An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROJEKT: BIOENERGETSKI PARK Lokacija: Koprivničko – križevačka županija, Poslovna zona Koprivnički Ivanec, Republika Hrvatska Energy Environment Group, USA

  2. MAKROLOKACIJA – BIOENERGETSKI PARK • BIOENERGETSKI PARK • lociran u Poduzetničkoj zoni Kopr. Ivanca (205 ha) • Površina Bioenergetskog parka 21 ha • Broj zaposlenika cca. 200 ljudi • Iznos ukupne investicije cca. 220 mil. € POSLOVNA ZONA ‘’DANICA’’ - Podravka, Carlsberg Bioenergy park project - Energy Environment Group, USA

  3. Sam projekt sastoji se od nekoliko faza koje su povezane međuenergetskom zavisnošću s ciljem postizanja visokog stupnja iskorištenja cijelog bioenergetskog parka ( > 85%). Sva postrojenja nabrojana po fazama su u simbiotičkom odnosu - energetskom i/ili materijskom. Faze se dijele na: • 1. IZGRADNJA TERMOELEKTRANE NA DRVENU SJEČKU (TEKI) • 2. IZGRADNJA BIOREAKTORA ZA AGRARNU BIOMASU • 3. IZGRADNJA POSTROJENJA ZA UZGOJ ENERGETSKIH ALGI I PROIZVODNJU BIODIZELA • 4. IZGRADNJA SOLARNE ELEKTRANE Bioenergy park project - Energy Environment Group, USA e-two energy d.o.o.

  4. ARHITEKTONSKI KONCEPTUALNI PRIKAZ Bioplinsko postrojenje - površina = cca. 6 ha Staklenici za energetske nasade - površina cca. 1,5 ha Regionalni centar za Obnovljive izvore energije - površina cca. 1,5 ha Uzgajalište energetskih algi i postrojenje za proizvodnju biodizela - površina = cca. 4 ha Termoelektrana na drvenu sječku – TEKI - površina = 5,3 ha Solarna (PV) elektrana - površina = cca. 2 ha Bioenergy park project - Energy Environment Group, USA

  5. TERMOELEKTRANA NA DRVENU SJEČKU (TEKI) • DOBAVLJAČI • Hrvatske šume d.o.o. • Fizičke osobe • ZAPOSLENO OSOBLJE • 36 zaposlenika u samom postrojenju • Više od 200 ljudi na plantažama energetskih nasada 80.000 tona trupaca 80.000 tona sječke • PROIZVODI: • Električna energija = 20 MW • Toplinska energija = 30 MW + 5 MW • Tehnološka voda = 20 m3/d • Dimni plinovi (CO2 + H2O) = 100.000Nm3/h • REFERENTNO POSTROJENJE • Wittenberg i Bischofferode • (Njemačka) • Identična termoelektrana i tehnologija • KUPCI • El. energija  HEP • Toplina  vlastita potrošnja • Dimni plinovi  vlastita potrošnja • Procesna voda  vlastita potrošnja • CIJENA INVESTICIJE • cca. 87.000.000 € Bioenergy park project - Energy Environment Group, USA

  6. POSTROJENJE ZA PROIZVODNJU BIOPLINA • DOBAVLJAČI • Fizičke osobe (farme i poljoprivredni posjedi) • Podravka • Carlsberg • ZAPOSLENO OSOBLJE • 20 zaposlenika u samom postrojenju • Više od 100 ljudi u transportnoj logistici • PROIZVODI • Bioplin, Bioetanol • El. energija • Organsko gnojivo • POTENCIJALNI KUPCI • Bioplin  Belupo, Podravka, Carlsberg • Bioetanol, Biometanol Postrojenje za proizvodnju Biodizela, Industrija pića • Organsko gnojivo (cca. 100.000 t/g)  OPG – Obiteljska Poljoprivredna Gospodarstva • El. energija (cca. 20 MWe)  HEP • CIJENA INVESTICIJE • cca. 70.000.000 € Bioenergy park project - Energy Environment Group, USA

  7. UZGAJALIŠTE ENERGETSKIH ALGI I POSTROJENJE ZA PROIZVODNJU BIODIZELA • ZAPOSLENO OSOBLJE • 35 zaposlenika u samom postrojenju • DOBAVLJAČI • TEKI (toplina, CO2 i tehnološka voda) • Priroda (Sunčeva energija) • PROIZVODI • Biodizel • Glicerin • Alga biomasa • KUPCI / POTENCIJALNI KUPCI • Biodezel  Vlastita proizvodnja, Podravka, INA • Glicerin  Vlastita proizvodnja,Belupo • Alga biomasa (Visoko-proteinska sirovina) Podravka, Belupo • CIJENA INVESTICIJE • cca. 50.000.000 € Bioenergy park project - Energy Environment Group, USA

  8. SOLARNA (PV) ELEKTRANA • ZAPOSLENO OSOBLJE • 10 zaposlenika u samom postrojenju za održavanje sustava POVRŠINA KOJU ZAUZIMAJU SOLARNE ĆELIJE IMAT ĆE DVIJE FUNKCIJE: 1. Proizvodnja el. energije (1 MWe u električnu mrežu) 2. Natkrivat će vanjsko skladište trupacaštiteći tako trupce od vlage • CIJENA INVESTICIJE • cca. 6.000.000 € Bioenergy park project - Energy Environment Group, USA

  9. REGIONALNI CENTAR ZA OBNOVLJIVE IZVORE ENERGIJE • SVRHA: • Znanstveno - istraživački centar za primjenu OIE te edukacijska funkcija, znanstveni turizam. Bioenergy park project - Energy Environment Group, USA

  10. STANJE PROJEKTA • UČINJENO: • Idejna projektna dokumentacija za TEKI je izrađena (Austrian Energy & Environment, • Građevinski fakultet, Fakultet strojarstva i brodogradnje, Fakultet elektrotehnike i računarstva, • Brodarski institut, Nemeth projekt, Pȍyry, RBA Consulting) – utrošeno 3,5 mil. € vlastitih • sredstava. Vlasništvom e-two-energy–a na tim dokumentima, prenešena je tehnologija i • Know how u RH. • Dobivene sve suglasnosti za izdavanje Lokacijske dozvole • Aplicirano na natječaj Hrvatskih šuma za prodaju drvne biomase • Potpisan Memorandum of understanding sa EBRD-om, Deutsche Bank i klub hrvatskih • banaka poslao Term sheet Bioenergy park project - Energy Environment Group, USA

  11. HVALA NA PAŽNJI! Bioenergy park project - Energy Environment Group, USA