1 / 14

SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS

SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS. Relationship between Seveso II transposition and implementation. Interdependent Processes Part of the overall Regulatory cycle. Relationship between Seveso II transposition and implementation.

Download Presentation

SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SEVESO II transposition and implementation – possible approaches and lessons learned from MS/NMS

  2. Relationship between Seveso II transposition and implementation • Interdependent Processes • Part of the overall Regulatory cycle

  3. Relationship between Seveso II transposition and implementation • In order to transpose adequately the requirements you need to know: • The technical scope of the legislation • The target groups • The capacity of both CA and operators • The current status • The expected impact of the legislation • The public expectations • In order to implement the transposed legislation you need to know: • The requirements of the legislation • The competencies and the capacity of the CA • The duties of the operators • The attitude of the public

  4. Seveso II transposition • The transposition process should be: • Consistent • Systematic • Transparent • Based on the public expectations • Adequate to the overall HSE policy • It also should take into account • The political and administrative system • The safety and administrative culture of the operators • The available resources • The existing legal requirements • The feedback form the inspection authorities • The capacity of the CA

  5. Seveso II transposition • The transposition process should involve all relevant stakeholders: • National authorities • Regional and local authorities • The general public (especially living around Seveso sites) • Industry • NGOs • Scientific Institutions Everyone can contribute to the proper transposition!

  6. Possible steps towards the Seveso II transposition • Development of a National policy for Major accident safety/prevention • Development of an Action plan for achieving the goals of the policy, incl. transposition with deadlines, targets and clearly delegated responsibilities • Assessment of the existing legal requirements • Drafting of the new legislation • Assessment of the Compliance with the EU requirements • Impact assessment of the proposed legislation • If possible, pilot projects on the implementation of the legislation • If necessary, negotiation of transitional periods • Final endorsement of the legislation All relevant stakeholders should be encouraged to discuss the proposed measures at all stages of the process!

  7. Seveso II transposition – Bulgarian experience • Late 90’s – public pressure for safer environment and better quality of life – State policy in the area of major accident prevention established • Start 2000 - PHARE Project (start of the transposition process with the help of EU experts) • 2001 – Public discussion on the proposed legislation • 2002 – Environmental Protection Act • 2003 – Seveso Regulation • 2005 – Amendment to EPA – Directive 2003/105/EC • 2006 – New Seveso Regulation

  8. Seveso II Implementation • The implementation process should be: • Consistent • Systematic • Transparent • Establishing level playing field • Flexible • Able to give feedback when inadequacies are found • Adequate to the political and administrative system • Feasible within the available resources • Based on the administrative capacity of the CA

  9. Seveso II Implementation • The implementation process could be facilitated by: • Guidance notes on different technical aspects of the legislation • Guidance notes on assessment of the documentation, submitted by the operator • Guidance notes on the coordination of and the cooperation between the CA • Unified risk assessment methodologies • Training of the CA and the Industry • Active involvement of the NGOs and the general public • Establishment of feedback channels from the inspecting authorities • Establishment of appropriate registers and databases

  10. Possible steps towards the implementation of Seveso II • Preparatory Phase • Number of the sites • Procedures for notification • Coordination and cooperation between CA • Training of CA and operators • Implementation Phase • Procedures for assessment of the documentation • Procedures for inspections • Procedures for Feedback • Review and Follow-up Phase • Procedures for evaluation • Procedures for review and follow-up

  11. Seveso II - Involvement of the relevant stakeholders • Preparatory Phase • Training of operators • Public awareness campaign • Consultations on the proposed legislation • Implementation Phase • Public information • Public participation • Feedback from operators • Scientific Progress • Review and Follow-up Phase • Evaluation of the overall acceptance of the legislation – operators, public • Consultations during the review and follow-up of the legislation

  12. The implementation of Seveso II – Bulgarian experience Preparatory Phase • Pilot permits • Chemical Industry • Petroleum Products Storage Facility • Metallurgy • LPG Storage and Distribution Site • Set of Guidance Notes • Classification • MAPP and SMS • Safety Report • Risk Analysis

  13. The implementation of Seveso II – Bulgarian experience Implementation Schedule • 2004 – New Enterprises • No Transitional Period • 2006 – Existing Enterprises • No Transitional Periods • Accent on Safety Management • Investment Requirements – in IPPC for the majority of the big industrial sites

  14. Implementing Seveso in Bulgaria Implementation Progress • By 2008 – 101 Enterprises • About 10 Enterprises in the Pipe • App. 99 % of the Sites within the Scope of the Directive • Dynamic Process – Influx of new Sites • Significant problems with SMEs • Problems with sites with no experience