160 likes | 243 Views
This progress report covers the verification of power budget, building and testing new Tx board, alignment tolerance tests, and preliminary transmitter board test results. Challenges faced and next steps outlined for continued debugging and testing. Key consideration: driving Imod too high may affect chip or VCSEL.
E N D
ECE 4006B Fall, 2002, Group 3, ROBIEL TECLEMICHAEL Progress Report Period (November 7-14, 2002) Progress: • Power Budget has been Verified • Built a New Tx Board and the results are promising • Performed Alignment Tolerance Tests on Rx. • Big Obstacle!!!!! The System Test Module was Down NO EYE Next Week: • Continue Working on Tx Board • Continue Alignment Tolerance Tests on other PD
ECE 4006B Fall, 2002, Group 3, ROBIEL TECLEMICHAEL Progress Report Period (November 7-14, 2002) Tx Board Debugging • Built new board • Recalculated Rmod • Replaced 1K Rmod POT with 20K POT • Lowered VCSEL to less than 4mm from board • Cut off VCSEL leads • Next step: • Build and test new Tx • Potential Problem • Driving Imod too high could have effected the chip or VCSEL
ECE 4006B Fall, 2002, Group 3, ROBIEL TECLEMICHAEL Progress Report Period (November 7-14, 2002 Preliminary Transmitter Board Test Results- PRBS7
ECE 4006B Fall, 2002, Group 3, ROBIEL TECLEMICHAEL Progress Report Period (November 7-14, 2002
ECE 4006B Fall, 2002, Group 3, ROBIEL TECLEMICHAEL Progress Report Period (November 7-14, 2002) Center of Measurement Sample 10 Points Eye for raised Z by 0.87mm