The LHC sewage infrastructure project encompasses the Outfall Sewer and Force Main construction, with a total cost of $32,236,360. The project includes $26,169,500 for WWTP & IPS, $3,587,605 for Outfall Sewer, and $2,479,255 for Force Main. It aims to achieve Consent Decree compliance by eliminating 13 out of 27 recurring Sanitary Sewer Overflows (SSOs) with a deadline set for January 31, 2013. This initiative not only meets federal and state requirements but also facilitates future growth and addresses community needs through additional projects like South Main and Bel-Air improvements.
Comprehensive Overview of LHC Sewer and Force Main Project Costs and Compliance
E N D
Presentation Transcript
Construction Costs LHC WWTP & IPS = $26,169,500 LHC Outfall Sewer = $ 3,587,605 LHC Force Main = $ 2,479,255 Total = $32,236,360
Consent Decree Compliance • Eliminates 13 of 27 recurring SSOs • Deadline January 31, 2013 • Stipulated Penalties - $500 - $2000/day missed project deadline
Summary • Federal & State compliance • Allows for future growth • Meets the needs of the community
Additional Projects • South Main Sanitary Sewer Improvements • Supplemental Environmental Project (SEP) • Bel-Air Sanitary Sewer Improvements