Projects under Operational programme “Transport and transport infrastructure” 2014-2020

Projects under Operational programme “Transport and transport infrastructure” 2014-2020 Eng. Lazar Lazarov Chairman of Road Infrastructure Agency Management board 28 - 29 November 201 6 Sofia. “Kalotina – Sofia” MW Lot 1 Western Arc of Sofia Ring Road, Phase 2. OVERPASS

yvonnev
Download Presentation

Projects under Operational programme “Transport and transport infrastructure” 2014-2020

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Projects under Operational programme “Transport and transport infrastructure” 2014-2020 Eng. Lazar Lazarov Chairman of Road Infrastructure Agency Management board 28 - 29November 2016 Sofia

  2. “Kalotina – Sofia” MW Lot 1 Western Arc of Sofia Ring Road, Phase 2 OVERPASS BLVD. “LOMSKO SHOSE"

  3. Motorway “Struma” Lot 3.1 from Blagoevgrad to Krupnik fromkm 359+000 tokm 366+000 and fromkm 370+460 tokm 376+000

  4. Motorway “Struma” Lot 3.1 - “Jeleznitsa” tunnel Procedures are carried out under the PPA with the subject: - Design and construction of the motorway "Struma“ Lot 3.1 Jeleznitsa tunnel - Supervision of the design and construction of the motorway "Struma" Lot 3.1 Jeleznitsa tunnel

  5. Motorway “Struma” Lot 3.3 fromKresna to Sandanski from km 397 +000 to km 420 + 624 = 420 + 628 478 km Overall length: 23.6 km

  6. Motorway “Struma” Lot 3.3

  7. An archaeological site 16 km 419 + 670 to km 420 + 384 village Damyanitsa, municipality of Sandanski, Blagoevgrad

  8. Finds of the preliminary exploring archaeological site 16 km 419 + 670 to km 420 + 384 VI – V century BC III-IVcentury

  9. Application Formfor Struma Motorway Project – Lot 3.1, Lot 3.3 and Zheleznitsa Tunnel • Received comments and remarks from Jaspers - May 2016 • Agreed with Jaspers updated traffic model and CBA • Submission for Jaspers’ review of the updated Application form and supporting documents – 19 December 2016

  10. Struma Motorway Lot 3.2 from Krupnik to Kresna • Lot 3.2 falls in the environmentally sensitive and technically difficult construction area • The intensive traffic on the road through the Kresna Gorge increases the risk of traffic accidentsinvolving casualties. For Struma Motorway Lot 3.2 passage through the Kresna Gorge various technical alternatives were developed. Four alternatives (objects of the new EIA) had been currently prepared: • 15.4 km long tunnel (2008-2014) • Dual Carriageway (2014) • Dual Carriageway (2015) • Eastern Bypass (2016)

  11. Long Tunnel Alternative (2008-2014)

  12. Dual Carriageway Alternatives (2014-2015)

  13. Eastern Bypass Alternative (2016) • 2 lanes and with a total width of 10.5 m • The new carriageway bypasses theKresna Gorge from the east and the other carriageway uses the existing road E-79 (I-1). The existing road will be rehabilitate and mitigating measures to limit the risk of mortality of wild animals and fragmentation of their habitats will be implement

  14. EIA Procedure • Developed updated Terms of Reference for the scope and content of the environmental impact assessment (EIA) of the investment proposal - "Improved layout of Lot 3.2 of Struma Motorway“ will be issued. Consultations with the specialized administrations, stakeholders and public were performed • The statements had been received and processed. The reference for consultations is under preparation as the ToR for EIA have been precised and supplemented • The submission of the ToR for the EIA for consultation with the competent authorities (MoEW and Ministry of Health) will occur in December 2016 • Expected preparation of the first draft of the EIA /AA Report - March 2017 • Submission of the EIA/AA Report in the MoEW for assessment of their quality • Public consultation on the EIA/AA Report after positive assessment of their quality by the MoEW.

  15. Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa, approximate length: 126 km

  16. Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa, approximate length: 126 km • Start of design activity – July 2013 • Deadline for preparation of technical projects – July 2018

  17. THANK YOU FOR YOUR ATTENTION!