1 / 14

DPW Quarterly Report

DPW Quarterly Report. 4th Quarter FY 2016. Projects. $11,485.35 for Drainage work done throughout the island. Jobs Include: 12 th Street. Dog Park Improvements. $15,154.19 Inlet Ave Parking Lot Resurfacing. $21,595.10 DPW Building Improvements. $116,064.00 Street Resurfacing.

cainj
Download Presentation

DPW Quarterly Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DPW Quarterly Report 4th Quarter FY 2016

  2. Projects • $11,485.35 for Drainage work done throughout the island. Jobs Include: • 12th Street

  3. Dog Park Improvements

  4. $15,154.19 Inlet Ave Parking Lot Resurfacing

  5. $21,595.10 DPW Building Improvements

  6. $116,064.00 Street Resurfacing

  7. Maintenance • Facilities, Restrooms & Parks: Cost $48,458.59 • Landscaping: Cost $61,384.91 • Street Trash: Cost $32,093.24 • Beach Trash & Recycling: Cost $33,814.62 • Signage: Cost $1511.40 • Beach Swings,Mobi-Mats,&Crossovers: Cost $1547.37 • Drainage: Cost $11,485.35 • Road Maintenance: Cost $22,211.00 • Beach Maintenance: Cost $7,336.98

  8. Memorial Day: Cost $1175.00 Orange Crush $4639.03 Rainbow Festival $377.60 Beach Bum Parade $100.00 Holidays, Festivals, and Events

  9. YMCA: 6 • Campground: 0 • Police Dept.: 1 • M.S.C.: 10 • Fire Dept.: 1 • Lifeguards: 2 • DPW: 5 • Facilities: 4, Parks: 1, & Restrooms: 4 • City Hall: 1, & Residents: 3 • TEMA: 0 • Water Dept.: 0 • Parking Services: 13 Total Work Orders & Requests for Work : 51

  10. Campground: 4 Parts: $126.59 • Police Dept.: 61 Parts: $3,677.60 • Fire Dept.: 4 Parts: $2,259.64 • TEMA: 0Parts: $0 • DPW: 69 Parts: $18,567.89 • Water Dept.: 8 Parts: $438.22 • Sewer Dept.: 6 Parts: $984.96 • Parking: 4 Parts: $439.58 • Ocean Rescue: 7 Parts: $280.00 • Beach Patrol: 17 Parts: $1,489.36 Total cost for parts: $28,263.84 Total Fleet Work Orders: 180

  11. Major Purchases • ADA Picnic Tables $15,358.26 • Street Resurface $116,064.00 • Resurface of Inlet Ave. Parking Lot $5,981.29 Total Purchases • 230 Purchase orders have been made this quarter, amounting to $230,210.29

  12. Garbage & Recycling DPW Yard – 381.68 Total Tonnage • Organic – 12 Hauls • Construction Debris/Solid Waste –195.87 Tons, 29 Hauls • Compactor – Solid Waste 45.04 Tons, 12 Hauls • Metal/Recycle – 26.91 Tons, 6 Haul South-end Business District Compactors – Total Tonnage • Atlantic Ave Recycling – 16 Tons • Lovell Ave – 104.86 Tons

  13. HAVE A GREAT DAY!

  14. Thank You For Watching The Department of Public Works Quarterly Report