Palomar West Medical Center Segmental Review. Brett W. Beekman, S.E. Senior Structural Engineer, Southern California. Segmental Review Pilot. Palomar West Medical Center Located in Escondido, San Diego County 11 story steel framed structure with one basement level

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Palomar West Medical Center Segmental Review' - woody


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
palomar west medical center segmental review

Palomar West MedicalCenter Segmental Review

Brett W. Beekman, S.E.Senior Structural Engineer, Southern California

segmental review pilot
Segmental Review Pilot

Palomar West Medical Center

Located in Escondido, San Diego County

11 story steel framed structure with one basement level

Gross square feet: 725,000

Number of beds: 328

Estimated construction cost: $400,000,000.00

segmental review pilot1
Segmental Review Pilot

InpatientTower

Floors 1 - 11

D & T Low-rise Base

Floors 1 - 3

break down of increments
Break Down of Increments
  • Increment 1: Foundation Only Package
  • Increment 2: Architectural & MEP
  • Increment 3: Exterior Curtain Wall Systems
  • Increment 4: MEP & Medical Equipment Anchorage
  • Increment 5: MEP Pipe, Duct & Conduit Bracing
  • Increment 6: Major Structure Except Foundation
scope of increments 1 6
Scope of Increments 1 & 6
  • Increment 1 originally contained the entire major structure including foundation and was divided into 5 segments
  • The foundation was separated into it’s own increment, at owner’s request & became Increment 1
  • Increments 2 - 5 were already designated & input into Logbook, OSHPD’s project tracking system
  • Increment 6 added and includes the balance of the major structural system
increments 1 6 segments
Increments 1 & 6 Segments

Scheduled Actual Scheduled Actual

Submittal Submittal Approval Approval

Date Date Date Date

Segment 1 (Detailed Approach) 2/14/07 2/22/07 3/16/07 4/03/07

Segment 2(Loading Criteria) 3/05/07 3/08/07 3/30/07 4/20/07

Segment 3A(Lateral Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07

Segment 3b(Gravity Comp. Model) 4/11/07 4/11/07 7/30/07 8/02/07

Segment 4(Specs, Gen’l Notes, etc) 6/04/07 6/04/07 8/31/07 9/07/07

Segment5A(Foundation, Basement) 7/02/07 7/02/07 9/28/07 10/12/07

Segment5B(Diaphragm Design) 7/02/07 7/02/07 9/28/07 11/02/07

increments 1 6 submittals
Increments 1 & 6 Submittals

Increment 1: Foundation Only Submittal

  • Submitted on time (9/28/07)
  • Scheduled completion date 12/21/07
  • Change in code necessitated reevaluation of soils report
  • Ground motion studies were the main focus of the reevaluation.
  • Alternate Method of Compliance granted allowing use of the 2007 CBC

Increment 6: Superstructure Submittal

(excluding foundation)

  • Submitted on time (9/28/07)
  • Scheduled completion date 3/25/08
  • Revised completion date 4/15/08
  • A Wind Tunnel study proposed by the SEOR was implemented during segment 3A and focused on local wind pressures at corner conditions
increment 2 submittal
Increment 2 Submittal

Increment 2: Architectural and MEP Submittal

  • Submitted on 9/28/08
  • Revised submittal on 12/4/07
  • Scheduled completion date 9/28/08
  • Several items from Increments 1 or 6 were included in Increment 2 to facilitate the respective approval schedules
  • Items moved to Increment 2 included
    • Loading Dock and Block House Foundations
    • Site Walls and Window Washing Davits
increment 3 submittal
Increment 3 Submittal

Increment 3: Exterior Curtain Wall Systems Submittal

  • As of 2/15/07, the “Begin the Review Process” was scheduled as “TBD”
  • 100% CD set submittal scheduled for 9/07
  • Review to be completed by 6/08
  • Unforeseen conditions resulted in a schedule modification
  • New schedule for the Curtain Wall Submittal has been broken into 5 segments
increment 3 segments
Increment 3 Segments

Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval Date Date Date Date

Segment 1 5/12/08 9/12/08

(Package 1, Phase 1)

Segment 2 6/16/08 10/17/08

(Package 2, Phases 2-3-4)

Segment 3 9/22/08 1/16/09

(Package 3, Phases 5-6)

Segment 4 10/20/08 1/23/09

(Package 4, Phases 7-8)

Segment 5 1/12/09 5/15/09

(Package 5, Phases 9-10)

increment 4 submittal
Increment 4 Submittal

Increment 4: MEP & Medical Equipment Anchorage Submittal:

  • As of 2/15/07, the “Begin the Review Process” was

scheduled as starting 2/08

  • 100% CD set submittal scheduled for 9/08
  • Review to be completed by 9/09
  • Unforeseen conditions resulted in a schedule modification
  • New schedule has been broken into two segments
increment 4 segments
Increment 4 Segments

Scheduled Actual Scheduled Actual Submittal Submittal Approval Approval Date Date Date Date

Segment 1 4/30/08 1/30/09

(MEP Equipment Anchorage)

Segment 2 6/30/08 2/27/09

(Medical Equipment Anchorage)

increment 5 submittal
Increment 5 Submittal

Increment 5: MEP Pipe, Duct & Conduit Bracing

  • As of 2/15/07, the “Begin the Review Process” was scheduled as

“TBD”

  • 100% CD set submittal scheduled for 9/08
  • Review to be completed by 9/09
  • Unforeseen conditions resulted in a schedule modification
  • New submittal date is 5/08
  • Review to be completed 7/09

The design team has requested the package be submitted and permitted on a floor by floor basis. This request is currently under review.

phased review lessons learned
Phased Review - Lessons Learned
  • Continual communication between OSHPD, contract reviewers and designers is essential in segmented review
  • Coordination between disciplines on the design team is essential
    • Continuously updating team on changes in the design
  • Submit long lead reviews, i.e. geotech reports, design criteria, AMC, material testing reports, etc., far in advance of plan review submittals
more lessons learned
More Lessons Learned
  • Deciding what to put into each increment is key
    • Including “unique” items may shift focus from major portions of the work
  • Use every tool in the box
    • Reminders and checklists
    • Review FAQs, PINs & CANs
  • Flexibility by all parties is essential in resolving schedule conflicts and design changes