An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gate Review Process presented at DODCAS 2009 DON Session CAPT Jim Baratta Deputy Director, NCCA

  2. Gate Review Process Overview • Purpose • improve governance and insight • ensure alignment between capability requirements and acquisition • improve senior leadership decision making • gain better understanding of RISKS and COSTS • Objectives • endorse or approve key JCIDS and acquisition documents • facilitate decisions regarding capabilities and material solutions • 2-Pass, 6-Gate Process • address Requirements and Acquisition governance respectively • EVERY GATE reviews program health – cost, risks, budget

  3. Gate Review BoardMembership • Principal (voting) members • CNO / CMC / VCNO / ACMC • ASN (RDA) / PDASN • ASN (FM&C) • OPNAV N8 / HQMC DC P&R and DC CD&I • Appropriate SYSCOM Commander • Advisory (non-voting) members • Resource Sponsor, CHSENG • N80, N81, N091, FMB • Cognizant DASN • DASN (C&E) • Attendance limited to Principal or Deputy (Flag/SES) plus one

  4. Pass 1 Gates • Gates 1, 2, and 3 “Requirements” Gates • Led by CNO or CMC • Starts prior to Material Development Decision, ends after Gate 3 • Leads to: • Approving the ICD • Approving AOA guidance • Selecting an AOA “optimal” alternative • Approving a CDD • Developing a CONOPS • Approving System Design Specification (SDS) Development Plan

  5. Pass 2 Gates • Gates 4, 5, and 6 “Acquisition” Gates • Led by ASN(RDA) • Starts after Gate 3, ends after Milestone B (initial EMD phase) • Leads to: • Approving the SDS • Approving release of the RFP • Assessing readiness for production • Assessing sufficiency of the EVMS PMB • Assessing the IBR • Follow-on Gate 6’s pre- and post-Milestone C and FRP DR • Serve as Configuration Steering Boards and review program health

  6. Pass 1 – Requirements Gates • Gate 1: Approval of the ICD • input: Service review of the ICD • brief: AoA assumptions, cost constraints and life-cycle considerations • outcome: Validates AoA guidance, authorizes to proceed to MSA phase • Gate 2: Approval of the preferred alternative • input: Approved ICD, AoA, “sufficiently mature” MS-A documentation • brief: AoA assumptions, analysis, findings, preliminary TRL assessment • brief: Projected life cycle costs for all AoA options • outcome: Approves development of CDD and CONOPS for alternative

  7. Pass 1 – Requirements Gates • Gate 3: Approval of the Service CDD and CONOPS • input: Approved AoA, SDS development plan • input: Service review of CDD/CONOPS, • supports LCCE(employment, sustainment, training, manning, etc) • brief: Initial independent cost estimate & schedule assessment • brief: Compare to PM estimates • outcome: Approves the CDD/CONOPS, SDS development plan • outcome: Approves program to MS-A (or with MS-B preparations)

  8. Pass 2 – Acquisition Gates • Gate 4: Approval of the SDS • may be combined with Gate 5 and MS-B for ACAT IC/IAC/II • input: Approved CDD, CONOPS, and review of SDS • input: Independent cost estimate, PM cost estimate, budget • brief: Capability, risk, independent/PM cost/schedule estimates • outcome: Authorizes program to proceed to Gate 5 (or Milestone B) • Gate 5: Approval of release of the RFP • may be before, concurrent with, or after MS-B • input: Approved SDS, key business elements in acquisition strategy • brief: Capability, risk, independent/PM cost and schedule estimates • outcome: RFP approval for release to industry

  9. Pass 2 – Acquisition Gates • Gate 6: Assesses readiness for production • occurs after contract award and IBR completion • input: Source Selection completed, contract awarded, IBR completed • brief: Capability, risk, independent/PM cost and schedule estimates • brief: Assesses IBR results, sufficiency of the SDS and EVMS PMB (EAC) • outcome: follow-on Gate 6 reviews prior to and post MS-C, FRP DR • Gate 6 follow-on: Pre-LRIP, Pre-FRP DR • “as needed” tailored approach • specific elements undefined in SECNAV 5000.2, same as Gate 6

