National grid local system plan
Download
1 / 21

National Grid Local System Plan - PowerPoint PPT Presentation


  • 134 Views
  • Updated On :

National Grid Local System Plan. Needs Assessment/Potential Solutions PAC Meeting September 21, 2010. Purpose of Local System Plan. Per Attachment K – Local, the LSP is a report that: Describes projected improvements to non-PTF that are needed to maintain system reliability Reflects:

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'National Grid Local System Plan' - zelig


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
National grid local system plan l.jpg

National GridLocal System Plan

Needs Assessment/Potential Solutions

PAC Meeting

September 21, 2010


Purpose of local system plan l.jpg
Purpose of Local System Plan

Per Attachment K – Local, the LSP is a report that:

  • Describes projected improvements to non-PTF that are needed to maintain system reliability

  • Reflects:

    • LSP Needs Assessments

    • Corresponding transmission system planning and expansion studies

  • Identifies:

    • Local Planning Process

    • Criteria, Data, and Assumptions


Lsp communication l.jpg
LSP Communication

  • PAC, Transmission Customers, and other Stakeholders have 30 days to provide any written comments for consideration by National Grid.

    • National Grid’s contact:

      Gabriel Gabremicael

      Mgr Transmission Planning, New England

      National Grid

      40 Sylvan Road

      Waltham, MA 02451-1120

  • The ISO-NE RSP project list links to each individual TO’s LSP project list.

  • National Grid’s project list is located at:

    • http://www.nationalgridus.com/oasis/filings_studies.asp

      • "LSP - LTP Transmission Projects - August 2010


Lsp project list l.jpg
LSP Project List

  • The LSP Project List is a cumulative listing of proposed regulated transmission solutions that may meet LSP needs.

  • Lower voltage facilities contained in the LSP Project List pertain to facilities supplying our wholesale municipal customers.

  • The LSP Project List contains the status of each project:

    • Concept

    • Proposed

    • Planned

    • Under Construction

    • In Service



Local system planning process l.jpg
Local System Planning Process

  • Local studies can result from:

    • Load Growth

    • Area Reliability Assessments

    • Point of Delivery Request from Customer

    • Generation Interconnection Request

    • Asset Replacements (included in list as a new addition)

  • A Planner –

    • summarizes the results from the needs assessment and provides: criteria, data and assumptions used in study

    • builds study cases with proposed alternatives

    • determines the most effective solution

    • summarizes the results of the solutions study


Criteria l.jpg
Criteria

  • All National Grid facilities that are part of the interconnected National Grid system shall be designed in accordance with the National Grid Transmission Planning Guide.

  • The National Grid Transmission Planning Guide is posted on our website under:

    http://www.nationalgridus.com/transmission/c3-8_standocs.asp as:

    • Transmission Planning Guide


Data and assumptions l.jpg
Data and Assumptions

Resources for studies:

  • NEPOOL Library cases for load flow and ASPEN short circuit studies

  • CELT Report Load forecasts for NE wide loads

  • Customer provided forecasted loads for local areas



Addressing 2009 lsp comments l.jpg
Addressing 2009 LSP Comments

At the request of the Massachusetts Attorney General, National Grid added the following data categories to our LSP:

  • Dollar amounts for projects

  • Company Asset Owner



Lsp massachusetts fonts in red are new or updates l.jpg
LSP – Massachusetts(Fonts in Red are new or updates)


Lsp massachusetts continued l.jpg
LSP – Massachusetts Continued


Lsp massachusetts continued14 l.jpg
LSP – Massachusetts Continued


Lsp massachusetts continued15 l.jpg
LSP – Massachusetts Continued


Lsp massachusetts continued16 l.jpg
LSP – Massachusetts continued


Lsp massachusetts continued17 l.jpg
LSP – Massachusetts continued


Lsp massachusetts continued18 l.jpg
LSP – Massachusetts continued


Lsp rhode island l.jpg
LSP – Rhode Island


Lsp removed from list l.jpg
LSP – Removed From List