New xTCA Developments at SLAC. CERN xTCA for Physics Interest Grou p Sept 26, 2011 Ray Larsen SLAC National Accelerator Laboratory. Topics. Standards developments Applications Demonstration Program Future Plans. Standards. Hardware, Software working groups meet weekly/ needed

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'New xTCA Developments at SLAC' - uyen


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
new xtca developments at slac

New xTCA Developments at SLAC

CERN xTCA for Physics Interest Group

Sept 26, 2011

Ray Larsen

SLAC National Accelerator Laboratory

New xTCA Developments at SLAC - R. Larsen

topics
Topics

Standards developments

Applications Demonstration Program

Future Plans

New xTCA Developments at SLAC - R. Larsen

standards
Standards
  • Hardware, Software working groups meet weekly/ needed
  • 2 new HW standards approved
    • ATCA
      • PICMG3.8 Standard IO interface to Rear Transition Module (RTM), IPMI extension & power connector
    • MTCA
      • MTCA.4 Crate, 2-wide AMC & RTM, IO interface, IPMI extension and power pins designated

New xTCA Developments at SLAC - R. Larsen

standard extensions for physics
Standard Extensions for Physics

New xTCA Developments at SLAC - R. Larsen

standards details
Standards Details
  • ATCA PICMG3.8
    • 120 5GHz BW IO channels on 3- 4x10 ZD connectors
    • New connector (Positronix) for IPM, power
    • Mechanical, E-keying functions
    • Implemented on SLAC MPP Processor (M. Huffer)
  • MTCA.4
    • Extends double-wide shelf (crate) to include RTM
    • 60 ChIO, IPMI on 2- 3x10 ZD connectors
    • Extended backplane timing, trigger, interlocks layer
    • Compatible with all existing 1-wide AMC products
    • Implemented by Schroff, ELMA, PT, others in dev’mt

New xTCA Developments at SLAC - R. Larsen

slide6

PICMG3.8 RTM Interface Standard

Rear View

120 - IO Channels (3x40)

IPMI, Power Connector (blue)

2 Mechanical Keys

Courtesy M. Huffer, SLAC

New xTCA Developments at SLAC - R. Larsen

mtca 4 amc rtm shelf concept
MTCA.4 AMC-RTM-Shelf Concept

New xTCA Developments at SLAC - R. Larsen

mtca 4 12 amc backplane
MTCA.4 12-AMC Backplane

Intlk, Vector Sums

Parallel Triggers

New xTCA Developments at SLAC - R. Larsen

slide9

MTCA.4 Backplane Timing Distribution

2 radial clocks per AMC,low jitter

MCH

Cross-

Point-Switch

Backplane

Central Timing

AMC

Timing

AMC

ADC

AMC

ADC

Enc.Clock

Enc.Clock

Trigger

Trigger

Interlock

Interlock

8 bussed lines,M-LVDS for

Clocks, triggers, interlocks

Courtesy K. Rehlich, DESY

New xTCA Developments at SLAC - R. Larsen

rtm extended ipmi circuit
µRTM Extended IPMI Circuit

New xTCA Developments at SLAC - R. Larsen

mtca 4 prototype shelves modules
MTCA.4 Prototype Shelves & Modules

Emerging New Electronics Standards - R. Larsen

mtca 4 12 slot shelf dual star
MTCA.4 - 12 Slot Shelf Dual Star

Back-Plane

Dual PU slot

Dual MCH Slot

12 Payload AMC-RTMs Dual Star Redundant Front View

New xTCA Developments at SLAC - R. Larsen

mtca 4 6 slot shelf non redundant
MTCA.4 - 6-Slot Shelf Non-Redundant

6 Slot Development Shelf

1-Star Non- Redundant

Front View

6-Slot Rear View

Courtesy Schroff, Struck

New xTCA Developments at SLAC - R. Larsen

slac applications demonstrations
SLAC Applications Demonstrations

LLRF for Main Linac S-Band 50MW station

Klystron interlocks for 10MW L-Band station

Beam Position Monitors for LCLSII Injector

New xTCA Developments at SLAC - R. Larsen

1 s band llrf
1. S-Band LLRF
  • Demonstrate intra-pulse feedback to achieve ~30fs phase control
    • Lower noise RF front end chassis
    • New solid state sub-booster
    • Feedback loop implemented in MTCA.4 using Struck 10 Ch ADC 2 Ch DAC developed w/DESY
    • New LCLSI waveguide water-stabilized rack
    • Test on Standby triggering, switch to Accelerate
  • Tests on accelerator to complete Oct 2011

New xTCA Developments at SLAC - R. Larsen

llrf mtca rf chassis testing
LLRF MTCA & RF Chassis Testing

New xTCA Developments at SLAC - R. Larsen

rear view
Rear View

New xTCA Developments at SLAC - R. Larsen

rtm inputs
RTM Inputs

Note – Preliminary RTM shown

Final RTM

with full IPMI complete, In test.

