An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Production - Part II Kaushik De Univ. of Texas at Arlington U.S. ATLAS Grid Workshop Boston, June 2002

  2. Atlfast Production Schedule - July • July 1-15: Phase 0, 10^7 events • Globus 2.0 beta • Grappa - 3.0.1, common disk model • Dan Engh, Horst Severini, Kaushik De • Magda - data management • Wensheng Deng, Ed May • 5 physics processes - http cached • Kaushik De • BNL VO manager • Rich Baker • Random job scheduler • Kaushik De • GridView+perl? Monitoring • PatrickMcGuigan, Dantong Yu

  3. Schedule - August • August 5-19: Phase 1 • 10^8 events @ all ATLAS sites • VDT 1.1.1 • Hierarchical GIIS server • GRAPPA - Athena-atlfast 3.2.0 • Magda - data & replica management, metadata catalogue • 10 physics processes • MDS based job scheduler • GridView+perl?+visualization

  4. Schedule - September • September 2-16: Phase 2 • 10^9 events @ all sites • 1 TB storage, 40k files • VDT, Grappa and Magda same • 20 physics processes • Upgraded BNL VO manager • Dynamic job scheduler • Fancy monitoring • Athena-atlfast 3.2.0 instrumented

  5. Long Production • Currently limited U.S. participation in DC1 - BNL only • Need packaging for U.S. grid deployment - NorduGrid? • CPU intensive - use farms • Quality of service important • Emphasis on Virtual Data • Plan: July-November 2002