1 / 17

Designing Bank Operations to Support Program-Based and Sectorwide Approaches

Designing Bank Operations to Support Program-Based and Sectorwide Approaches. POLAND Road Maintenance & Rehabilitation I & II “ Program-based ” approach projects. Poland at a glance…. Population: 39 million inhabitants GNP/Capita US4,570 Upper Middle Income Countries: US$5,040

yehuda
Download Presentation

Designing Bank Operations to Support Program-Based and Sectorwide Approaches

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Designing Bank Operations to Support Program-Based and Sectorwide Approaches

  2. POLAND Road Maintenance & Rehabilitation I & II “Program-based” approach projects

  3. Poland at a glance… • Population: 39 million inhabitants • GNP/Capita US4,570 • Upper Middle Income Countries: US$5,040 • Motorization rate is increasing fast: • 9 million cars in 1990 • 14 million today • Poland compares poorly with EU neighboring countries both in terms of condition of the road network and safety • Road improvement: a CAS high priority

  4. National road network: 18,000 km. – Maintenance backlog estimated to US$1 billion…

  5. Brief Historical reminder… • In late 2003, Government (MoF) clearly preferred to use “Adjustment-type” rather than “Specific-Investment” lending instruments. • WHY?: Found easier, i.e., shorter preparation time and faster disbursement. • Initially the Roads III project was supposed to be a Programmatic SAL, actually the first of a series of 2-3 projects for a total Bank support of US$400 million during the next 4-5 years… • BUT finally we agreed to use an innovative “program-based” approach which allowed to preserve the above “Adjustment” benefits through a Specific Investment Loan….

  6. Main features of the RM&R project • Project amount: US$175 million, of which the World Bank finances 72%; • WB’s support focusing on road maintenance & rehabilitation works (sub-program financed at 2/3 or 67%); • WB funds were pooled with 2004 national budget for roads maintenance (see table next slide); • Environmental/Social andProcurement due diligence were carried out during project preparation to assess and to approve country own procedures (in view to grant country “certification” for future projects); • Environmental category: Financial Intermediary (FI). Publication of project Operational Manual chapter on environment and social was the only pre-requisite for appraisal.

  7. Poland RM&R project is a new kind of “hybrid” This component is financed under a pooling of funds scheme All the other components are using standard WB rules The loan amount (Euro 100 million equivalent US$126 ) was requested by the borrower to match with its budget planning and to minimize the loan’s fees (Front-end and commitment fees)…. [1] This amount corresponds to the national budget allocation 2004 for maintenance and reparation works for the national road network (Detailed figures in annex 5). [2] Corresponds to a financing ratio of 67%. [3] Identifiable taxes and duties are US$m0, and the total project cost, net of taxes, is US$m199.9. Therefore, the share of project cost net of taxes is 0%.

  8. Fast track preparation: • Concept review meeting April 2003 (Programmatic SAL); • ROS meeting Nov. 2003 (PSAL was not an option anymore!) • Pre-appraisal in Dec. 2003 (OK with a SIL) • Safeguard consultation meeting: January 12, 2004 • Quality Enhancement Review meeting: January 13, 2004 • 2nd Project decision meeting: January 26, 2004 • Appraisal/negotiations: mid February 2004 • Board presentation: March 30, 2004 • “…congratulations to the project team!” 3 Months

  9. Fast track implementation: • Board presentation: March 30, 2004 • Loan signature: April 7, 2004 • Loan effectiveness: June 15, 2004 • Project launching: June 15, 2004 • First supervision September/October 2004 • Disbursed as end of October: US$113 million • About 90% of the total loan proceeds • 164 contracts procured under NCB (see following table) • For a total of US$163.6 million of which 43.8% invoiced 4.5 Months

  10. Implementation by component (Feb. 2005)[WB disbursement %] • A – GDDKiA Modernization Action Plan (MAP)[25.0%] • Independent technical audit of the GDDKiA completed by December 2004 – Revised MAP under preparation: • B – Road Maintenance & Rehabilitation Program[100.0%] • Completed by end of October • C – Road Safety Improvement Program[10%] • Will continue until completion of Roads II (June 2006) • D – Promotion of PPP in the road sector[5.0%] • Selection of consultant under Spanish CTF on-going. Final report available by September 2005.

  11. Conclusions 1/2 • Our Polish client clearly likes this new form of partnership; • A “repeater” US$130.5 million RM&R II project has just been negotiated for 2005 (through video conference in less than two hours); • Previous projects – especially RM&R I project -- have helped for new “repeater “ project preparation; • Fundamentals: • Based on reciprocal trust between World Bank and “mature” client countries; • Shifting from an”ex-ante” to “ex-post” control system; • Report-based, faster disbursement against % of total program expenditures; • Maximized use of existing administrative procedures, with a few exceptions; • Not tying up huge amount of loan, but fitting Client’s fiscal year budget

  12. Conclusions 2/2 • Main changes in the “repeater” RM&M II project: • Same €100 million Specific Investment Loan for year 2005 but with: • increased scope of works allowed, i.e., significant changes in the road geometry within the right of way, using national environmental/social requirements as acceptable to the World Bank; • launching of procurement process before project approval; • further simplification in reporting requirements, e.g., suppression of the quarterly consolidation report; • Further proposal for simplification, i.e., single category of expenditure not yet approved!

  13. The Road Maintenance & Rehabilitation I & II Projects for Poland “Program-based” Approach projects Thank you! • SWAp Session in Open eXchanges February 24, 2005

More Related