on Charlotte FMS and no procedural errors • Warranties • Pre/ post-warranty meetings • Ensure warranties per contract/ technical proposal

  20. Understanding Project Scope (Documentation)

  21. Understanding Project Scope (TMCs) • Satellite Traffic Management Center (STMC) • New Gigabit Ethernet switch • New SunGuide servers • SunGuide Software (FDOT furnished) • Video Wall Expansion • 12 new cubes • Video wall controller • 5 new workstations • Electrical wiring • SWIFT Center • Video Wall upgrade to handle new CCTVs • Provide standby Gigabit Ethernet switch • Operations • STMC backup to SWIFT

  22. Understanding Project Scope (Testing & Integration) • MTR requires: • Preliminary Integration Plan • 30 days prior to Pre-Integration Meeting • Pre-Integration Meeting • Discuss Preliminary Integration Plan • Integration Plan • 90 days prior to Integration Work • Testing • Factory • Stand-Alone • Subsystem • Operational Test • Burn-in

  23. Understanding Project Scope (Testing & Integration) STMC SHI HHI • Server Software • SunGuide(SWRI) • Keys to Successful Integration: • Start From Day 1 (Design) • Good System Understanding • Main Components • Software • Hardware • Interfaces • Software/Software Interface (SSI) • Software/Hardware Interface (SHI) • Hardware/Hardware Interface (HHI) • Testing • Right Type • Functional, Operational • Right Number • When and Where • Clear • Well Defined Metrics • Well Defined Pass/Fail Criteria • Work-stations • Servers SSI Plans • Network Exist. Field Devices New Field Devices • FieldDevices • FieldDevices HHI Keys • ExistingNetwork SWIFT • Servers • Work-stations • SunGuide(SWRI) • MicrosoftCluster Existing F&I by DBF Furnished by FDOT

  24. Unique Project Issues F&I by Southwest Research Institute (SWRI) • Microsoft Cluster • STMC / SWIFT / SunGuide • First deployment of SunGuide in a back-up mode at STMC • Testing of STMC back-up functionality without disrupting SWIFT operations • TMC software is normally integrated at the end of the project which could impact the schedule. • Two contractors (SWRI and DBF) preforming time critical interdependent work. • MOT • HARB at Erie Road overpass will require MOT (lane closures) for installation as well as maintenance. F&I by Design Build Firm • Oracle Data Guard

  25. Unique Project Issues Steep Slopes • Steep Slopes • DMS • North of the Braden River • North of West River Road • Difficult installation • Lane closures during installation and maintenance. • No pull boxes in slopes - will make conduit transition from underground to bridge mount difficult • Conduit 8’ from Fence • Flooding areas could impact maintenance / reliability • Numerous crossing of wet ditches Fence Proposed Conduit 8’ FromFence DBF may propose

  26. Innovative Concepts • Use of FDOT ERC system for all submittals • Expansion of the RTVM (Traceability Matrix) • Include additional project requirements such as NEC • Expand verification method (Factory, Stand-alone, Subsystem) • Develop comprehensive field check lists using the RTVM • Verification of as-built and ITSFM tool sheets with sub-foot accuracy equipment • Specialty staff only as-needed • STMC agreement to provide large meeting room to reduce CEI field office costs • Project Share Site for exchange of large files

  27. The Allied Team Allied * AIM * Genesis * Media Relations Group * Scheda * URS Proposed Staffing Quantity Proposed Availability of Staff Qualifications/ Certifications of Staff Quality/ Experience on Similar Projects Team’s Past Performance on Similar Projects

