Prepare Strategic Business Cases for NDA. Consolidate nuclear materials at Sellafield Work underway with Sellafield Ltd. Developing final business case Assessing facility impacts Developing transportation logistics Work with Sellafield Deliver business case for NDA decision

yitta
Download Presentation

Prepare Strategic Business Cases for NDA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Prepare Strategic Business Cases for NDA • Consolidate nuclear materials at Sellafield • Work underway with Sellafield Ltd. • Developing final business case • Assessing facility impacts • Developing transportation logistics Work with Sellafield • Deliver business case for NDA decision • Deliver early closure of Winfrith site • preparing business case for NDA consideration • Perform alongside Harwell programme • Considering ILW transfer to Harwell

  2. RSRL Waste & Nuclear Material Transfers Key Objective To gain security benefits by transferring Waste and Nuclear Material from Harwell, making use of facilities across the NDA estate in line with ‘Strategy 2’. Scope The permanent removal of all identified material (Dragon, LEU, CHILW &CLDs). 2

  3. RSRL Waste and Nuclear Material Dragon fuel in 40-litre containers Low Enriched Uranium in 200-litre drums Contact Handled ILW Drums in 200-litre drums Concrete Lined Drums (200, 450 & 670-litre) 3

  4. Summary of Transport Movements 4

  5. Rail method of operation • Multi modal-currently used for both nuclear and non nuclear • Road transfer from Harwell to railhead • Rail transfer from railhead to Sellafield • Up to 4 packages per movement ~300 rail moves

  6. Programme • Business case submitted Sept 11 • Enabling works through to 2013 • Transfer operations 2013 to 2017

  7. Closure of RSRL Winfrith • Decommissioning of all RSRL facilities • Hand back to NDA • Consideration of transfer of waste to other sites • Impact to existing tenants • Delivery of the programme

  8. Harwell Oxford Campus • Science, innovation, and business campus • Owned and managed by joint venture: UK Atomic Energy Authority, Science and Technology Facilities Council, Goodman

  9. Near term focus: Legacy waste processing Groundwater clean-up Campus development facilitation Harwell Lifetime Plan Long term focus Complete decommissioning Store ILW until national facility ready

  10. RSRL Considering ILW Storage Options • Interim storage of ILW needed until geological disposal facility available • Geological disposal not available until after 2040 • Maximises release of Harwell site to campus development • RSRL considering options for Harwell, Winfrith and Culham ILW to achieve benefits including... • Release of land for new uses • Avoid unnecessary construction • Redirect construction and operations costs to decommissioning activities • Proposals will be based on Best Available Techniques assessments

  11. Potential Storage Facility Sizes

  12. B C A Potential Locations for ILW Storage Facility