CO2 progress and issues on the control system. Lukasz Zwalinski – PH/DT 28.09.2009. Requirements for thermosiphon. Requirements for test stand : 30 Analog Input s 5 Analog Output s 6 Digital Input s 5 Digital Output s SCADA system with long term logging. 1.

abiola
Download Presentation

CO2 progress and issues on the control system

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CO2progress and issues on the control system Lukasz Zwalinski – PH/DT 28.09.2009

  2. Requirements for thermosiphon Requirements for test stand: • 30 Analog Inputs • 5 Analog Outputs • 6 Digital Inputs • 5 Digital Outputs • SCADA system with long term logging 1 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  3. Industrial Supervision Layer Operator Consoles Interface to operators (Monitoring & Command emission) SCADA Servers Real time DB & Archiving Industrial Control layer PLC Process Control Ethernet Network & TCPIP communication services Control Logic Actions PLC Process Control & Field interface Industrial Field layer Fieldbus Networks control system connection to the process directly or through field-buses UNICOS - UNified Industrial COntrol System • UNICOS environment supports all three control system layers: • supervision (SCADA: PVSS) • control (PLC: Siemens S7 and Schneider) • field layer • The package of programming tools includes: • baseline library (with modular PID algorithm) • code generator • skeleton templates and example of objects list • Object definitions provided by UNICOS are split into: • I/O Objects (Digital Input, Digital Output, Analog Input) • Field Objects (OnOff, Analog, Controller, etc.) • Process Control Objects (PCO). 2 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  4. UNICOS user interface 3 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  5. UNICOS – how does it work UNICOS project creation:1 – Exel specyfication preparation 2 – PLC hardware configuration3 – PLC & PVSS instance generation4 – Process logic programation5 – Code compilation 6 – Loadingto PLC7 – Commisionig & operation Specyfication SCADA server Instance Generator SIEMENS PLC Logic Generator All generated files will be kept in Subversion Version Control (SVN) service. 4 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  6. Selected equipement – SIEMENS Ethernet (TN) 5 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  7. Plant operation There will be ? option modes driven by allowance table System Stopped Warm Stop Stand By Cool down Run Cold Stop Option mode 1 Option mode 2 Option mode 3 Option mode 4 Option mode 5 6 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009

  8. Cost summary Siemens: (first estimation)cost estimated13.5k chf ~ 9k €- cost of electrical work is not included- PVSS data server in CCC not included (3267€)- racks and mechanics is not included (6000€)Sources:- prices from orders in TE/CRG/CE Section – Marco Pezzetti- http://ab-project-unicos.web.cern.ch/ab-project-unicos/- detail costing .xls is placed on project work space- Siemens online ordering system 7 L.Zwalinski – PH/DTCO2 test stand control system7.10.2009