nTof Civil engineering Status -21 November 2013

nTof Civil engineering Status -21 November 2013. Contractor’s main works started on 13/05/2013: Done : Worksite installation Demolition of barrack 559 and deviation of the existing networks Earthworks Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery Piles

annora
Download Presentation

nTof Civil engineering Status -21 November 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. nTof Civil engineering Status -21 November 2013 • Contractor’s main works started on 13/05/2013: Done: • Worksite installation • Demolition of barrack 559 and deviation of the existing networks • Earthworks • Beam shaft and opening ɸ80 in the roof of the nTOFtechnical gallery • Piles • Concreting works • Finishing works : waterproofing, insulation and « chape » Ongoing: • Remaining finishing works and landscaping L.A.Lopez

  2. Somepictures of the worksfrom the last meeting: Concretingworks

  3. Finishingworks : waterproofing, insulation, chape

  4. Façades

  5. Nextsteps • Completion of finishingworks (doors, painting) → November – December 2013 • Landscaping → November – December 2013 • Handover to CERN expected on January 2014 (date to beconfirmed) L.A.Lopez