San Francisco-Oakland Bay Bridge East Span Seismic Safety Project Contractor Outreach August 13 and 14, 200

San Francisco-Oakland Bay Bridge East Span Seismic Safety Project Contractor Outreach August 13 and 14, 2002 SFOBB New East Span August 13 and 14, 2002 Outreach event Welcome - my name is Sarah Picker Purpose Agenda Networking What can we accomplish?

Ava
Download Presentation

San Francisco-Oakland Bay Bridge East Span Seismic Safety Project Contractor Outreach August 13 and 14, 200

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. San Francisco-Oakland Bay Bridge East Span Seismic Safety Project Contractor Outreach August 13 and 14, 2002

  2. SFOBB New East Span August 13 and 14, 2002 Outreach event • Welcome - my name is Sarah Picker • Purpose • Agenda • Networking • What can we accomplish? • Sign-In Please • Survey - day or night meetings

  3. Agenda Aug 13 and 14, 2002

  4. Purpose - Aug 13, 14 • Present information on project • SFOBB New East Span • encourage participation, primes meeting potential sub-contractors and suppliers

  5. Welcome • Paul Hensley Caltrans Chief Deputy District Director

  6. Project Limits San Francisco Oakland Project Limits

  7. T1/E2 foundations (04-0120E1) Transition structure (04-0120H1) E2 Retrofit/Substation (04-0120G1) T1 SAS superstructure (04-0120F1) W2 foundation (04-0120C1) Building demolition Yerba Buena Island YBI/SAS Contracts

  8. Welcome • James Fields City and County of San Francisco Human Rights Commission

  9. Welcome • Deborah Barnes City of Oakland

  10. The project team proposes the following contracts: • YBI Building Demolition(R/W) • a contract to remove three USCG buildings and one state building executed as a right-of-way service contract

  11. The project team proposes the following contracts: • SAS W2 Structures • a contract to construct the Self-Anchored Suspension bridge land-based foundation, pier W2

  12. The project team proposes the following contracts: • YBI Substation & Viaduct Retrofit • a contract to construct a replacement electrical substation on YBI near the westbound on-ramp and complete relatively simple bridge retrofit work near the YBI tunnel (this work is combined due to the close proximity of the work)

  13. The project team proposes the following contracts: • SAS E2/T1 Structures • a contract to construct the Self-Anchored Suspension bridge in-bay foundations, the main tower (T1) and pier E2 just to the east of YBI

  14. The project team proposes the following contracts: • SAS Superstructures • a contract to construct the tower and superstructure of the Self-Anchored Suspension bridge

  15. The project team proposes the following contracts: • YBI Structures • a contract to construct the temporary detour and permanent bridges on YBI

  16. SAS/YBI Discretization • What in the heck does that mean? • Did you go to the March 12 Contractor Outreach? • At that time, we exhibited information related to a certain project code 04-012064 SAS/YBI

  17. SAS/YBI Discretization • June 11, 2002 letter from Brian Maroney, Project Manager, announced that we were breaking up the project • smaller contracts that focus specific types of construction work create more opportunities for DBE and small business participation

  18. Recap of SFOBB East Span Seismic Safety Project • already awarded • PIDP 04-012084 • Skyway 04-012024 • Geofill 04-012054 • Archeological Excavation and Midden Site 04-012074

  19. Recap of SFOBB East Span Seismic Safety Project • YBI Building Demolition(R/W) • SAS W2 Structures 04-0120C1 • YBI Substation & Viaduct Retrofit • SAS E2/T1 Structures • SAS Superstructures • YBI Structures

  20. Recap of SFOBB East Span Seismic Safety Project • Oakland Touchdown • Existing bridge demolition

  21. SFOBB East Span • Tonight’s discussions relate to the W2 construction contracts we are planning to advertise for bid this fall and the Division of Right of Way’s service contract

  22. That would be the following: • SAS W2 Structures • YBI building demolition (R/W)

  23. What is the schedule? • We plan to advertise the W2 contract 04-0120C4 in September 2002 • Why do I keep repeating the contract number? • The R/W contract may hit the streets in late August/early September

  24. Other Introductions • Will the Potential Prime Contractors in the room volunteer to raise their hands? • Would the DBE certified businesses raise their hands? • Would the potential DBE or small businesses raise their hands?

  25. Suggest a resource • How Caltrans Builds Projects • www.dot.ca.gov/hq/oppd/Proj_book/overview.pdf

  26. Roadway Items Steven Hulsebus Office Chief, Toll Bridge Program

  27. Project Limits San Francisco Oakland Project Limits

  28. T1/E2 foundations (04-0120E1) Transition structure (04-0120H1) E2 Retrofit/Substation (04-0120G1) T1 SAS superstructure (04-0120F1) W2 foundation (04-0120C1) Building demolition Yerba Buena Island YBI/SAS Contracts

  29. YBI Transition Structure W2 foundation contract

  30. YBI Eastbound On-Ramp W2 foundation contract

  31. Self-Anchored Suspension Span (SAS) W2 foundation contract

  32. Yerba Buena Island • Varied topography -- 60 meter elevation change • Steep slopes • Narrow winding roads • USCG base for 24 hour Search and Rescue unit • Lots of underground utilities

  33. Environmental Constraints at YBI Historic Structures W2 foundation contract W2 foundation contract USCG Facilities

  34. Special Aquatic Site - Yerba Buena Island Yerba Buena Island

  35. San Francisco-Oakland Bay BridgeEast Span Seismic Safety Project DBE/SBE/DVBE Outreach Program Fall 2002

  36. YBI Structures • YBI Transition Structure • EB On-Ramp • Viaduct Modifications (Initial) • Viaduct Modifications (Final) • Temporary Detour Structures

  37. Contract Limits OAKLAND APPROACH YBI TRANSITION SUSPENSION SKYWAY OAKLAND GEOFILL SKYWAY SUSPENSION OAKLAND APPROACH YBI TRANSITION Existing Bridge

  38. YBI Structures: Quantities • Temp Detour Structure: • Towers and Floor Beams = 5,700,000 kg • HP360 Piles = 6,200 meters • Permanent Structure: • HP Piles = 14,500 meters • W Piles = 10,000 meters • Total Concrete • Concrete: 55,000 m3 • Bar Reinforcing Steel: 10,000,000 kg

  39. Construct W2 Foundation and Column 657 m 385 m 80 m 180 m 12 m Elev. +160m Pier W2 Aprox. OG along PG Line Pier 1 Tower Pier E2

  40. Earthwork & Piling at W2 • Structure Excavation (W2) 15,600 m3 • Structure Backfill (Bridge) 3,640 m3

  41. Geologic Cross-Section

  42. Excavation & Backfill at W2

  43. Structural Concrete at W2 • Structural Concrete, Bridge Footing (SAS) 7,220 m3 • Structural Concrete, Bridge (SAS) 400 m3 • Structural Concrete, Retaining Wall 770 m3

  44. Pier W2 Elevation