1 / 23

Cost Estimates

Cost Estimates. Katherine Prewitt kprewitt@spp.org Director, Planning. RSC Motions (Oct 2010). 2. MOTION 1 : RSC recommends that SPP review what is the best manner to address significant cost increases and/or overruns of transmission projects that are regionally funded.

brett-rojas
Download Presentation

Cost Estimates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Estimates Katherine Prewitt kprewitt@spp.org Director, Planning

  2. RSC Motions (Oct 2010) 2 • MOTION 1: RSC recommends that SPP review what is the best manner to address significant cost increases and/or overruns of transmission projects that are regionally funded. • MOTION 2: RSC recommends that SPP review the Novation Process and report to the RSC by April 2011. • MOTION 3: RSC recommends that SPP consider establishing design and construction standards for transmission projects at 200 kV and above that are regionally funded. • MOTION 4: SPP evaluate how cost estimates are established for transmission projects before Cost Benefit Analysis are performed. • MOTION 5: CAWG to study various methods on how costs that exceed some standard can be addressed with different cost allocation mechanisms and recommend strategies to RSC.

  3. Cost Estimation Improvements • Standardized Cost Estimate Reporting Template (SCERT) • All cost estimates • Quarterly reporting • Conditional Notification to Construct (CNTC) • > $20 Million • > 100 kV • Establish Project Estimate baseline • CNTC Project Estimate (CPE) • NTC Project Estimate (NPE) 3

  4. Cost Estimation Improvements 4 • Project Cost Working Group • Deviates or is expected to deviate +/- 10% from established baseline cost • Report monthly • Deviates or is expected to deviate +/-20% from established baseline cost • Provide detailed cost variances via updated SCERT with explanations regarding the variances

  5. Project Cost Working Group (PCWG) 5 • Oversee a quarterly report • Study Estimate Design Guide (SEDG) • Review estimation variances • Regionally funded project >300 kV and >$20 million • Explanation for the cost estimate variances as well as • Reasons why the project should or should not move forward • Develop business practices

  6. Stages of Cost Estimation • Conceptual Estimate (Staff) • prepared by SPP from historical data • used for screening purposes only • Study Estimate (DTO) • submitted by DTO if project passes Conceptual screening and requires more refined estimate • NTC Project Estimate (NPE)/CNTC Project Estimate (CPE) (DTO) • submitted by DTO in response to CNTC/NTC issuance • established as baseline for project cost variance • Design/Construction Estimate (DTO) • submitted by DTO in quarterly tracking process for cost estimates as engineering and construction for project is underway/completed

  7. Cost Estimate Stage Definition

  8. Conditional Notification To Construct (CNTC) • Projects within the financial commitment window • Study Estimate > than $20 Million and > 100 kV • Additional time and cost recovery for DTO to refine estimate • SPP re-evaluates project if CNTC Project Estimate (CPE) outside accepted bandwidth • NTC issued • Cost variance is acceptable • BOD approves the refined cost analysis

  9. Conditional NTC (CNTC)Project Estimate Variance • CPE bandwidth exceeds Study Estimate bandwidth • Re-evaluate project • Make a recommendation to the BOD • Possible SPP staff recommendations: • Accept the cost variance and approve as is • Modify the project • Replace the project with new solution • Cancel the project 9

  10. $ 70 M $ 100 M $ 130 M - 30 % + 30 % CPE Evaluation Illustrations $105 Million Study Estimate: $100 Million $84 M $105 M $126 M CNTC Project Estimate: Action: SPP IssuesNTC to DTO If the +/-20% precision bandwidth of the project’s CPE is within the accepted range, an NTC will automatically be issued

  11. $ 70 M $ 100 M $ 130 M - 30 % + 30 % CPE Evaluation Illustrations $120 Million Study Estimate: $100 Million $96 M $120 M $144 M CNTC Project Estimate: Action: SPP Re-evaluation and BOD Review If the +/-20% precision bandwidth of the project’s CPE is outside the accepted range, SPP Staff will re-evaluate the project and submit updated analysis to BOD for review

  12. Study Estimate Design Guide 12

  13. Study Estimate Design Guide Study Estimate Design Guide (SEDG) Establish Study Estimate Design Guide to be used by the SPP’s Transmission Owners (TOs) in developing Study Estimates for SPP footprint projects rated at voltages at 100 kV and greater. These SEDGs are intended to ensure consistency in TO Study Estimates. 13

  14. Transmission Lines Minimum Conductor Sizing for normal ratings is specified, e.g., 1,200 Amps for 230 kV and 3,000 Amps for 345 kV Reconductoring should consider advanced conductors if possible Reactive Compensation costs should be included in project costs estimates 14

  15. Reactive Compensation

  16. Substations Substations should be designed with : Accommodations for future expansion Suggested bus configurations by voltage class and number of terminals Minimum terminal equipment ratings Minimum bus ratings 16

  17. Protection/Controls Protection and control designs should include: Redundancy PMUs or Intelligent Electronic Devices (EIDs) for 230 kV and above SCADA and RTUs 17

  18. SCERT Questions • Is there an instruction manual? • Should there be a confidentiality statement on the estimate or documents? • How should the forms be submitted? PDF or hard copy? • Do ROW/Land Rights cost need to be broken down in more detail than one-line?

  19. SCERT Questions • Will NTC be issued on a program or project basis? • Under Line Assumptions – Structure, are Tangents and Dead Ends the number of assumed structures and Underbuild? • For Station Assumptions – Breaker Scheme, are you looking for information on substation arrangement? • How should or who should questions be submitted?

  20. SCERT Question – Nominal vs Current $ • Costs should be in current dollars • Unless a project is considered ‘multi-year’ • 1st year cost should be in current dollars regardless of start date • Estimated as if they started today • All multi years projects calculated with escalation rate chosen by DTO

  21. SCERT Question – Nominal vs Current $ Example: Year 1: $100,000 Year 2: $200,000 Year 3: $100,000 Total $400,000 Using a escalation rate of 2%/yr Year 1: $100,000 = $100,000 Year 2: $200,000 @ 2% = $204,000 Year 3: $100,000 @ 2% = $104,040 Total: = $408,040

  22. SCERT Form • SPP provided • SPP Project Name • Project ID • Upgrade ID • RTO Determined Need Date • Estimate Request Date added (New) • DTO provided • Estimate Provider • Point of Contact

More Related