An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Management SOS ch 6

  2. Risks • Bad things that might happen • two aspects • uncertainty - probability of happening • loss - cost if it happens

  3. Risk Exposure • Expected value of the risk event • Product of risk probability and cost

  4. 2 games – flip 2 coins • Game A: • 2 heads pays $10 • 1 head costs $2 • 0 heads costs $4 • Game B: • Pay $2 to play • 2 heads pay $10 • No other combination pays • Which is better?

  5. Example 6.3

  6. Risk Decision Tree • The top level branch splits on alternatives • Lower levels split on possible events

  7. TTYP1 • Assume that each additional review will cost an extra $6K but will cut in half the current probability of an error. • Assume that an error in the delivered product would cost Company XYZ $800K. • If the initial probability of an error is 5%, how many reviews should the company do? What if the initial probability of an error is 10% • Draw the risk decision tree and calculate the risk exposure for each choice

  8. TTYP2 – Deal/No Deal • If you are the contestant and you have two boxes left: $1,000,000 and $10,000, should you deal if the deal amount is $500,000?

  9. Risk Categories • Project risks • budget, schedule, personnel, requirements • Technical risks • design, implementation, interface, testing problems • Business risks • product viability

  10. Proactive • How do we mitigate those risks? • Planning which task to do first • Using quality assurance tasks • Monitoring progress • How does this relate to life-cycle model?