Department of Transport . Department of Transport. MTEF And Strategic Plan Presentation To Select Committee Presentation by Ms M. Mpofu Director General: Transport 27 May 2008 . Department of Transport. Contents.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Department of Transport' - wilford


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
Department of Transport

Department of Transport

MTEF And Strategic Plan Presentation To

Select Committee

Presentation by Ms M. Mpofu

Director General: Transport

27 May 2008

slide2
Department of Transport

Contents

  • Vision, Mission, Mandate and Values
  • DoT Strategic Focus Areas
  • Management Issues
  • Performance Highlights for 07-08 financial year
  • Context of DoT Strategic Plan
  • 5.1 January 2008 Cabinet Lekgotla Resolutions
  • 5.2 Cluster Priorities for 2008
  • 5.3 Apex Priorities
  • Overview of 2008 Medium-Term Expenditure Budget
    • 6.1 List of additional allocations
    • 6.2 Issues highlighted by the Minister of Finance
    • 6.3 Budgets per Programme
    • 6.4 Breakdown of major budgets
    • 6.5 Other budgets and major projects
    • 6.6 Under expenditure in 2007/08
    • 6.7 Gautrain expenditure and budgets
    • 6.8 PTIS expenditure and budgets
    • 6.9 Growth in major capital budgets
  • Planned projects/activities over next three years

2

vision and mission
Our Vision

“Transport, the Heartbeat of Economic Growth and Social

Development”

Our Mission

to “Lead the development of efficient integrated transport systems

by creating a framework of sustainable policies and regulators and

implementable models to support government strategies for

economic, social and international development.”

Vision and Mission

3

dot mandate
Our Mandate

to maximize the contribution of transport to the economic and social development goals of the society by providing fully integrated transport operations and infrastructure.

Our Values

Maintain fairness and equity in all our operations

Strive for quality and affordable transport for all

Stimulate innovation in the transport sector

Ensure transparency, accountability and monitoring for all operations

Ensure sustainability, financial affordability, accessibility as well as the upholding of the Batho Pele principles.

DOT Mandate

4

dot focus areas
To effectively manage a national innovative research centre and provide economic advice and analysis for all modes of transport

To create an enabling regulatory environment for road, aviation and maritime transport, and manage accident and incident investigations in all modes of transport

To manage and facilitate integrated planning and intersphere coordination for transport infrastructure and operations

DOT Focus Areas

5

dot focus areas cont
To manage the implementation of the transport logistics strategy and the development of freight movement corridors

To develop integrated accessible and affordable quality public transport networks that meet the needs of both rural and urban passengers

To develop appropriate mandates and monitoring mechanisms for public entities

DoT Focus Areas (Cont…)

6

slide7
Department of Transport

DoT

07-08 Performance Highlights

7

slide10
Department of Transport

Context for DoT Strategic Plan

10

slide11
January Cabinet Lekgotla Resolutions
  • Integrated infrastructure plan
  • Implementation of the industrial policy
  • Implementation of Public Transport Key Action Plans

(Taxi recapitalization, subsidy system and investment plans)

  • Road accident fund
  • Implementation of the Rural Transport strategy and Implementation of Shova- Kalula
  • 2010 FIFA World Cup – progress, challenges and interventions required
  • Inter - cluster activities

11

cluster priorities
Economic Cluster Priorities

Integrated infrastructure Plan – De Hoop Dam Pilot Project.

Electricity Shortage intervention plan

Increase economic efficiencies- ICT, Phased Rollout of Public Transport network

Second Economy Framework integrated into Anti –Poverty Strategy

Promote dynamic growth sectors- implementation of the industrial policy

Integrate support for small and micro- enterprises

Governance and Administration ClusterPriorities

Capacity of the state – 5 year local govt. agenda, Skills assessment and Capacity Development

Good Governance- Anti- Corruption, Gender and Disability, Batho Pele and Public Participation

Transversal Systems- Integrated Planning, the Government Wide- Monitoring and Evaluation System and the National Statistics System (NSS)

ClusterPriorities

12

cluster priorities continued
International Relations, Peace and Security

Consolidation of the African Agenda

The strengthening of the South- South Co-operation

Strengthening of the North- South Co-Operation

Participating in a Global System of Governance- Multilaterals

The strengthening of political and economic relations- Bilaterals

Justice Crime Prevention and Security Cluster Priorities

Crime Prevention and Public Safety

Upholding National Security

Big events

Social Cluster Priorities

Second Economy Interventions: Social Sector Cluster Aspects

Comprehensive Anti-poverty Strategy

Social Crime Prevention

ClusterPriorities (continued)

