1 / 8

M1 Calculation Options CWG/MCWG ERCOT Public December 16, 2013

M1 Calculation Options CWG/MCWG ERCOT Public December 16, 2013. Mass Transition Timing. Given a system limitation of approximately 75,000 transactions/day, the timing of a Mass Transition will differ greatly depending on the Counter-Party.

bernardl
Download Presentation

M1 Calculation Options CWG/MCWG ERCOT Public December 16, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. M1 Calculation Options CWG/MCWG ERCOT Public December 16, 2013

  2. Mass Transition Timing Given a system limitation of approximately 75,000 transactions/day, the timing of a Mass Transition will differ greatly depending on the Counter-Party. 82% of Counter-Parties with ESIIDs can be transitioned in three days, but 78% of ESIIDs would require seven days or more. ERCOT Public

  3. M1 M1 covers additional actions besides Mass Transition. ERCOT Public

  4. Mass Transition Timing The total timing of a Mass Transition could range up to 41 days after the operating day assuming transitions take place on weekends and holidays. M1 Weighted average transition-only days Note: Assumes two-day cure period. ERCOT Public

  5. M1 Proposed Approach • Proposed approach: • Decompose M1 into two components: • M1a – Time period required to cover any termination event • M1b – Time period to cover mass transitions only • M1a applicable to all entities; M1b applicable only to Counter-Parties with Load • In M1b, adjust the mass transition days to reflect the decline in potential exposure during the transition period • Give credit against M1b to Counter-Parties meeting ERCOT Creditworthiness Standards

  6. M1 Proposed Approach • Calculation • Determine number of Counter-Party ESIIDs (n) • Determine estimated ESIID switch rate (assumed 75,000/day) (r) • Unscaled number of days = u = n/r (round up to whole days) • Weighted average transition number of days = s = 2+max(1, (u+1)/2) (round up to whole days) • If Counter-Party meets ERCOT Creditworthiness Standards, reduce s by a defined percentage p, (1-Discount Factor) * M1b Example:

  7. M1 Proposed Approach Under the proposed methodology, the M1 value for most ERCOT Counter-Parties would decrease.

  8. Questions ERCOT Public

More Related