CC Poland PlusProjects Review Meeting 11-12 April 2011. Project overview “ EGOR-CO2 ” „ Integration of CO 2 Sequestration with EGOR-CO2 technology (Enhanced Gas and Oil Recovery method). ” Speaker: Stanisław NAGY. Clean Coal Technologies. Project summary. Project summary. Contents.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Project overview “ EGOR-CO2 ”' - tyra


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

CC Poland PlusProjects Review Meeting

11-12 April 2011

Project overview

“ EGOR-CO2”

„Integration of CO2 Sequestration with EGOR-CO2 technology (Enhanced Gas and Oil Recovery method).”

Speaker: Stanisław NAGY

Clean Coal Technologies

slide4
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Contents

Organisation of the project with workpackages.

Deliverables/products.

Timetable

Budget

Market analysis

Open issues

slide5
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Organisation of work packages

WP0: Preparation of market analysis and assessment of businessopportunities.(PGNiG, LOTOS, AGH) budget: 11 k€

WP1: Data collection and construction of the static model of the Zalecze &Zuchlow gas field at basin and reservoir scale. (PGNiG, AGH); budget:

105 k€

WP2: Flow simulation and elements of geomechanics. Integrity analysis of the existing wells. (AGH, PGNiG), budget: 245 k€

WP3: Analysis of the possibilities to devise an inland transport of the CO2 to the potential injection zone, injection site infrastructure optimization and the assessment of the productivity. (PGNiG, AGH) budget: 85 k€

5

slide6
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Organisation of work packages

WP4: Construction of geological & numerical model of B3 oil field with history match (AGH), budget: 115 k€

WP5: Analysis of possibilities to increase the recovery factor with the CO2-EOR method (AGH, LOTOS, EDF), budget: 181,4 k€

WP6: CO2 Injection monitoring design (AGH, Lotos), cost: 79 k€

WP7: Feasibility study (LOTOS, AGH), budget: 57 k€

WP8: Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity (Univ. Stavanger, AGH), budget: 760 k€

slide7
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Interdependences between packages

MARKET ANALYSIS

WP1

WP2

WP3

WP4

WP5

WP6

WP7

WP8

slide8
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description- expectations

  • improvement of oil recovery efficiency: recovery of significant amount of oil which arises in a reservoir after finishing the primary & secondary exploitation;
  • minimizing risk of geologic sequestration
  • answering the technical questions necessary for EOR method introduction in the industry: features of the technology is an increase of mobility and change of viscosity
  • Diagnosis of the EOR and EGR processes and their consequences
  • confirmation of logistical solutions of CO2 transportation
slide9
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description – necessary workplan

slide10
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.1 (AGH, PGNiG)

Data collection and construction of the static model of the Zalecze & Zuchlow gas field at basin and reservoir scale

T1.1Data collection and verification of the data quality

T1.2Construction of the static model at basin and reservoir scale

WORKPACKAGE No.2 (AGH, PGNiG)

Flow simulation and elements of geomechanics. Integrity analysis of the existing wells

T2.1Flow simulation and elements of geomechanics

T2.2Integrity analysis of all existing wells

slide11
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.3 (PGNiG, AGH)

Analysis of the possibilities to devise an inland transport of the CO2 to the potential injection zone, injection site infrastructure optimization and the assessment of the productivity

T3.1Elaboration of the most convenient and effective ways of transportation of the CO2

T3.2Injection infrastructure optimization

T3.3 Influence of the miscibility zone appearance on productivity

slide12
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.4 (AGH)

WORKPACKAGE No.5 (AGH, LOTOS, EDF)

Analysis of possibilities to increase the recovery factor with the CO2-EOR method

Construction of geological & numerical model of B3 oil field with history match

T5.1 Analysis of technical state of underground and surface infrastructure

T5.2. Lab analysis with emphasis to sealing of structure after filling it with CO2 (chemical reaction/ long term laboratory work/simulation)

T4.1Data collection and analysis

T4.2Geomechanical analysis of reservoir and caprock strata

T4.3Construction of numerical model of B3 field

slide13
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.5 (AGH, LOTOS, EDF)

WORKPACKAGE No.6 (AGH, LOTOS)

Analysis of possibilities to increase the recovery factor with the CO2-EOR method

New CO2 Injection monitoring design

T6.1Project of passive seismic monitoring

T6.2Optic parameters permanent downhole measuring system

T 6.3 Water surface monitoring system

T5.3Infill drilling opportunities - analysis and new drilling projects

T5.4Short & long Impact of CO2 injection on Sea and Air Environment

slide14
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.7 (AGH, LOTOS)

WORKPACKAGE No.8 (Univ. Stavanger, AGH)

Feasibility study

Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity

T 7.1Standard monitoring of process

T 7.2Analysis of transport opportunity from Lotos Refinary Plant

T 7.3Multivariant final economic analysis

T8.1Methods of tight gas production at the Gro field

A)Use of CO2 injection for the purpose of the fracturing process of the tight gas field

T8.2Carbon dioxide injection as a tool to increase oil/gas production

slide15
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Project description

WORKPACKAGE No.8 (Univ. Stavanger, AGH)

Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity

T8.1Methods of tight gas production at the Gro field

A)Use of CO2 injection for the purpose of the fracturing process of the tight gas field

T8.2Carbon dioxide injection as a tool to increase oil/gas production

B)Comparison of advantages of the usage IOR/IGR vs EOR/EGR

T 8.3 Increase of oil recovery factor by means of natural gas injection at the Skarv field

C) Increase of oil recovery factor by means of CO2 injection at the Skarv field

slide17
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

KIC added value

Innovation

  • the introduction of innovative seismic monitoring system for industry purposes
  • transportation plan
  • site developement plan
  • technology for increased exploitation of oil/gas (monograph, 3 papers)
  • PhD and MSc programms considering recovery methods (1-2 PhD, 3 MSc)

Technology

Education

slide18
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Timing/deliverables

slide20
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Budget - financing

slide23
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Market analysis (WP0) – PGNiG, Lotos

  • Title: Preparation of market analysis and assessment of business opportunities.
  • T0.1. External market analysis.
  • Market analysis: the estimation of the current and future market size will be proceeded. The market capacity, potential demand and absorptivity of the new technology is going to be assessed. The prospective consumers and their motives will be determined, taking under consideration the distribution channels to the recipient.
  • b. Recognition of the competition structure will be performed and the risk evaluated, if new competitors are expected to appear. The value of project competitiveness will be underlined.
slide24
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Market analysis (WP0)

  • Title: Preparation of market analysis and assessment of business opportunities.
  • T0.2. Consortium's internal analysis.
  • Assessment of material and immaterial resources capabilities of the partners partaking in the project (devices, materials, etc.), especially from among immaterial resources the importance of management capacity, institutions, reputation, etc.
  • b. The characteristics of the consortium's opportunities: recognition of strengths and weaknesses, which have an impact on chances of success depending on external circumstances, threats, formal legal issues risk.
  • c. The capabilities and outlook on generating new patents, recovered oil profit, extension of exploitation
  • liveliness by developing new technology.
slide25
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Launching new products in a market

Questions: What- service/product?

Whomay be interestedin?

What for?

How?

mainly energy companies

profit, safety reasons

  • Creation and testing. Implementation for partner’s purpose.
  • Commercialization
  • finding the discriminatory features
slide27
KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy

Thank you for your attention