  28. FDOT District One Jim Nichols Construction Project Manager Katherine Duvall/ Mark Roberts Traffic Operations Proposed Staff Quality Assurance Kristina de Moya, P.E. Allied Joe McConnell, P.E. URS Southern Barry Wilson, P.E. Genesis Principal-In-Charge/ Project Manager Paula McQueen, CPA Allied Senior Project Engineer Vay Scott, P.E. Allied Sr. ITS Engineer Alex Mousadi, P.E. URS Southern Project Administrator Lisa Propps Allied Secretary/ RCS Kim Grebe Allied ITS Engineer (Field) Matt Cousins URS Southern Specialty Staff Public Information Officer Alicia Gonzalez (MRG) Ken Nelson (AIM) CEI Environmentalist Sarah Johnson, MS (Scheda) Professional Surveyor Bob Potter, PSM (AIM) Building Inspector Mark Smalley (Allied) Sr. ITS Inspector Carmon Thompson AIM James Randy Cosby URS Construction Services CEI Sr. Inspector Ted Garcia Allied Robert Walker Genesis Contract Support Specialist Chris Morris Allied Additional Inspection Matt Hicks, Densel Landrum Dean Greathouse, Mark Walters Allied Tony Cognina Genesis CEI Inspector Kenneth Hilton Genesis ITS Inspector Ron Horn URS Construction Services

  29. Quantity/ Availability Proposed • Key staff full-time through design • Core inspection/field staff during construction/testing • Specialty staff as-needed • Reduced staff during Operational Period/ Burn-in • All team members 100% available (February, 2012) 34,875 Man-hours

  30. Qualifications/ Certifications of Staff • Vay Scott, P.E. - Sr. Project Engineer • 28 years experience on FDOT projects • Florida Licensed Professional Engineer • Significant CEI management experience • Lakeland CCTV Installation Project • QA Manager for Charlotte FMS and Charlotte ATMS Projects • Proactive approach to issue identification and resolution Early completion of complex US 92 project in D7!

  31. Qualifications/ Certifications of Staff • Lisa Propps, E.I. - Project Administrator • Degreed Civil Engineer • Over 14 years of CEI experience • PA on $230 Million Tampa Airport Interchange • Oversight of project staff of 18 • Included ITS device (40+) and fiber installations • PA on District 7 Push Button Traffic Operations Project • $25 Million contract/ 33 Task Work Orders assigned to date • Design Build contracting method Responsible for Final Plan reviews of 33 District Wide TWO’s

  32. Qualifications/ Certifications of Staff • Alex Mousadi, P.E., Sr. ITS Engineer • Electrical Engineer • Over 21 years experience in the ITS industry • Experience encompasses design, construction, testing & integration • Key projects include; • 23 miles of I-75 for the Charlotte FMS for FDOT District 1 • Roadside Animal Detection System (RADS) for FDOT District 1 • 250+ interstate ITS work in Florida (I-4, I-75, I-275, I-595, I-95) • I-595 PPP in District 4 • Participated in development/integration of eight (8) TMC’s nationally • Lead system designer & integrator for Tampa Bay SunGuide Ph 3 Diverse background allowing for prompt and efficient issue resolutions!

  33. Qualifications/ Certifications of Staff • Matt Cousins, ITS Engineer (Field) • BS in Electrical Engineering, MS in Civil Engineering • Six years experience in electrical & traffic engineering • Three years experience dedicated to ITS planning & design • Design background includes fiber optics, CCTV, DMS radar detection sub-systems, and power distribution • Recent SunGuide experience includes; • 23 miles of I-75 for Charlotte FMS, District 1 • Tampa Bay FMS Phase 3 (50 miles of I-4, I-275 and Skyway Bridge) • FTE SunNav West (80 miles of Florida Turnpike) Responsible for resolution of integration issues @ SWIFT- Charlotte FMS

  34. Qualifications/ Certifications of Staff • Chris Morris– Contract Support Specialist • Over 13 years of construction inspection experience for FDOT • Qualified CSS, Assistant PA, Sr. Inspector • CSS/ Assistant PA on Charlotte FMS • IMSA level I & II, drilled shaft certified • Available to assist in the field as needed • Inspected 450 miles of fiber optic interstate installation nation-wide Allied’s Secret Weapon