13

apex priorities business unusual
Industrial Policy Action Plan (Project 1, Economic Cluster)

Self-employment interventions in the Second Economy

(Project 9, Economic Cluster)

Speed up community infrastructure programme (Project 10 Social Cluster)

Ensure integrated planning across all spheres

(Project 16, G&A Cluster)

Improve civic services (Project 17, G & A Cluster)

Implement special crime combating and security initiatives (Project 18, JCPS)

Consolidate advances relating to peace and reconstruction in DRC (Project 22, IRPS)

Apex Priorities (Business Unusual)

14

slide15
Department

of Transport

Overview of 2008 Medium-

Term Expenditure Budget

15

slide16
Issues highlighted by the Minister of Finance

Department of Transport

  • PPP arrangements in funding large infrastructure projects, particularly in passenger rail
  • Institutional arrangements and concurrent functions in transport, specifically the roles and responsibilities in public transport
  • Progress on the Bus Rapid Transit system and PTIS spending and delivery in general
  • RISFSA road quality assessments, reclassification and criteria for prioritisation

16

issues highlighted by the minister of finance
Alignment of the subsidised bus routes with the Public Transport Strategy and Rural Transport Strategy

Outstanding business plan for Shosholoza Meyl as a ring fenced business within the SARCC.

Finalisation of the National Land Transport Bill.

Development of the institutional and regulatory framework to guide the implementation of the National Freight Logistics Strategy.

Issues highlighted by the Minister of Finance

Department

of Transport

17

slide18
Additional allocations

Department of Transport

18

slide19
Budgets per Programme

Department of Transport

19

slide20
Breakdown of major budgets (Continued)

Department of Transport

R’000

  • Allocations for rail operations and capital remain the largest single budget item.
  • The budget for road infrastructure overtakes that of bus subsidies from 2007/08 onwards.
  • Allocations for infrastructure from the Public Transport Infrastructure and Systems Grant was introduced in 2005/06 at R241,7m, growing to R700m in 2006/07.
  • The National contribution to the Gautrain Rapid Rail Link was introduced in 2006/07 at R3,241Bn, and declines to R317,5m in 2010/11

20

slide23
1

200,000

2

150,000

3

4

100,000

5

6

7

50,000

8

9

10

11

12

13

14

15

16

0

Breakdown of major other budgets for 2008/09

Department of Transport

23

slide24
Budgets per economic classification

Department of Transport

24

slide27
Gautrain expenditure and budgets

Department of Transport

R Million

Actual

--------Medium term budgets--------

Actual

2008/09

Total budget R12,36 bn over 5 years

27

slide28
PTIS expenditure and budgets

Department of Transport

Actual

Actual

----Medium term budgets-----

Actual

R Million

2008/09

Total budget R13,6 bn over 6 years(excl. monitoring & evaluation)

28

slide29
(R’000)

Growth in major capital budgets

Department of Transport

29

slide30
Under expenditure in 2007/08

Department of Transport

30

slide31
Under expenditure in 2007/08

Department of Transport

  • The National Land Transport Information System and Arrive Alive project was not funded and the department identified and shifted savings within the department late during the 07-08 Financial Year.
  • The development of several policies was delayed due to sub standard bids received and delays in the payment to service providers who still have some work to complete.
  • The major areas and reasons for under expenditure in the Programme are detailed below:
  • 3.1 Economic Regulation (Road Transport) R1,3 million:
  • Funds have been allocated to this component for operational expenditure but no posts could be filled in time in this regard to perform the functions attached to this post - this was after the resignation of the project leader.
  • 3.2 Standards Regulation R3,4 million:
  • The Director attached to this component was only appointed during the second half of the financial year and he was only able to appoint the officials in the vacant posts during the second half of the financial year which had a negative influence on the operational expenditure (under expenditure). The appointees also had to be trained in service.

31

slide32
Under expenditure in 2007/08

Department of Transport

  • 3.3 Traffic Safety Systems R5,113 million:
  • This under expenditure relates to the non transfer of the eNaTIS project to the RTMC.
  • 3.4 Rail Transport Regulation R2,323 million:
  • Non appointment of any official in this component. One official in the then Rail Economic Regulation handled the establishment of the Rail Economic Regulator.
  • 3.5 Civil Aviation Security R1,625 million:
  • A service provider has been appointed at a late stage to develop a security system for the OR Tambo Airport. The appointment has only been finalised in the 2008/09 financial year.
  • 3.6 Maritime Safety and Bilateral Affairs R4,716 million:
  • Lack of capacity limited the development of the Maritime Safety Coordination Centre in its full context.

