Tier-1 SC4 planning Update on the planning material. GDB meeting CERN 8.11.2005 Alberto Aimar alberto.aimar@cern.ch. Background information. Sites submitted plans at the GDB in Bologna Different format Quite different content. Templates for Planning.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Tier-1 SC4 planning Update on the planning material' - wylie-hancock


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
tier 1 sc4 planning update on the planning material

Tier-1 SC4 planningUpdate on the planning material

GDB meeting

CERN 8.11.2005

Alberto Aimaralberto.aimar@cern.ch

background information
Background information
  • Sites submitted plans at the GDB in Bologna
    • Different format
    • Quite different content

CERN - LCG

templates for planning
Templates for Planning
  • The MB agreed to change the way projects do planning and are monitored and reviewed
    • Milestone tables for each site/area/project
    • Templates to have the same format
    • Review of the plans in order to have consistent content, naming, timescale
    • Compare with the needs of the users
  • Converted all plans to the templates
    • Added high-level milestones
    • Capacity, bandwidth, service availability

CERN - LCG

planning for sc4 and beyond
Planning for SC4 (and beyond)
  • Each plan needs to be completed by every site
  • Adding information
  • Verify if they are consistent with the High Level plan
  • Check if they meet the needs of the experiments
  • Used at least to discuss on clear and organized information
  • Used to plan, monitor and report the status
  • The goal is to identify problems (and react) as soon as possible

CERN - LCG

examples
Examples
  • Adding information
    • Clear capacity and performance availability at key dates SC3: Jan 06, SC4: April 06, Jul 06
    • Clear planning of installations and changes in the services providedSRM 2.1, LFC, FTS, CE, RB, BDII, RGMA
    • Several steps needed to set-up hardware or a service (ex: choose, procure, start install, end install, make operational)
    • Include important infrastructure not only software and computers

CERN - LCG

slide11
PIC

Clear capacity and performance availability at key dates

CERN - LCG

cc in2p3
CC-IN2P3

Clear planning of installations and changes in the services provided

SRM 2.1, LFC, FTS, CE, RB, BDII, RGMA

CERN - LCG

slide13
RAL

Include important infrastructure

not only software and computers

CERN - LCG

us atlas bnl
US ATLAS (BNL)

Several steps needed to set-up hardware or a service

(ex: choose, procure, start install, end install, make operational)

CERN - LCG

first version of the plans

M.Vetterli (Canada, TRIUMF)

  • F,Hernandez (France, CC-IN2P3)
  • H.Marten (Germany, FZK)
  • M.Mazzucato (Italy, CNAF)
  • K.Bos (Nederlands, Sara-Nikhef)
  • B.Vinter (NDGF)
  • G.Merino (Spain, PIC)
  • T.Cass (Switzerland, CERN)
  • S.Lin (Taipei, ASGC)
  • A.Sansum (UK, RAL)
  • B.Gibbard (US, BNL)
  • I.Fisk (US, FNAL)
First version of the plans
  • Plans have to be enriched with more milestones and information
  • Identify the people in charge

CERN - LCG

next steps
Next Steps
  • Today: Ask sites to review/add milestones (urgent)
    • Capacity and bandwidth available (Jan 06, Apr 06, Jul 06)
    • Services installations and upgrades: SRM 2.1, LFC, FTS, CE, RB, BDII, RGMA
    • Operations organization, installation, deployment
    • Procurement milestones
    • Details and comments
  • 16 Nov 05: Send me a new version in one week
  • Nov 05: I will contact on what is missing/unclear, discuss in order to complete the plan
  • Dec 05: Review, ask questions, discuss with the users, compare with the needs/schedules (capacity, services etc.) of the experiments
  • Jan 06: Used to plan, monitor and report
  • Summary at the GDB meetings