E N D
1. 1 Frequency ProjectBMW Georgia Tech April 13th 2006
2. 2 Outline Project background
Problem description and objective
Approach
Results
Recommendation for BMW
Future work
3. 3 European Parts Supplies 40% of parts needed by (Plant 10) Spartanburg are sourced in Europe and shipped across the Atlantic via:
regular ocean shipments
Airfreight expediting in case of stock-out at Spartanburg plant
4. 4
5. 5 Current Case Frequency:
Three times per week
Arrival Days:
Thursday
Friday
Saturday
6. 6 Project description
7. 7 Major variable elements
Changing the European (American) ports affects land lead times
Frequency of shipments affects needs for inventory at plant
Parts proportions (Split) to be shipped in each scheduled shipment may reduce stock-out?
Shipping lines have different rates per container, shipping lead times and reliability
8. 8 Approach used Collection of sailings data
Creation of a tool to search among the large number of Sailings
Selection of multiple optimal ports and lines combination for various frequencies (based on ocean and land lead time)
Simulation to find costs incurred with the different scenarios
Processing Simulation Outputs in Excel
9. 9 Collection of Sailings Ports were selected based on:
Ranking in terms of TEU of European ports
Ports preferred by BMW
Duration of Sailings offered
Geography
Data obtained from www.joc.com1 (current Tender) and material Trans Atlantic Workshop provided by BMW (new Tender)
1sometimes data not accurate
10. 10 Constraints on Sailings Cutoff for sailing time: 18 days
Entry Ports considered :
Savannah, Norfolk, Charleston, New York, Montreal, Newark, Baltimore, Philadelphia, Miami, Houston, Halifax
European Ports considered:
Hamburg, Antwerp, Bremenhaven, Le Havre, Rotterdam, Copenhagen, Fos, Genao, Gioia Tauro, La Spezia, Le Verdon, Livorno, Montoir, Valencia, Algeciras, Barcelona
11. 11 General Assumptions If it arrives in port on Saturday or Sunday it cannot be shipped until Monday
(high extra charge if pulling out of port on weekends)
We are not considering multiple arrivals at Spartanburg on the same day
High and Low runners can not be mixed on a container
Capital Charge: 12 %
Non-Capital Holding Charge applied in Spartanburg:
5% (High Runners)
10% (Low Runners)
12. 12 Port Selection Tool (Excel Model) Assignment Model to minimize lead times under each scenario. Each scenario is a combination of:
Various ports in Europe
Various ports in the US
Various shipping lines used
Different weekdays of arrival
13. 13 Port Selection Tool(Assignment Model in Excel)
14. 14 Simulation Input Parameters used
Holding/carrying cost:
Values of Engines
Detailed Expediting costs
Major points included in the simulation
Demand uncertainty (difference between forecast and actual usage)
Ocean lead time variability
Lead time variability between US-port and Spartanburg
15. 15 Simulation in Arena (1)
16. 16 Simulation in Arena (2)
17. 17 Simulation in Arena (3)
18. 18 A Simulation with 500 runs 1000 days each was performed for each engine for each scenario
The average values for key variables were obtained by aggregating data in Excel
Transportation costs were calculated in Excel using the simulation output
Costs were summed to total figure
19. 19
20. 20 Split Split policies were simulated for:
One high and one low runner engine
For a frequency of three
21. 21
22. 22
23. 23
24. 24 Recommendations
25. 25 Total Cost incl. Transportation
26. 26 Future Work Improve model to consider only integer number of container loads
Come up with a policy concerning mix of parts on a container
Simulate other plant 10 parts
Improve modeling of safety stock
More sensitivity analysis
Risk reduction by having multiple arrivals on one day