1 / 5

Airport Improvement Program (AIP) Withholding Levels and Grant Amendments

Federal Aviation Administration. Airport Improvement Program (AIP) Withholding Levels and Grant Amendments. AirTAP Fall Forum - October 2006 Nancy M. Nistler. Grant Withholding Levels. I mplemented in July 2005 Encourages more timely project closeout reports

barbra
Download Presentation

Airport Improvement Program (AIP) Withholding Levels and Grant Amendments

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Federal Aviation Administration Airport Improvement Program (AIP) Withholding Levels and Grant Amendments AirTAP Fall Forum - October 2006 Nancy M. Nistler Update on

  2. Grant Withholding Levels • Implemented in July 2005 • Encourages more timely project closeout reports • When project closeout report is submitted & approved for payment, final grant funds can be released: • $10K – Projects less than $500K • $50K – Projects $500K or greater Update on

  3. Grant Amendments for Cost Overruns • Unforeseen Overruns • Limited to 15% of grant amount • FAA looks at: • Are costs AIP eligible and necessary to complete projects listed in grant description? • Is AIP funding available? • If funding is available….. • We issue a grant amendment • If funding is not available: • We add the grant to our amendment list Update on

  4. Other Grant Amendments • Planning Grants – Cannot be amended • Amendments to add a NEW work item – Very limited. Cannot add funding too. Grant must be amended before new work commences or the work already accomplished is not eligible. • Amendments for land at primary airports – up to 15% of grant amount • Amendments for land at non-primary airports – up to 15% of the grant amount or 25% of the increased land costs whichever is greater • For further information: FAA Order 5100.38C, The AIP Handbook, Page 14, pages 205 - 208 and Appendix 13 Update on