1 / 13

Upcoming Dates Accumulator Ring:

Upcoming Dates Accumulator Ring:. ASAC Review September 22-24 DOE Review October 2003 Extraction magnets being assembled Injection DC Magnets and Kickers ( Complete ) in House. HEBT and RTBT Collimators Delivered Ring 1 and 2 Collimator Chambers Coated Design complete July 2003

ulfah
Download Presentation

Upcoming Dates Accumulator Ring:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Upcoming Dates Accumulator Ring: • ASAC Review September 22-24 • DOE Review October 2003 • Extraction magnets being assembled • Injection DC Magnets and Kickers (Complete) in House. • HEBT and RTBT Collimators Delivered • Ring 1 and 2 Collimator Chambers Coated • Design complete July 2003 • More ½ cells delivered • First doublet cell assembled • RF Cavities delivered – scheduled for late September. • First quarter cell assembled

  2. Hot Topics • New ½ cell Lifting fixture design sent to ORNL for review. • Magnet heat load verification/water flow verification. Hemmer/Lambiase • Lambertson design review last week. • Lower pressure available. Need cable information. • List of Central Shops Work yet to • be done. • FY 2004 Budget • Commit FY 2003 Funding

  3. Hot Topics ORNL Wednesday Morning Phone Conference • Installation drawings – HEBT complete. • Magnet resistance measurements – record the coil temperature. • Magnet water flow measurements. • Water system pressure lowered to 100 psi or less delta P. • 36Q85 must define installation configuration (they are doing drawings). • Remote clamp design requires 3” of beamline space. • Lambertson final video conference, power point – mechanical design only, bidders list, install, lifting fixture, electrical spec.

  4. HEBT Magnets HEBT Dipole, 12Q45 Quadrupole, & 16CD20 Corrector HEBT/RTBT 27CD30 Corrector (BNL participation complete other than payment). • NETC – 7 verticals + 2 horizontals at ORNL . HEBT/RTBT 21Q40 Quadrupole – Phase II • 8 Magnets received BNL. • Second shipment dispatched end of June - Revised to July 11 – Revised to August 8, - Actual August 11, 8 magnets and 5 frames to ORNL. • Third shipment dispatched end of July? Final shipment dispatched end of August?.

  5. Ring Magnets • 902 ½ Cell Assembly Area • Production on hold for magnet acceptance/inspection • Lifting fixture for ORNL ring crane. • 17D120 - complete • 21Q40 Quadrupole – 29/29 in house • Shimming/magnetic measurement complete • Phase II HEBT 21Q40 magnets to be shipped to ORNL for testing. • 26Q Quadrupole Requisition(production measurementpriority 1) • Magnet measurement seven good magnets (three shimmed) • One magnet with high multipole component has been realigned. • Measurement schedule.

  6. Ring Magnets • 30Q Quadrupole Requisition (1st article measurement 30Q44 underway) • Shipment #1 in house • Shipment #2 in house • Shipment #3 in house, inspection • Shipment #4 in house, inspection • Shipment #5 on a truck • 21S26 High Field Sextupole (production measurements priority 2) • Production, 6 in house and accepted. • One shorted magnet returned to Alpha for repair? • 26S26 High Field Sextupole • 1st article approved 5/15/03 – In production. • 27CDM30 Corrector All Magnets in house

  7. Ring Magnets • 21CO26 Corrector – 8 at ORNL – one spare at BNL • 21CS26 Corrector – ALL 9 in house • Production Measurement complete. • 41CDM30 Corrector (production measurements priority 4) • 8 in house. • #5 failed high pot – returned to the vendor yet?? • #1 and #2 returned to the vendor. • 36CDM30 Corrector(production measurements priority 3) • 9 in house • 8 of 9 measured.

  8. Special Injection Magnets Injection Vacuum Chambers • In the shops – vacuum group to leak check. Injection Septum Magnet - magnet measurements in 902. • SDMS vacuum chamber to be shipped September 8. Injection Dump Septum Magnet (delivery date?), Chicane Magnet #2 (magnet meaurements), Chicane Magnet #3 (delivery date?), Chicane Magnet #4 (return to NETC) – Z Bumps IV in the works? Chicane Magnet #1 Alpha Magnetics delivery date ?? Thin Foil Mechanism – D. Gassner motor control design. Thick (Injection Dump) foil fabrication underway Magnet Stands – Complete (location?) Injection Kicker Magnets • Production Assembly #2 long pair complete, #1 short magnet pair complete. • Shipping container magnet. • Ceramic Chamber Coating Continuing

  9. Magnet Measurement Schedule First Articles • 26S26 – Done • 30Q44 – Done • 30Q58 – Done, high multipole component! • Chicane #2 • Chicane #3 • Chicane #4 • Chicane #1 • Chicane #2 and #3 together • Injection septum • Dump septum • 36Q85 • 36CDR30 • Lambertson Magnet Production Measurements LARGE APERTURE COIL SMALL APERTURE COIL • 41CDM30 – 2 Done • 26Q40 – 7 Done, one being realigned. • 21S26 • 36CDM30 – one left • Remeasure re-aligned 26Q40 • 26S26 • 30Q58 • 30Q44 • 21Q40 – RTBT magnets for ORNL • 41CDM30 • 36Q85/36CDR30 with 26 cm coil?

  10. Special Extraction And RTBT Magnets Extraction Kicker Magnets • Ferrite Order Complete • All drawings approved • Shops RFQ for downstream kicker assembly? Lambertson Magnet • Drawing being checked. • Specification and SOW complete. • ORNL Design Review Completed/Minutes Sent. 36Q85 - Fifth production coil winding complete 36CDR30 – All Coils Wound

  11. Collimators - HEBT Friday 11:00 Weekly Meeting in the EAG Conference Room • HEBT Collimator Beam Line Stand - RFQ approved • HEBT collimators at ORNL • HEBT Strippers 919B ready for assembly. • HEBT Momentum Collimator shielding contract with Oak Ridge Machine Shop • HEBT Momentum Collimator Shops RFQ. Remaining Work: Assemble and drive HEBT Strippers

  12. Collimators - Ring Friday 11:00 Weekly Meeting in the EAG Conference Room • Procurement STATUS SDMS – ring 1 (primary) collimator ordered • Ring Primary Collimator Drawings approved. • Change orders for ring 2 and 3 • Ring Moveable Scraper Fabrication Shop order 1072 • Moveable and Primary Shielding Layout must be revised for remote clamp. Remaining Work: Primary/Moveable Collimator Stand and Shielding, Assemble and drive moveable scrapers, Ring 1 and 2 shielding order

  13. Collimators - RTBT Friday 11:00 Weekly Meeting in the EAG Conference Room • RTBT #1 shipped August 14, 2003. • New RTBT #2 top lifting plate change order. Remaining Work: RTBT 1 and 2 shielding, stands, and jacks.

More Related