An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities

  2. Agenda • Introduction Dr. Green • Project Overview Rob Gaertner • Questions/Comments

  3. Introduction • Projects were included in the 2010/11 Capital Funding Plan • Address ongoing maintenance of the District’s facilities. • The total value of the major construction contracts that were awarded is $861,390.

  4. Roof Replacement at McKnight Elementary School • Replaced 42,500 square feet of rubber roofing that was installed in 1990. • Replace Greenhouse roofing, gutters and downspouts. • Installed new roof insulation. • Replaced and relocated roof drains. • Installed new metal roof edge. • Project should be substantially completed on August 25, 2010.

  5. McKnight Elementary School

  6. Installation of Elevators for the Cafeteria and Technology Education areas at NAI • Replaced the existing chair lifts with elevators. • Modified existing building to provide space for the two new elevators and equipment rooms. • Provide a Student Activities area in the lobby outside of the Cafeteria. • The Café Elevator is scheduled to be inspected on August 20, 2010. • The Tech Ed Elevator is tentatively scheduled for inspection on August 27, 2010

  7. NAI Cafeteria Elevator Installation

  8. NAI Student Activities Area

  9. NAI Tech Ed Elevator Installation

  10. Masonry Repairs at Bradford Woods Elementary • Removal and replacement of the glazed brick installed above the Kitchen and Receiving area doors. • Removal and replacement of the five brick piers on the sides of the main entrance stairs. • Project was completed on July 23, 2010.

  11. Masonry Repairs at BWE

  12. Greenhouse Masonry Repairs at McKnight • This project included the repairs to the existing masonry around the base of the Greenhouse. • Installation of a coating of mortar over the existing block to seal the existing masonry. • Installation of a stainless steel flashing around the base of the greenhouse glazing to direct the water away from the masonry. • Sealing of the new masonry coating. • This project was completed on August 13, 2010

  13. Greenhouse Masonry Repairs at McKnight

  14. Installation of Additional Exterior Cameras at NASH • Installed fourteen additional digital cameras around the exterior of NASH. • Student Parking Lot – 4 • Around the perimeter of the building - 10 • Installed ten additional digital cameras around the interior of NASH. • Inside the Stair Towers – 8 • Cafeteria - 2 • This project should be completed by August 30, 2010.

  15. Installation of Exterior Door Card Key System at MMS • Installed card key access control system on 4 exterior doors at MMS. • Auditorium Entrance • Gym Entrance • Receiving Area • Back of Gym • This work was completed on August 17 , 2010.

  16. Other Projects • Painting of the exterior steel at BWE. • Repairs to the gutters at BWE, MES, MMS and the Baierl Center – In Progress. • Modifications to the ductwork for the IT Server Room HVAC system. • Concrete Sidewalk and Curbs Repairs at: • BWE, MES, McK, and NAI • Driveway and Parking Lot Repairs at: • HES, IES, McK, NAI and Transportation

  17. Other Projects • Subdivision of Room 107 at IMS. • Construction of the Cumberland Campus trail. • Replacement of the projection screen on the stage at CMS. • Installation of wall pads in the small gym at NAI – In Progress. • Repairs to the locker room shower controls at NASH. • Installation of electronic ballasts in the classrooms at NAI – On Going.

  18. Questions/Comments