32

slide33
Under expenditure in 2007/08

Department of Transport

  • 3.7 Aviation and Maritime Investigations R3,483 million:
  • Funds have been allocated for the Commissioner of Civil Aviation which did not take place in the 2007/08 as clarity did not exist whether this function must be transferred from the SACAA to the Department. The FAA investigation and report and the published Civil Aviation Bill of 2008 give clear guidance in terms of the way forward with regard to this matter. It is envisaged that the Bill will be passed through the Parliamentary process during this Parliamentary session.
  • 4 & 5. The Programme did not have enough funds to procure the required number of bicycles (500,000), which delayed the tender process. Most of the under expenditure was earmarked to purchase 60,000 bicycles and a rollover of R30,98 million was applied for. The remaining funds were earmarked for the National Airports Development Plan (NADP) and a rollover of R7 million was applied for. The appointment of an appropriate service provider too eight months for the NADP.
  • The Programme also applied for other rollovers of R6,5 million for projects that were delayed and longer term projects, such as the National Transport Master Plan, development of the National Land Transport Bill, and the development of guidelines and standards for monitoring of Transport Planning.

33

slide34
Under expenditure in 2007/08

Department of Transport

  • Amounts budgeted to assist Provinces with the construction of the Sani Pass and overload control facilities could not be paid because the budgets were not included in the Division of Revenue Act, and because there was uncertainty about the appropriate method of payment and ownership of the assets.
  • The Treasury recommended that the Department should apply to roll over the funds and have the funds allocated to the Provinces via the Division of Revenue Act or Provincial Infrastructure Grant.
  • The Department, in collaboration with the Treasury’s PPP Unit, invited Requests for Proposals in September 2007, and planned to appoint service providers to develop the feasibility study for which R20 million was earmarked. The bids that were received were referred to the SARCC as the SARCC would be in a better position to manage the project. The Department applied to roll over the R20 million and to increase the transfers to the SARCC by that amount.
  • 8.1 All of the funds that were budgeted for the scrapping of taxis were paid to the Scrapping Administrator by 31 March 2008. R7,25 million could not be utilised by 31 March 2008, because the scrapping process was slowed down to accommodate the available budget.

34

slide35
Under expenditure in 2007/08

Department of Transport

  • 8.2 The Department withheld transfer payments to SANTACO amounting to R8,9 million, because SANTACO could not provide progress reports and financial statements as required in the contract.
  • 9. An amount of R14 million could not be spent on the RAF restructuring because Regulations had to be developed for the RAF Amendment Act before various provisions dealing with the liability of the RAF could come into operation. There were also delays due to the ill health of the Minister of Health, who has to be consulted on certain provisions.
  • 10. The Ports Regulator only became operational late in the financial year, because the CEO could only be appointed in March 2008. During the year, effective governance structures were developed, and premises were secured and equipped. The Department made payments on behalf of the Ports Regulator, but could not transfer the amount budgeted, because the entity only became operational in March 2008.

35

slide36
Planned projects/activities over next three years

Department of Transport

Programme 2.

Transport Policy

&

Economic Regulation

36

slide42
Planned projects/activities over next three years

Department of Transport

Programme 3

Transport Regulation and Accident & Incident Investigation

42

slide43
Quick Wins for 2008/09

Department of Transport

43

slide44
Quick Wins for 2008/09

Department of Transport

44

slide45
Quick Wins for 2008/09

Department of Transport

45

slide48
Planned projects/activities over next three years

Department of Transport

Programme 4.

Integrated Planning & Intersphere Coordination

48

slide49
Department of Transport

Quick Wins for 2008/09

49

slide50
Department of Transport

Quick Wins for 2008/09

2010 FIFA World Cup™

50

slide51
Department of Transport

Quick Wins for 2008/09

2010 FIFA World Cup™

51

slide52
Department of Transport

Quick Wins for 2008/09

52

slide53
Integrated Planning & Intersphere Coordination

2009-10

Department of Transport

53

slide54
Integrated Planning & Intersphere Coordination

2010-11

Department of Transport

54

slide55
Planned projects/activities over next three years

Department of Transport

Programme 5:

