30 likes | 141 Views
This document outlines the recent infrastructure upgrades and plans at the AIP campus, including history, current projects, and potential future developments. It covers site preparations, GPP master substation bypass, cooling options, and project risks. Stay informed about the campus's engineering advancements.
E N D
Muon Campus AIP ReviewMC Infrastructure Upgrade GPP UpdateRuss AlberFESS EngineeringJanuary 23, 2013
Site Prep GPP History Site Prep GPP (original) - $3.2M • Relocate Kautz Road and gas line - $2.1M • New loop/redundant Feeder 24 - $1.1M Current lab-wide infrastructure upgrades: GPP – Master Substation Bypass SLI - new Master Substation - upgraded ICW upgrade Close Well No.1
“Infrastructure” GPP Candidates • Infrastructure GPP (New) - $?? • Required to run Projects • A-0 Cooling Options: • OPTION 1 Pond Cooling – • Phase 1 - $0.5M (2014) – run g-2 (pumps and piping risk to project) • Phase 2 - $1.0M-$1.5M (2017) – Pump and vault upgrades • OPTION 2 ICW - $?? • OPTION 3 Cooling Towers - $?? • MI-52 Extension - $0.5M (2014) • Possible Project Risks • Parallel Feeder 24 - $1.0M (2016) • New CUB LCW heat exchanger and pumps - ? • Chilled water piping replacement - ? • PBarHVAC (electronic and building cooling) - ?