  10. DON Requirements Acquisition Annual CSB # Gate Review PASS 1 PASS 2 OSD/JOINT LEVEL MS B** JROC MS A** JROC JROC CD NAVY/USMC LEVEL 1 2 3 5 4 6 SDD SSAC CDD and CONOPS Approval RFP Approval Contract Award ICD Approval Alternative Selection SDS Approval CBA Forum*: Lead Org: Chair: R3B OPNAV/HQMC CNO (N8)/DC, CD&I R3B OPNAV/HQMC CNO/CMC R3B ASN(RD&A) ASN(RD&A) R3B ASN(RD&A) ASN(RD&A) R3B ASN(RD&A) ASN(RD&A) R3B OPNAV/HQMC CNO/CMC PEO/SYSCOM/ OPNAV/HQMC LEVEL AOA CONOPS CDD InitiaI SDS RFP IBR Updated SDS Illustrated example for program initiation at Milestone A

  11. DON Requirements Acquisition Annual CSB # Gate Review PASS 1 PASS 2 OSD/JOINT LEVEL MS B** MS A** JROC JROC CD NAVY/USMC LEVEL 1 2 3 5 4 6 SDD SSAC CDD and CONOPS Approval RFP Approval Contract Award ICD Approval Alternative Selection SDS Approval CBA Forum*: Lead Org: Chair: R3B OPNAV/HQMC CNO (N8)/DC, CD&I R3B OPNAV/HQMC CNO/CMC R3B ASN(RD&A) ASN(RD&A) R3B ASN(RD&A) ASN(RD&A) R3B ASN(RD&A) ASN(RD&A) R3B OPNAV/HQMC CNO/CMC PEO/SYSCOM/ OPNAV/HQMC LEVEL AOA CONOPS CDD InitiaI SDS RFP IBR Updated SDS Illustrated example for program initiation at Milestone B

  12. Program Cost UncertaintyOver Time Pre Systems Acquisition Systems Acquisition Sustainment Pre Systems Acquisition vs. BUDGET? Material Solution Analysis Technology Development Engineering & Manufacturing Development Production & Deployment Operations & Support Cost, Technical, and Programmatic Uncertainty A B C IOC FOC Disposal Gate Reviews 1 2 3 4 5 6 6 fo 6 fo 6 fo ITR ASR SRR IBR PDR TRR OTRR PCR Technical Reviews Preferred System Concept System Specification/ CDD SFR Allocated Baseline CDR FRR SVR/PRR ECPR System Functional Baseline Product Baseline Product Baseline Parametric Analogy Parametric Analogy Engineering Build-Up Parametric Analogy Extrapolate Actuals Engineering Build-Up Parametric Extrapolation of Actuals Engineering Build-Up Estimating Techniques

  13. Gate Review ProcessPotential “Cost Community” disconnects? • How often are the program’s definition and bounds changing during the pre-MS-B timeframe? • What reliable data is available to estimate a program this early in its acquisition life cycle? • What documents are complete and approved leading up to each Gate? • To what extent are CAIV decisions still being made prior to RFP release? • Do “best practice” estimating methods allow significant cost estimate confidence at this point? • As the estimate progresses, in what “ballpark” should the estimate’s upper bound of range be expected to cover potential costs into MS-B? • How will the range and estimates be used to program a budget at this early phase in the program? • What value does an independent assessment add in the early “requirements” Gates?

  14. Questions? COST ANALYSIS Go Army!

  15. Cost Estimate Confidence thru Pre-MS-B Phase of Programs Mature? Stable? PROGRAMMATICBASELINE TECHBASELINE Defined? Steady? Analogy? Parametric? Program info? SCORE COSTDATA Methodology? Underlying data? ESTIMATECONFIDENCE Budget supportable? OVERRUNPOTENTIAL MOST CASES WILL BE RED OR YELLOW ESTIMATESTABILITY Small changes early in program life? Upper Bounds Stable? COSTRISK