Transport Logistics and Corridor Development Branch

55

quick wins for 2008 09
Quick Wins for 2008/09

Department of Transport

56

quick wins for 2008 0957
Quick Wins for 2008/09

Department of Transport

57

slide60
Planned projects/activities over next three years

Department of Transport

Programme 6

Public Transport

60

slide61
Quick Wins for 2008/09

Department of Transport

PT Operational Modal plans for 2010 FIFA World Cup

61

slide62
Quick Wins for 2008/09

Department of Transport

Second Phase of passenger rail consolidation

62

slide63
Quick Wins for 2008/09

Department of Transport

Acquisition of Autopax

63

slide64
Department of Transport

Quick Wins for 2008/09

Turnaround Strategy for OLB’s

64

slide65
Department of Transport

Public Transport

2009-10

65

slide66
Department of Transport

Public Transport

2010-11

66

slide67
Planned projects/activities over next three years

Department of Transport

Programme 7

PUBLIC ENTITY OVERSIGHT AND BORDER CONTROL

67

public enterprises reporting to dot
Public Enterprises reporting to DoT

Department of Transport

68

quick wins for 2008 0969
Quick Wins for 2008/09

Department of Transport

69

quick wins for 2008 0970
Quick Wins for 2008/09

Department of Transport

70

slide73
Planned projects/activities over next three years

Department of Transport

Management Services

73

slide74
Quick Wins for 2008/09

Department of Transport

74

slide75
Quick Wins for 2008/09

Department of Transport

75

slide76
Management Services

2009-10

Department of Transport

76

slide77
Management Services

2010-11

Department of Transport

77

departmental structure
DEPARTMENTAL STRUCTURE
  • Total Establishment: 1020
      • 668 posts activated
      • 352 posts inactive
  • Vacancy rate 35.48%
  • Current turnover rate:10,67% (46)
  • Number of internal promotions (Apr – March ’08): 32

78

slide83
Advertising

Prepare advert & confirmation 3 days

Procurement 2 days

Run advertisement for 2 weeks

Executive Summary

+-2 working days per post depending on the number of posts

Final 1 Month depending on the availability of managers & applications received

Short-listing

Preliminary: 1 day

Final: 1 Month depending on the availability of managers

Tests

Competency: Conducted within 2 weeks from date of scheduling

PPA: On the date of interview

Interviews

A week after the Competency Assessment report is due

 Submission for filling of post

5 working days (within HRM)

 Appointment Offer

1 day

 Total

3 Months

FILLING OF POSTS TIMETABLE

83

internal bursaries
RACE

GENDER

TOTAL

A

W

I

C

F

M

129

4

6

3

86

55

142

Active Bursaries

51

Not Active

71

Resigned from Public Service

3

Studies Completed

5

Transferred files

11

Withdrawn

1

TOTAL

142

Internal BURSARIES

86

interventions to reduce the vacancy rate to 17 by march 2009
INTERVENTIONS TO REDUCE THE VACANCY RATE TO 17% BY MARCH 2009
  • Weekly monitoring the vacancy rate
  • Implementation of Retention Policy:
  • -Relationship management interventions
  • -Employee satisfaction survey
  • -Reward outstanding performers with scarce &
  • critical skills
  • Accelerated management development programmes
  • Streamline the short listing process
  • Outsourced response handling for posts below SMS

89

job standardization job evaluation
The job standardization process has been finalized and related posts job evaluated,

JE Unit consulted the DPSA to seek clarity on some issues raised by the JE Panel,

JE Panel to finalize all outstanding cases by end of May 2008,

JE conducted in line with the Public Service Regulations, 2001 and DPSA’s directives:

Departmental Job Evaluation Policy,

Benchmark similar posts within and against other Depts,

Job enrichment where applicable,

Implement DPSA’S benchmark job descriptions.

JOB STANDARDIZATION / JOB EVALUATION

90

slide91
STATUS OF PMDS
  • Employees on salary levels 12 and lower
  • 2007/08 performance cycle
    • Annual Performance Assessment finalized: 317
    • Outstanding: 0
  • Employees on SMS level
  • 2005/06 and 2006/07 performance cycles
    • Moderation of performance ratings currently underway.
  • 2007/08 performance cycle
    • Performance Agreement submitted: 69
    • Outstanding: 15
    • SMS members recently appointed: 4

91

slide92
Quick wins – 2008-09

Financial Services

92

slide93
Quick Wins for 2008/09

Department of Transport

93

slide94
Quick Wins for 2008/09 (continued)

Department of Transport

94

slide95
Quick Wins for 2008/09 (continued)

Department of Transport

95

slide96
Department of Transport

Office of the DG

96

2008 09 business plan
2008/09 Business Plan

Fully functional M&E system for DoT Flagship Projects

97

slide98
Department of Transport

Communications