  35. Qualifications/ Certifications of Staff • Carmon Thompson– CEI ITS Senior Inspector • Extensive experience in traffic signal & intersection design/inspection • Sr. ITS Inspector for: • City of Naples ATMS • Collier/ Lee FMS (98 miles along I-75) • Charlotte County FMS (23 miles along I-75) • Roadside Animal Detection System (RADS) • Drilled shaft, fiber and ITS device installation experience • Certifications include; • IMSA Level I and II, Traffic Signal Inspector • FDOT Advanced MOT 34 years in working with FDOT District 1 (direct employee and CCEI)

  36. Qualifications/ Certifications of Staff • Teddy Garcia– CEI Senior Inspector • 17 years construction inspection experience • Charlotte County ATMS • Charlotte County FMS • 23 miles along I-75 • IMSA Level I & II • Drilled shaft, fiber and ITS device installation experience Successful track record in working with Sarasota Operations

  37. Qualifications/ Certifications of Staff • Specialty Inspectors • Matt Hicks / Dean Greathouse (Drilled Shaft QA) • Mark Smalley (Building/ Structural Inspector) • Additional Resources • Scheda Ecological Associates (Sarah Johnson, MS) • AIM Engineering and Survey (Bob Potter, PSM) • Media Relations Group (Alicia Gonzalez, Primary PIO) • Ken Nelson (AIM, Back-up PIO)

  38. Quality/ Experience on Similar Projects

  39. Quality/ Experience on Similar Projects

  40. Team’s Past Performance on Similar Projects • Charlotte County ATMS • Returned $80,000 in CEI Fees • Final Grade of 4.2 • Set the standard in communication, coordination & proactive issue resolution • Charlotte County FMS • Returned $50,000 in CEI Fees • Final Grade of 3.9 • Continued to establish new standards in communication, coordination & proactive issue resolution

  41. Team’s Past Performance on Similar Projects • Strong QA Program = Quality services • QA Team: • Kristina de Moya, P.E. (Allied) • Joe McConnell, P.E. (URS) • Barry Wilson, P.E. (Genesis) • 50 years CEI experience with significant ITS installations • Reviews per the Scope of Services to include; • Quality & quantity of personnel assigned • Quality of project records • Communication & feedback with FDOT

  42. Other Considerations Communication Abilities Commitment to Satisfy Department’s Needs

  43. Communications Abilities • Public Information • Coordination with Cindy Clemmons from day one for all PI activities • Two prong approach: day to day PI issues/overall communication of benefits (awareness and education) • Coordination with all local PIOs in order to have consistent and strong project message • Maximize existing communication resources available • Message the project benefits in real-time

  44. Communications Abilities • PIO - Proven Effective on Charlotte FMS • MPO presentations • Sarasota-Manatee Transportation Incident Management Team presentation and engagement • Work with 511 • Newsletter for local and state publications on progress • Opportunity to showcase District One at ITS Florida • Bring in media early Media coverage helps raise public awareness for ITS program in the community.

  45. Communications Abilities • Effective Communications with Stakeholders • Began in advance of CEI advertisement • FDOT - Traffic Operations, Sarasota Operations, District Construction, District PIO, SWIFT Center • Manatee County and Sarasota County • Attended DB Pre-Proposal Meeting • Stay involved in DBF Selection Process • Facilitate Project Meetings • Action Item Log • Thorough Documentations CEI Performance Evaluation: Provided necessary project information to all project stakeholders – 5! “Excellent communication between CCEI staff, contractor, Department & local municipalities”

  46. Commitment to Satisfy Department Needs • DRB letter recognizing the Allied team for their outstanding performance on Charlotte FMS • Nominated for FTBA Excellence in Construction Award • Nominated for ITS Florida Outstanding Achievement Award

  47. Commitment to Satisfy Department Needs • Proven abilities to interpret the contract and resolve issues at project level • Proven knowledge of technical issues • Proven abilities to properly document and inspect the work • Proven communication abilities • Proven ability to manage CEI and construction dollars • Proven Commitment to FDOT Experienced Team! ITS Allied!