DECATUR PUBLIC SCHOOLS. High School Task Force. 02/03/2009. The Need. Physical Needs Summary Many building systems are at the end of their useful lives (piping, windows, doors, heating/cooling equipment).

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'DECATUR PUBLIC SCHOOLS' - zarek


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
decatur public schools
DECATUR PUBLIC SCHOOLS

High School Task Force

02/03/2009

the need
The Need

Physical Needs Summary

  • Many building systems are at the end of their useful lives (piping, windows, doors, heating/cooling equipment).
  • Many components of the building envelope are beyond their useful life, particularly at EHS.
  • Many interior finishes are worn and should be replaced (there are some hazardous materials consequences).
  • There are opportunities for increased energy savings.
  • Most spaces lack air conditioning.
  • In addition to addressing these physical needs is the need to alter spaces to accommodate changing educational programs.

DPS #61 High School Task Force

the need1
The Need

Possible Enhanced Programming

  • AP Classes
  • Gifted Program
  • Night School
  • Community Partnerships
  • Decatur Technical Academy and DPS61
  • Foreign Language
  • Colleges in our Building

DPS #61 High School Task Force

the need2
The Need

Possible Enhanced Programming (cont.)

  • Small Learning Communities
  • Local Business
  • Student Mentors
  • State of the Art Science Labs
  • Clubs and Intramurals
  • Extra Curricular Activities

DPS #61 High School Task Force

high school entrances
High School Entrances

DPS #61 High School Task Force

decatur area technical academy
Decatur Area Technical Academy

TECH ACADEMY ENROLLMENT HISTORY

YearTotalYearTotal

1999-2000 393 2004-2005 478

2000-2001 449 2005-2006 519

2001-2002 394 2006-2007 579

2002-2003 414 2007-2008 639

2003-2004 409 2008-2009 645

DPS #61 High School Task Force

decatur area technical academy1
Decatur Area Technical Academy

TECH ACADEMY PROJECTED ENROLLMENT

(based upon 4% growth)

Year Total

2009-2010 670

2010-2011 697

2011-2012 725

2012-2013 755

2013-2014 784

2018-2019 950

DPS #61 High School Task Force

decatur area technical academy3
Decatur Area Technical Academy

Automotive Annex Entrance

decatur area technical academy4
Decatur Area Technical Academy

Inside Main Entrance

21st Century Entrance

decatur area technical academy5
Decatur Area Technical Academy

21st Century Entrance

DPS #61 High School Task Force

decatur area technical academy6
Decatur Area Technical Academy

Typical Classroom

21st Century Classroom

decatur area technical academy7
Decatur Area Technical Academy

Health Occupation Classroom

decatur area technical academy8
Decatur Area Technical Academy

Computer Repair Laboratory

planning process
Planning Process
  • Discovery
  • Visioning
  • Build Solutions
  • Selecting

DPS #61 High School Task Force

process timeline
Process Timeline

Discovery

  • February 25 EHS Walk-Through
  • March 16 MHS Walk-Through
  • April 7 Tech Academy Walk- Through
  • April 29 Review Existing Building Conditions/ Educational Programs

DPS #61 High School Task Force

process timeline1
Process Timeline

Visioning

  • May 18 Visioning Workshop

DPS #61 High School Task Force

process timeline2
Process Timeline

Build Solutions

  • June 11 Develop Alternatives Renovate Existing Buildings

DPS #61 High School Task Force

process timeline3
Process Timeline

Selecting

  • June 29 Select Best Option Renovate Existing Buildings

DPS #61 High School Task Force

process timeline4
Process Timeline

Build Solutions

  • July 20 Develop Alternatives Consolidated High School/ Tech Academy

DPS #61 High School Task Force

process timeline5
Process Timeline

Selecting

  • August 10 or 12 Select Best Option Consolidated High School/ Tech Academy

DPS #61 High School Task Force

process timeline6
Process Timeline

Selecting

  • August 31 Options Forum Renovate or Build New

DPS #61 High School Task Force

process timeline7
Process Timeline
  • September 1 or 2 Presentation Preparation

DPS #61 High School Task Force

process timeline8
Process Timeline
  • October 13 Decatur Public School District #61 Board Meeting

DPS #61 High School Task Force

recap of purpose
Recap of Purpose

DPS PK-12 ENROLLMENT HISTORY

20012002200320042005200620072008

PK 292 384 398 437 460 461 500 585

K-6 5950 5577 5395 5140 5051 4927 4930 4837

7-8 1776 1703 1665 1559 1531 1392 1368 1286

9-12 2546 2546 2491 2548 2572 2452 2392 2428

Total 10564 10210 9949 9684 9614 9232 9190 9136

Annual

Change N/A -354 -261 -265 -70 -382 -42 -54

Annual %

Change N/A -3% -3% -3% -1% -4% 0% -1%

*Green indicates an increase

*Red indicates a decrease

slide95

DPS History and Averages

YearReg EdSpedTotalAnnual Change

2001 2145 385 2530 -94

2002 2247 273 2520 -10

2003 2240 251 2491 -29

2004 2292 256 2548 57

2005 2411 70 2481 -67

2006 2241 211 2452 -28

2007 2200 192 2392 -60

2008 2228 200 2428 36

*Green indicates an increase

*Red indicates a decrease

3 Year Average Enrollment 2424

3 Year Average Change -18

5 Year Average Enrollment 2460

5 Year Average Change -13

8 Year Average Enrollment 2480

8 Year Average Change -25

recap of purpose1
Recap of Purpose

DPS High School Summary

New Students 2007-2009

Coming From:2006-20072007-20082008-2009 Average

Returning Students 39 28 28 32

Macon County 105 104 61 90

Outside Macon Co. 61 58 61 60

Outside Illinois 54 47 40 47

Other 19 19 15 18

Total:2241 256 205 246

High school enrollment has stabilized recently due to gaining an average of 246 students per year from outside districts.

next meeting
Next Meeting
  • February 25, 2009 at 6:30 p.m.
  • EHS Walk-through and Meeting