New xTCA Developments at SLAC - R. Larsen

rf chassis reference lo sources downmixers
RF Chassis – Reference, LO, Sources, Downmixers

Note – Next stage

plan is to test L-Band down-mixers, other RF modules in

MTCA card format

New xTCA Developments at SLAC - R. Larsen

amc 10 2ch adc dac 16bit 125 msps
AMC - 10/2Ch ADC/DAC 16bit 125 MSPS

Initial Applications:

LLRF DESY XFEL

LLRF SLAC Upgrade Proto

Photo courtesy M. Kirsch,

(Struck )

Emerging New Electronics Standards - R. Larsen

rtm 10 ch adc dac ipmi interface
RTM 10 Ch ADC-DAC, IPMI Interface
  • Rear Panel
  • Mini-Coax IF Signals In
  • RF Ref In
  • Trigger in
  • Dual I&Q DAC Out
  • IPMI Extension to RF Chassis

Courtesy A. Young, SLAC

Emerging New Electronics Standards - R. Larsen

2 mtca klystron interlocks s l band
2. MTCA Klystron Interlocks S&L Band
  • FPGA based interlocks in MTCA.4
    • S-Band interlocks currently in separate FPGA non-modular chassis
    • L-Band interlocks currently FPGA based in VME
    • MTCA solution will serve both in future
    • SLAC designed RTM mates to new TEWS Spartan 6 FPGA module (just received in US)
    • RTM testing starting
    • 1 board pair serves 8 Ch-60MSps, 16 Ch-2KSps
    • 2 board pairs serve 1 S- or L-band station

New xTCA Developments at SLAC - R. Larsen

rtm fpga interlocks
RTM FPGA Interlocks
  • Rear Panel
  • Inputs
  • - 8-60 MSps Ch
  • - 16-2 KSps Ch
  • - 12 bits Diff +/- 1V
  • - Diode protection
  • All channels
  • Outputs
  • - Interlock Sums
  • RF Interlocks for
  • L-Band 1 msec, S-band 1.5 µsec

Courtesy D.G. Brown, SLAC

Emerging New Electronics Standards - R. Larsen

amc tamc651 fpga w rtm
AMC TAMC651 FPGA w/RTM

Courtesy TEWS

Note – Completion date for ESB installation Dec. 2011.

New xTCA Developments at SLAC - R. Larsen

3 bpms for lcslii injector
3. BPMs for LCSLII Injector
  • Goal: Demonstration of 8 BPMs in 12-slot
    • RTM has 4 Ch analog plus calibration w/ strip-line coupling between 120 Hz pulses
    • AMCs will be 4 Ch 125 or 250 MSps (125 available now; 250 may be developed by commercial supplier(s)
    • 250 MSps needed if multibunch (2 bunches 8 nsec apart)
    • Requirements being finalized (16 bit ADCs)
    • Preliminary RTM layout indicates feasible

New xTCA Developments at SLAC - R. Larsen

bpm system block diagram
BPM System Block Diagram

Courtesy

S. Hoobler

et al, private communication

New xTCA Developments at SLAC - R. Larsen

conclusions 1
Conclusions 1
  • Standards for hardware have passed 2 major milestones
    • Committees will disband when SOWs complete
    • Software committee continues developing guidelines for architecture and protocols
    • Member labs remain involved in PICMG through Coordinating Committee for oversight, servicing tweaks
    • Start new initiatives, SOWs, form committees as needed

New xTCA Developments at SLAC - R. Larsen

conclusions 2
Conclusions 2
  • SLAC new initiatives open future opportunities
    • Main Linac RF upgrades for LCLSII, I.
    • BPM upgrades for LCLSII Injector, Main Linac
    • Interlock systems wholly contained in MTCA.4 combined RF-Controls package
    • Long range: Complete replacement CAMAC controls in 2-mile accelerator, $20M program
  • Timeline:
    • RF and interlock demos complete in Q1-2 FY12
    • BPM AIP completes Q2 FY13

New xTCA Developments at SLAC - R. Larsen