bus 375 exam 2 latest strayer n.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
BUS 375 EXAM 2 LATEST-STRAYER PowerPoint Presentation
Download Presentation
BUS 375 EXAM 2 LATEST-STRAYER

Loading in 2 Seconds...

play fullscreen
1 / 3

BUS 375 EXAM 2 LATEST-STRAYER - PowerPoint PPT Presentation


  • 0 Views
  • Uploaded on

\nVisit Below Link, To Download This Course:\n\nhttps://www.tutorialsservice.net/product/bus-375-exam-2-latest-strayer/\n\nOr \nEmail us on\nSUPPORT@TUTORIALSSERVICE.NET\n\nBUS 375 Exam 2 Latest-Strayer\nBUS375\nBUS 375 Exam 2 Latest-Strayer\nExam 2\nQuestion 1 Which of the following will correctly calculate the total slack in an activity?\nQuestion 2 Which of the following is provided by both the project network and the work breakdown structure?\nQuestion 3 Which of the following is NOT one of the basic rules to follow when developing project networks?\nQuestion 4 Which of the following is true about hammock activities?\nQuestion 5 Activities which can take place at the same time are termed\nQuestion 6 When translated into a project network, a work package will become\nQuestion 7 If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?\nQuestion 8 The backward pass in project network calculations determines all of the following EXCEPT\nQuestion 9 The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?\n

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'BUS 375 EXAM 2 LATEST-STRAYER' - tutorialsservicesnet


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
bus 375 exam 2 latest strayer

BUS 375 EXAM 2 LATEST-STRAYER

Visit Below Link, To Download This Course:

https://www.tutorialsservice.net/product/bus-375-exam-2-latest-strayer/

Or

Email us on

SUPPORT@TUTORIALSSERVICE.NET

BUS 375 Exam 2 Latest-Strayer

BUS375

BUS 375 Exam 2 Latest-Strayer

Exam 2

Question 1 Which of the following will correctly calculate the total slack in an activity?

Question 2 Which of the following is provided by both the project network and the work breakdown

structure?

Question 3 Which of the following is NOT one of the basic rules to follow when developing project

networks?

Question 4 Which of the following is true about hammock activities?

Question 5 Activities which can take place at the same time are termed

Question 6 When translated into a project network, a work package will become

Question 7 If testing cannot be completed any earlier than four days after the prototype has been built,

what type of lag exists?

Question 8 The backward pass in project network calculations determines all of the following EXCEPT

Question 9 The requirement for a freshly poured foundation to cure before beginning construction is an

example of which of the following type of lag?

Question 10 An activity that has more than one dependency arrow flowing into it is termed a(n)

question 11 if a project has more than

Question 11 If a project has more than one activity that can begin when the project is to start, a common

start node should be used to indicate a clear project beginning on the network. Without a common start

node, each path is a

Question 12 Which of the following represents an activity on an activity-on-node (AON) project network?

Question 13 Laura is forecasting the time and cost of developing an intranet for a new customer. Her

department has completed six such intranets for customers during the last two years. Although the

proposed system is about the same size as the others, she estimates that it will take about 10 percent

less time and money. Which of the following methods is she using?

Question 14 Companies are using which of the following for improving the estimating process for future

projects?

Question 15 Which of the following does NOT help describe a bottom-up estimating approach?

Question 16 Which of the following is NOT one of the recommended guidelines for developing useful

work package estimates?

Question 17 In practice, estimating processes are frequently classified as

Question 18 Typical kinds of costs found in a project include all of the following EXCEPT

Question 19 Refining estimates may be necessary for a number of reasons. For example, a manager

getting further into a project and obtaining a better understanding of what needs to be done to accomplish

a project and meet the needs of the customer is an example of

Question 20 Which of the following would best represent direct project costs?

Question 21 What is the relationship between organizational culture and estimating?

Question 22 Ed is looking over the actual results of projects and comparing them to what was estimated.

He notices that the projects that took six months or longer to complete were noticeably more off the

estimates. Which of the following factors is he recognizing?

Question 23 Sean is forecasting the time and cost of developing a customized software program by

looking at the number of inputs, outputs, inquiries, files, and interfaces. Which of the following methods is

he using?

question 24 refining estimates may be necessary

Question 24 Refining estimates may be necessary for a number of reasons. For example, people

working on prototype development needing time to interact with the design engineers after the design is

completed is a good example of

Question 25 Which of the following is NOT one of the bottom-up approaches to estimating project time

and cost?

Download Now